1995-4394 G Street Address
Category Serial #
y39 �
Name Description
Plan ck. # Year
K&S ENGINEERING
Planning Engineering Surveying
HYDROLOGICAL ANALYSIS
FOR
Wildflower Estates
Lots 26, 28 and 29
IN
CITY OF Encinitas
JN 9526 JUL 2 5 19 5
Jul 23 1995
Y � y..
Na 48592
Exp. 6 -30 -96 *
5. ;W<I RE. 48592
* �� CiVl4. �4 DA
P� OF CAti��`
78 Mission Center Court, Suite 200 -San Diegb, Cdifornia 921 - (619)296 -5565 • Fax (619)296 -5564
I
TABLE OF CONTENTS
1.SITE DESCRIPTION
2.HYDROLOGY DESIGN MODELS
3.HYDROLOGIC CALCULATIONS .......................... APPENDIX A
4.HYDROLOGY MAPS .... ............................... APPENDIX B
5.TABLES AND CHARTS . ............................... APPENDIX C
I,
1.SITE DESCRIPTION
THE OFF SITE DRAINAGE AREA CONSISTS OF GENTLY ROLLING TERRAIN.
WATER SHEET FLOWS SOUTHWESTERLY TOWARD THE NORTHERLY PROPERTY LINE
OF LOTS 27, 28 AND 29 WHERE A 24" BROW DITCH SYSTEM INTERCEPTS THE
WATER RUNOFF.
THE OFF SITE AND THE ON SITE DRAINAGE OF LOTS 28 AND 29 IS DIRECTED
TOWARD VIOLET RIDGE AND THEN ALONG THE STREET GUTTER TOWARD THE
EXISTING STREET LOW POINT, THEN INTO A BROW DITCH ALONG LOT 27
SOUTHERLY LOT LINE, THEN DISSIPATES VIA RIPRAP.
i
2. HYDROLOGY DESIGN MODELS
A. DESIGN METHODS
THE RATIONAL METHOD IS USED IN THIS HYDROLOGY STUDY; THE RATIONAL
FORMULA IS AS FOLLOWS:
Q = CIA, WHERE : Q= PEAK DISCHARGE IN CUBIC FEET /SECOND
C = RUNOFF COEFFICIENT (DIMENSIONLESS)
I = RAINFALL INTENSITY IN INCHES /HOUR
A = TRIBUTARY DRAINAGE AREA IN ACRES
*1 ACRE INCHES /HOUR = 1.008 CUBIC FEET /SEC
THE OVERLAND FLOW METHOD IS ALSO USED IN THIS HYDROLOGY STUDY; THE
OVERLAND FLOW FORMULA IS AS FOLLOWS:
T =(1.8 (1.1 —C) (L) -1] / ( S %) 113
C = RUNOFF COEFFICIENT
L = OVERLAND TRAVEL DISTANCE IN FEET
S = SLOPE IN PERCENT
T TIME IN MINUTES
B. DESIGN CRITERIA
— FREQUENCY, 100 YEAR STORM.
— LAND USE PER SPECIFIC PLAN AND TENTATIVE MAP.
— RAIN FALL INTENSITY PER COUNTY OF SAN DIEGO 1993 HYDROLOGY
DESIGN MANUAL.
C. REFERENCES
— COUNTY OF SAN DIEGO 1993, HYDROLOGY MANUAL.
— COUNTY OF SAN DIEGO 1992 REGIONAL STANDARD DRAWING.
— HAND BOOK OF HYDRAULICS BY BRATER & KING, SIXTH EDITION.
APPENDIX A
(3. HYDROLOGIC CALCULATIONS)
SAN DIEGO COUNTY
RATIONAL - HYDROLOGY
Rational Hydrology Study Date: 7 -23 -1995
- -- ------------------------------------------------------------------------
USER SPECIFIED HYDROLOGY INFORMATION*
- -- ------------------------------------------------------------------------
Rational method hydrology program based on
San Diego County Flood Control Division
1985 Hydrology Manual
4torm Event(Year) = 100.00
ap data precipitation entered:
HOUR, Precipitation(Inches) = 2.700
4 Hour Precipitation(Inches) = 4.500
Adjusted 6 Hour Precipitation (Inches) = 2.700
1 = 60.0 %
San Diego Hydrology Manual "C" Values Used
Runoff Coefficients by RATIONAL METHOD
Process from Point/Station 1.000 to Point/Station 2.000
* * * INITIAL AREA EVALUATION
Decimal Fraction Soil Group A = .000
Decimal Fraction Soil Group B = .000
Decimal Fraction Soil Group C = .000
Decimal Fraction Soil Group D = 1.000
SINGLE FAMILY runoff coefficient = .5500
Area Type is: SINGLE FAMILY
ime of concentration computed by the Natural
'Watersheds nomograph, (App. X -A)
C = [11.9 *Length(Mi) ^3) /(Elevation Change)] ^.385 *60(MIN /HR)
+ 10 min.
nitial Subarea Flow Dist. = 150.00
ighest Elevation = 277.70
owest Elevation = 260.00
levation Difference = 17.70
C = [(11.9* .0284 * *3) /( 17.70)]* *..385 = .842
+ 10 Min. = 10.842 Min.
100.00 Year Rainfall Intensity (In./Hr.) = 4.318
Subarea(Acres) _ .05 Subarea Runoff(CFS) _ .12
otal Area(Acres) _ .05 Total Runoff(CFS) _ .12
C(MIN) = 10.84
+++++ ++ I I I I I I + + + +++++ +++++++++ + ++++++ I I I I I I I I I I i i i i +++++ + + + + +++
rocess from Point/Station 2.000 to Point/Station 3.000
* * * PIPEFLOW TIME (USER SPECIFIED SIZE)
pstream point elevation = 260.00
ownstream point elevation = 214.00
low length(Ft.) = 360.00 Mannings N = .015
o. of pipes = 1 Required pipe flow (CFS) _ .12
iven pipe size (In.) = 24.00
alculated Individual Pipe flow (CFS) _ .12
ormal flow depth in pipe = .74 (In.)
low top width inside pipe = 8.29 (In.)
Velocity = 4.170 (Ft/S)
ravel time (Min.) = 1.44 TC(min.) = 12.28
+ +++++++++++++++++ ++ +++ + + +++ + ++++++ + + + + + + + + + + + +++
Process from Point/Station 2.000 to Point/Station 3.000
* * * SUBAREA FLOW ADDITION s * s
100.00 Year Rainfall Intensity(In./Hr.) = 3.984
Decimal Fraction Soil Group A = .000
Decimal Fraction Soil Group B = .000
ecimal Fraction Soil Group C = .000
Decimal Fraction Soil Group D = 1.000
INGLE FAMILY runoff coefficient = .5500
ubarea(Acres) _ .90 Subarea Runoff(CFS) = 1.97
otal Area(Acres) _ .95 Total Runoff(CFS) = 2.09
C(MIN) = 12.28
+ + + ++
Process from Point/Station 2.000 to Point/Station 3.000
* * * CONFLUENCE OF MAIN STREAMS
---------------------------------------------------------------------------
OLLOWING DATA INSIDE MAIN STREAM ARE CALCULATED
100.00 Year Rainfall Intensity (In./Hr.) = 3.984
he flow values used for the stream: 1 are:
ime of concentration(min.) = 12.28
Rainfall intensity (in./hr/) = 3.98
otal flow area (Acres) _ .95
Total runoff (CFS) at confluence point = 2.09
Program is now starting with MAIN STREAM NO. 2
++++++++++++++++++ +++++ + + + + + + + + + + ++++ + + + +++ + + + + ++
Process from Point/Station 4.000 to Point/Station 5.000
* * * INITIAL AREA EVALUATION
ecimal Fraction Soil Group A = .000
ecimal Fraction Soil Group B = .000
ecimal Fraction Soil Group C = .000
ecimal Fraction Soil Group D = 1.000
INGLE FAMILY runoff coefficient = .5500
ea Type is: SINGLE FAMILY
rime of concentration computed by the Natural
Watersheds nomograph, (App. X -A)
C = [11.9 *Length(Mi) ^3) /(Elevation Change)] ^.385 *60(MIN /HR)
+ 10 min.
nitial Subarea Flow Dist. = 190.00
ighest Elevation = 250.00
owest Elevation = 249.00
Elevation Difference = 1.00
C = [(11.9* .0360 * *3) /( 1.00)J* *..385 = 3.346
+ 10 Min. = 13.346 Min.
100.00 Year Rainfall Intensity (In./Hr.) = 3.776
Subarea(Acres) _ .70 Subarea Runoff(CFS) = 1.45
otal Area(Acres) _ .70 Total Runoff(CFS) = 1.45
C(mw) = 13.35
++++++++++++++ +++ ++++ + + + + ++++++++++ ++++ + +++++ ++ + +++ + + + + + + ++
rocess from Point/Station 5.000 to Point/Station 6.000
* * * TRAPEZOIDAL/RECT. CHANNEL TRAVEL TIME
pstream point elevation = 249.00
Downstream point elevation = 228.00
Channel length thru subarea(Feet) = 45.00
Channel base(Feet) = 4.00
Slope or "Z" of left channel bank = .000
Slope or "Z" of right channel bank = .000
annings "N" _ .012 Maximum depth of channel (Ft.) _ .50
Flow(Q) thru subarea(CFS) = 1.45
Upstream point elevation = 249.00
Downstream point elevation = 228.00
low length(Ft.) = 45.00
ravel time (Min.) _ .08 TC(min.) = 13.43
Depth of ow = t.
Average Velocity = 9.49 (Ft. /Sec.)
hannel flow top width = 4.00 (Ft.)
Process from Point/Station 5.000 to Point/Station 6.000
* * * CONFLUENCE OF MAIN STREAMS
** Compute Various Confluenced Flow Values * **
---------------------------------------------------------------------------
OLLOWING DATA INSIDE MAIN STREAM ARE CALCULATED
100.00 Year Rainfall Intensity (In./Hr.) = 3.762
The flow values used for the stream: 2 are:
ime of concentration(min.) = 13.43
Rainfall intensity (in./hr/) = 3.76
otal flow area (Acres) _ .70
otal runoff (CFS) at confluence point = 1.45
onfluence information:
Stream runoff Time Intensity
Number (CFS) (min.) (inch/hour)
---------------------------------------------------------------------------
1 2.09 12.28 3.984
2 1.45 13.43 3.762
SMX(1) _
1.000* 1.000* 2.1)
1.000* .915' 1.5)
3.421
SMX(2) _
944* 1.000* 2.1)
1.000* 1.000* 1.5)
3.428
Rainfall intensity and time of concentration
sed for 2 MAIN streams.
ndividual stream flow values are:
2.09 1.45
ossible confluenced flow values are:
3.42 3.43
ndividual Stream Area values are:
.95 .70
---------------------------------------------------------------------------
omputed confluence estimates are:
Runoff(CFS) = 3.43 Time(min.) = 13.425
Total main stream study area (Acres) = 1.65
I
+++++++++++++++++++++++++++++++++++++++ ++++++ + + ++++ + +++++. + + + + + +++ + + ++
rocess from Point/Station 3.000 to Point/Station 15.000
* * * STREET FLOW TRAVEL TIME
Upstream point elevation = 214.00
Downstream point elevation = 213.00
Street length thru subarea(Feet) = 70.00
annings "N" _ .015 Maximum depth of channel (Ft.) _ .50
Flow(Q) thru subarea(CFS) = 3.43
Flow length(Ft.) = 70.00
Travel time (Min.) _ .43 TC(min.) = 13.85
Depth of flow = .22 (Ft.)
Average Velocity = 2.72 (Ft. /Sec.)
treetl flow top width = 11.33 (Ft.)
+++++ + + + ++
Process from Point/Station 3.000 to Point/Station 15.000
* * * SUBAREA FLOW ADDITION
100.00 Year Rainfall Intensity (In./Hr.) = 3.687
Decimal Fraction Soil Group A = .000
Decimal Fraction Soil Group B = .000
Decimal Fraction Soil Group C = .000
Decimal Fraction Soil Group D = 1.000
SINGLE FAMILY runoff coefficient = .5500
Subarea(Acres) = 1.43 Subarea Runoff(CFS) = 2.90
otal Area(Acres) = 3.08 Total Runoff(CFS) = 6.33
C(MIN) = 13.85
++ ++++ + ++ ++
Process from Point/Station 15.000 to Point/Station 7.000
* * * PIPEFLOW TIME (USER SPECIFIED SIZE)
pstream point elevation = 213.00
ownstream point elevation = 198.00
low length(Ft.) = 180.00 Mannings N = .015
o. of pipes = 1 Required pipe flow (CFS) = 6.33
iven pipe size (In.) = 24.00
alculated Individual Pipe flow (CFS) = 6.33
ormal flow depth in pipe = 5.42 (In.)
low top width inside pipe = 20.07 (In.)
Velocity = 11.903 (Ft/S)
ravel time (Min.) _ .25 TC(min.) = 14.11
+++++++++ ++++++++++++++++ ++++++++ +++ + +++ +++ + + + + ++
Process from Point/Station 15.000 to Point/Station 7.000
* * * SUBAREA FLOW ADDITION
100.00 Year Rainfall Intensity(In./Hr.) = 3.644
ecimal Fraction Soil Group A = .000
ecimal Fraction Soil Group B = .000
ecimal Fraction Soil Group C = .000
ecimal Fraction Soil Group D = 1.000
INGLE FAMILY runoff coefficient = .5500
Subarea(Acres) _ .40 Subarea Runoff(CFS) _ .80
otal Area(Acres) = 3.48 Total Runoff(CFS) = 7.13
Cmm = 14.11
I
++++ +++++++++++++++++++ + + +++++++++ +++ ++++++++ + + + + + + +++
Process from Point/Station 12.000 to Point/Station 13.000
* ** INITIAL AREA EVALUATION * **
Decimal Fraction Soil Group A = .000
Decimal Fraction Soil Group B = .000
Decimal Fraction Soil Group C = .000
Decimal Fraction Soil Group D = 1.000
SINGLE FAMILY runoff coefficient = .5500
ea Type is: SINGLE FAMILY
ime of concentration computed by the Natural
atersheds nomograph, (App. X -A)
C = [11.9 *Length(Mi) ^3) /(Elevation Change)] ^.385 *60(MIN /HR) + 10 min.
Initial Subarea Flow Dist. = 140.00
Highest Elevation = 201.00
Lowest Elevation = 200.00
Elevation Difference = 1.00
C = [(11.9* .0265 * *3) /( 1.00)]* *..385 = 2.352
+ 10 Min. = 12.352 Min.
100.00 Year Rainfall Intensity(In./Hr.) = 3.970
Subarea(Acres) _ .70 Subarea Runoff(CFS) = 1.53
otal Area(Acres) _ .70 Total Runoff(CFS) = 1.53
12.35
Process from Point/Station 13.000 to Point/Station 14.000
* * * TRAPEZOIDAL/RECT. CHANNEL TRAVEL TIME
pstream point elevation = 200.00
ownstream point elevation = 173.00
hannel length thru subarea(Feet) = 45.00
hannel base(Feet) = 4.00
lope or "Z" of left channel bank = .000
lope or "Z" of right channel bank = .000
annings "N" _ .012 Maximum depth of channel (Ft.) _ .50
low(t) thru subarea(CFS) = 1.53
pstream point elevation = 200.00
ownstream point elevation = 173.00
low length(Ft.) = 45.00
ravel time (Min.) _ .07 TC(min.) = 12.42
epth of flow = .04 (Ft.)
verage Velocity = 10.44 (Ft. /Sec.)
hannel flow top width = 4.00 (Ft.)
rocess from Point/Station 9.000 to Point/Station 10.000
* ** INITIAL AREA EVALUATION "*
ecimal Fraction Soil Group A = .000
ecimal Fraction Soil Group B = .000
ecimal Fraction Soil Group C = .000
ecimal Fraction Soil Group D = 1.000
INGLE FAMILY runoff coefficient = .5500
ea Type is: SINGLE FAMILY
ime of concentration computed by the Natural
Watersheds nomograph, (App. X -A)
C = [11.9 *Length(Mi) ^3) /(Elevation Change)] ^.385 *60(MIN /HR) + 10 min.
nitial Subarea Flow Dist. = 160.00
ighest Elevation = 245.00
owest Elevation = 244.00
Elevation Difference = 1.00
C = [(11.9* .0303 * *3) /( 1.00)]* *..385 = 2.744 + 10 Min. = 12.744 Min.
100.00 Year Rainfall Intensity(In./Hr.) = 3.891
Subarea(Acres) _ .60 Subarea Runoff(CFS) = 1.28
Total Area(Acres) _ .60 Total Runoff(CFS) = 1.28 TC(MIN) = 12.74
++ + + + + + + +++ + ++++ + + +++ + + ++ + + + + + + + ++
rocess from Point/Station 10.000 to Point/Station 11.000
* * * TRAPEZOIDAL/RECT. CHANNEL TRAVEL TIME
pstream point elevation = 244.00
Downstream point elevation = 229.50
Channel length thru subarea(Feet) = 80.00
Channel base(Feet) = 4.00
Slope or "Z" of left channel bank = .000
Slope or "Z" of right channel bank = .000
annings "N" _ .012 Maximum depth of channel (Ft.) _ .50
Flow(Q) thru subarea(CFS) = 1.28
Upstream point elevation = 244.00
Downstream point elevation = 229.50
Flow length(Ft.) = 80.00
ravel time (Min.) _ .20 TC(min.) = 12.94
Depth of flow = .05 (Ft.)
Average Velocity = 6.79 (Ft. /Sec.)
Channel flow top width = 4.00 (Ft.)
End of computations.. ,
TOTAL STUDY AREA(ACRES) = 4.78
I
+ + + +++++ +++++ + + ++++ + +++ + + + + + + ++
rocess from Point/Station 1.000 to Point/Station 16.000
* ** INITIAL AREA EVALUATION * **
Decimal Fraction Soil Group A = .000
Decimal Fraction Soil Group B = .000
Decimal Fraction Soil Group C = .000
Decimal Fraction Soil Group D = 1.000
INGLE FAMILY runoff coefficient = .5500
Area Type is: SINGLE FAMILY
ime of concentration computed by the Natural
Watersheds nomograph, (App. X -A)
C = [11.9 *Length(Mi) ^3) /(Elevation Change)] ^.385 *60(MIN /HR)
10 min.
nitial Subarea Flow Dist. = 320.00
ighest Elevation = 277.70
owest Elevation = 245.00
levation Difference = 32.70
C = [(11.9* .0606 * *3) /( 32.70)]* *..385 = 1.596
+ 10 Min. = 11.596 Min.
100.00 Year Rainfall Intensity(In./Hr.) = 4.135
Subarea(Acres) _ .30 Subarea Runoff(CFS) _ .68
Total Area(Acres) _ .30 Total Runoff(CFS) _ .68
C(K41N) = 11.60
End of computations.. ,
OTAL STUDY AREA(ACRES) = 5.08
BROW DITCH FLOW CALCULATIONS * * * * **
* * * * * NON - PRESSURE, OPEN CHANNEL CALCULATIONS
ALCULATE DEPTH OF FLOW GIVEN:
row ditch Slope = - .095833 (Ft./Ft.) _ - 9.5833 %
ength of brow ditch = 240.000 (Ft.)
iven Flow Rate = .68 Cubic Feet/Second
** *BROW DITCH OPEN CHANNEL FLOW * **
annings "n" _ .012
Velocity (Ft. /Sec.) = 7.50
iven brow ditch Diameter(In.) = 24.00
row ditch flow = .6800 (CFS)
ormal flow depth in brow ditch = 1.61 (In.)
low top width inside brow ditch = 12.00 (In.)
ea of flow = 13.0528 (In2)
Wetted Perimeter = 12.57 (In.)
ritical Depth in brow ditch = 3.39 (In.)
Total flow of brow ditch(s) _ .6800 (CFS)
APPENDIX B
(4. HYDROLOGY MAP)
APPENDIX C
(5. TABLES AND CHARTS)
Z7 �• C I O 4- i
C
0"" in
^b-2
O ai 1..1
• C �1 a L 40 A 1 L K
L ILI A u r 7 C
t 3 7 vi da u
C' ?1 r N 4A r is r-•
L C C u 1!i L •� b p
W v - O r ai In r C cr. a
C O C� f- A 4j �O N •r
N C V - 4- p .� L 49 � 4-1 < ►
4j a A r Q 4-+ 4.+ 7 • w l
i� v v L a
.00)C L 3 _ccC O 13 � N
•
N N r A 4J S. 0 O a In r
C a s 'O O 00 r •r t C A
O L W O 4•0 a " 4+ 4+ a C a
r 4j 4J r a r t A A 4•j A a • L r
4j C i a 4J 41 41 Z C st C t
A C i r ce O r r I r O r C► :
N r \ A
u O O L CIO u C a C C u 06 E C u
•r r
4- K a air r r p a r C r r
r 41 C 10 CL u L L u u L C a a •• r -
a
t0. A '4 a C O C 4+ d a t .+ O • d
CL 4.+ 4 L 16. i s- r T- L 4j N Cr C N m
••- 2 d 4
a .b ai N C a r ID Q
d 7 w i L a/ C r O E L C.
L rONOT! t4A ^ A Cr r O La..
O u E Me- C r L 4J L L r r a 41 U- O
V - a A /C v r0
so .0 L t o r C A •fl z
f. E 4j a - O r u C a a t
N Q • r C 4.r r qr a to a l o w r O O 41 +
C L d A QI N N a t 4J r r u ar
o E s 4n ++ O 4.i .0 r. .0 a
r p a C In • - a gO 0 n A O — A r
4� LRL /0 a M== o r- %- S- 0-- tt u a u
u LL. N h- .!- G C 4•+ 4J 4J C- O G a i-- 4+ r N d Q 4J
a �
i CL
t2 O r N In A In a O r N en
C
Z 6 -Hour Precipitation (inches)
o In o In o In o In o In o
%C IR111 Qd• !•'1 N N r r
- _�- -- .-
CW
0. 14 Q •� •� :SI' / - - -' -r '1' 11
v - -
v • i , - _ — _ __- _— - - __ _ _ -
.. «, a ca - — —
Cr
o (.1 •1 7 "_1. — 'fir: _ ":'I� ',1� _
�' APPEEiAI XI IY -
CM
CD
CD CD
.d... gym. L IN
Ln
La
CA OU
V t / cc •
CLO
CD ca Cl? - _ ` - z N N
= LW u
�a1 N
P _ noes : "�i�1 i fir' r
4c 0 Z t
CD 0 Y
k
<
I L A b • tC=
t p <
<z
C) u>
.. V M J
n paw -
LAJ
O f
Z L6
Cc m
O w O
�FE
C g '' o
r JAM /• j � `; . . `,� � � � _�i � 'V
r O
LM
O V I —� v ;• c
.....
Z Lo
LO
cn
Cm co
L �
cli
dOW
R
Cm --
h /ot;r
1 ry ca
co
t�
J O
v t-
b s C
2 C i<
u a:
O U =�
m
<<
y r
co
� � y
U J
Y
O O a
cc: u +.
tit o 0
Z s r� •- s G 3 �'+
H v
1 9
/ d 0 �• o
W ..d 1• W
D 4. = O
M
M
Y
' r
• . • ■E ■M■■■ ■ ■ ■ ■■ ■■ 1 IM 1 I I/ 11.
■.■M........0 == _►.� ►CCC��CC�� ■CSC ►ICI.CCCC =CSC..
■■■■■■■■■■■.■. rl■ ■ ■.■r . I
.,■ . ■ ■ ■ ■ /� ■■
■■■■■■■ ■■ ■E ■ It ■I■ ■FAI Cl/A ■■ ■ ■ ■�� ■■
■M■■■ ■■CNO■E V CE ■C. ■II ■M'.M /I ■ ■ ■OMMME
■M■■ ■■MMME■ Et.■■■l ■V■/,■.� ■ENE IA■■ ■U ■AM
■E■■CCMA■■■ =M r. ■ / ► ■. ■'I ■. ■ ■I/A1l ■ ■I / ■. ■. ■■I,M■■■
■
MEMO■■.■■■ ■ r1Erl■■ ■ ■■
■■■•■■■■■■■■■ ■IA■ ■II■■IAMIMI,MMII■ /.■ASE.MMM■■
• • ■■ ■E■■ ■EE■ ■. b ■■■r�■ r1■ ■� /I■ ■. ■ ■// ■ ■ ■.■
■■■■■■■■■■■. ■ u r, ■ =I� ■■M� ■ ■■ ■V■MMM
=
EMME■■E ■■MME MEAN am I .. /,.. ►I�■.► �AOO /I ■ ■ ■M ■■
ME■MMEEMMM■ Erl■u■ UM.AM ■■I.■ ■M■MM
. ■
■■MSE■ SAME • ■■ ■■■.OIISI� %■■MIME■■ ■■■
■■ ■■■■M■■■ Or.Erl ■ ■r, ■E /SII I a �■■ II■■■■■■AM
E■■EO■■■ ■E OII■IIE ■I/ ■I�EE'II� ■ ►� • �■ •,�.■■ ■MM ■■
■■ ■ EEE ■ ■ ■EMEM ■VAMAMMAMFA ■I,MU ■ /,■ ■■ /.■M■■■■■■
■■■■■■■■■■■ E■■ 1. ■ ■I■. .■ ■■■■■■■
■■■■■■■ ■■■■EO..■rl■■N ■IJMNM" ■I,M ■Ii■ ■■ / ■O■■ ■■■■■■
... ■ ■■ ■■ ■■■.■■■■rl■rIE■' /■TAMIL/ ■►I ■I /OOA►I ■ ■ ■ ■. ■M■ ■EE :.
MMMMM MEMM a��i��C Mumm AmunramCC iMMENUMiiiii
■■■ ■M■■■M ■ ■ ■/MHMMA.. ■F.IA ■I /.U■■MENMM■■■ ■EA ■I %M
■MMM ■ ■MOMMMMI1MWOMMEM WMAMUEI ■E ■I %■■. ■M ■S■ ■Ld■■
■OMM■■■MM ■ ■MIAWMhf lM'IM►IIjM /,M■U ■M/I ■■■■MOMMVAMMMr►
■M ■M ■M ■ ■ ■ ■ME./I ■■I II /M'AMUMAM ■ ■I■■MMMMBEi ■SS►%
■■ M■ ■ ■MMM■ ■/,MwMMll"M"KMI, ■MMUM■■VAM■ •
ME■■ M■ M■ MMMFIEM■FIIr /I.M'IM' / ■ /I ■MMU ■ ■■ ■ /%SM /iA ■■
• • ■OMMM ■MMMMM III /M /Mrl■IIIAMIA ■I.MMM /jM ■M■ I.A ■ ■IAMMMR
■■■EEE■■■■..w■II ■ill. %IEAMWMMIM • .M ■M ►M■■MFA/
■ O■ M ■ M ■M■MWMMIIirg11I/M1A ■Ii■■EI■■■ Ei ■E■p%■■
MM ■ MMMMMM ■N"MMM' /lf,/A /AI, /MMU ■M■ • /M■■9dM ■■ •
■ ■ES ■ ■MOMEAMIN INUF / ■UE % ■ on / /iA ■ ■I%
dmmrnmm
■ ■ ■M ■■MMM"UNIU/, ■ %!1/ /I.MO ■ I %M ■M .I ■/% i ■C / ■ ■■
■■ M ■■ ■ ■■E/.I,.UnEINI1 ■/%■MMM6M■ /a■ ` lMMMMM
■ ■ ■ ■■■■■mmE►/I, / /iliM' / ■M %MMMM &moo No im ■■E ■,�l
E■■■ SA■■ IIU I.�I�/UI.IIIi ■MI ■ ■SE %E��A ■F % ■ ■. ■ % ■ /iA■
.. EMMM■■ E/ EU /iI. /i /A1:M■I■■MP%MI.d ■O m.I_% 2E ■E■
=A■ SSA ■I / /II.E' /' /, /II.�IEI ■MAR % ■AAA► %MITES E/M •
■OEEEEIJIM.I�� / % /I /:1 ■■ ■GAR % ■I. % ■�L ■ ■ ■ /i� • iENE■
• E.■ E■■'/./. / %gilt! %R %11■ ■� ■/MOB /EI ■■ ■ICE ■■ % ■■
■ ■ ■E ■1 / % %� /. / /I, /�MEII ■% ■TER % ■ / % ■ ■ /�i ■ ■��" ■ • �� •
■ ■ASI. % %�.� %: /.%EA ■1! %R %ECM /i ■ ■ /iM ■ ■RiAM�■ ` .I■■
■ EMI. U % iii / %: ■ ■ME /.•1 ►.�� /o�■ ■ /� /EEC�E ■ ■M
MAEME ■
um
■■ MOO■ ■MM ■ / %nRLn % /zd.ni ■ ■ME:■MMMM ■OM ■ ■M ■M■
■ M■■ MM■ ■R % %G /.L /i/IM /■ ■ /_i ■ ■ ■ ■ ■■!i/ ■ ■■ ■ ■rte•'
■ M■ M■■ Mn i /. /. %n %R %MMii ■M■:z ■ ■ ■AM ■ ■AE/ ■
AAA■ AE%%%%%%/ �� ■ ■!�i /SA. ■_AME•!i� ■ASi■■!���.
■
Nor A/';% i! /• ■■M ■ ■ ■ ■ l mmmmmmm
■■■■■■■ mmmmumm
TABLE 2
RUNOFF COEFFICIENTS (RATIONAL METHOD)
DEVELOPED AREAS (_ U
Coeffi C
Soil Group (1)
Land Use
A B C D
Residential:
Single Family .4o .45 .50 .55
Multi -Units .45 .50 .60 .70
Mobile homes .45 .50 .55 .65
Rural (lots greater than 1/2 acre) .30 .35 .40 .45
Commercial ( . .15 .80 .85
80% Impervious
Industrial( . .85 .90 .95
90% Impervious
NOTES:
(]) Soil Group mans are available at the offices of the Department of Public Works.
( actual conditions deviate significantly from the tabulated impervious-
ness values of 80% or 90%, the values given for coefficient C. may be revised
by multiplying 80% or 90% by the ratio of actual imperviousness to the
tabulated imperviousness. However, in no case shall the final coefficient
be less than'0.50. For example: Consider commercial property on D soil.group.
Actual imperviousness - 50%
Tabulated imperviousness - 80%
Revised C 80 x 0.85 ' 0.53
IV -A -9
' APPENDIX IX -8
,<. : Rev. 5/81
Average Values of Roughness Coefficient (Manning's n)
Roughness
Type of Waterway Coefficient (n)
1. Closed Conduits (1)
Steel (not lined) 0.015
Cast Iron 0.015
Aluminum .021
Corrugated Metal (not lined) 0.024
Corrugated Metal (2) (smooth asphalt quarterlining) 0.021
Corrugated Metal (2) (smooth asphalt half lining) 0.018
Corrugated Metal (smooth asphalt full lining) 0.012
Concrete RCP 0.012
Clay (sewer) 0.013
Asbestos Cement Pvc-- 0.011
Drain Tile (terra cotta) 0.015
Cast -in -place Pipe 0.015
Reinforced Concrete Box 0.014
2. Open Channels (1)
a. Unlined
Clay Loam 0.023
Sand 0.020
b. Revetted
Gravel 0.030
Rock 0.040
Pipe and Wire - 0.025
Sacked Concrete 0.025
c. Lined
Collcrote (poured) 0.014
Air,Blown Mortar (3) 0.016
Asphaltic Concrete or Bituminous Plant Mix 0.018
d. Vegetated (5)
Grass lined, maintained - .035
Grass and Weeds .045
Grass lined with concrete low flow channel .032
3. Pavement and Gutters (1)
Concrete
0.015
Bituminous (plant- mixed) 0.016
APPENDIX XVI A
/d EQLIAT /ON
Feef Tc
5000 Tc ■ Tune O/ concen11=110n
t 0000 Lenglh of wales -shed
�H • D /t�enence in e%va lion a/av�g
?000 eliechme S/OOC / /ne (.ee 4WAdiX X T
L c
�bli /es
- e,,4 //ours Mina/es
1000 4 200
3 /BD
/O
/ODD
900
g0D 1 /20
700 /DO
ioo \\ s 90
S00 \ 80
000 \�"►� 0 70
/ 60
300
\ SD
200 \ \ 1 00
\ \ 30
/OD / SD OD
4QD0 20
IO 2000 \ \ 12
30 NOTE
/a00 9
FOR NATURAL WATERSIC-DS � /200 B
20 M ADD TEN MINUTES TO 9 oO0 7
r MPUTED TIME OF CON NTRATION- 800 6
� : z 100
600 S
/40 500 ¢
000
301 3
5 -
200
C H r
SAN DIEGO COUNTY NOMOGRAPH FOR DETERMINATION
_ DEPARTMENT OF SPECIAL DISTRICT SERVICES OF TIME OF CONCENTRATION (TC)
-y_
DESIGN MANUAL FOR NATURAL WATERSHEDS
l ir - A _1n pov c
i
Wa D /•V/do
. N
L
Wa�e�sfied '
Divide '
y
f
AteQ .9"
Arta B"
H Desl Pvinf
f�'1ccf Slope Line �`Yafersfie0� Duf lG�)
.SfIEO/n /�rOl /IC
L
Arta A" - Area-
SAN DIEGO COUNTY COMPUTATION OF EFFECTIVE SLOPE
T - DEPARTMENT OF SPECIAL DISTRICT SERVICES FOR NATURAL WATERSHEDS
__.
: DESIGN .MANUAL,
>, AP�ROVED , .rt DATE APPENDIX X- F
i Id A
NORTH COUNTY
COMPACTION
ENGINEERING, INC.
December 4, 1995
Project No. CE -5086
Mr. & Mrs. Bret Heers
3442 Fortuna Ranch Road
Encinitas, CA
Subject:. Report of Certification of Compacted Fill Ground
Propo d Heers Residence
Lot 28 Wildflower Estates
Encin tas, California
Dear Mr. & Mrs. Heers:
In response to your request, the following report has been prepared
to indicate results of soil testing, observations and inspection of
earthwork construction at the subject site.
Testing and inspection services were performed from November 1,
1995 through November 27, 1995.
Briefly, our findings reveal filled ground has been compacted to a
minimum of ninety percent (90 %). Therefore, we recommend
construction continue as scheduled.
SCOPE
Our firm was retained to observe grading operations with regard to
current standard practices and to determine the degree of
compaction of placed fill.
Grading plans were prepared by K & S Engineering, dated September
12, 1995.
Grading operations were performed by Greg Whilock of Vista,
California.
Reference is made to our previously submitted report entitled,
"Preliminary Soils Investigation ", dated October 23, 1994.
Approximate locations and depth of filled ground and extent of
earthwork construction covered in this report are indicated on the
attached Plate No. One entitled, "Test Location Sketch ".
Grading operations were performed in order to create a level
building pad to accommodate the proposed single family dwelling.
Should the finished pad be altered in any way, we should be
contacted to provide additional recommendations.
P.O. BOX 302002 • ESCONDIDO, CA 92030
(619) 480 -1116
NORTH COUNTY
COMPACTION
ENGINEERING, INC.
December 4, 1995
Project No. CE -5086
Page 2
The site was graded in accordance with recommendations set forth in
our previously submitted report.
The site was graded to approximately conform to project plans.
Actual pad size and elevation may differ. Finish grade operations
are to be completed at a later date.
LABORATORY TESTING
Representative soil samples were collected and returned to the
laboratory for testing. The following tests were performed and are
tabulated on the attached Plate No. Three.
1. Optimum Moisture /Maximum D6hsity (A.,TM D -1557)
2. Expansion Potential Test
3. Direct Shear
SOIL CONDITIONS
Native soils encountered were clayey- sands, clayey- gravels, and fat
clays. Fill soils were generated from the on -site excavation.
The building site contained a transition from cut to fill.
However, cut areas located within the building area were over
excavated a minimum of 3 feet and brought to grade with compacted
soil. Over excavation was carried a minimum of 5 feet beyond
exterior building perimeter. Hence, no consideration need be given
this characteristic.
Oversize material consisting of rock and boulders was left above
ground as landscape material. Oversize material. is defined as rock
and boulders in excess of 12 inches in size. It should not be
placed in structural fills. It may be placed in nonstructural
fills designated and supervised by North County COMPACTION
ENGINEERING, INC.
Expansive soils were observed during grading and exist at finish
grade. These soils were found to have an expansion index of 52 and
are classified as being moderate in expansion potential. It is our
understanding a post tension foundation system is planned to
compensate for this condition.
The key was approximately 15'feet wide, a minimum of 2 feet in
depth and inclined into the slope. During earthwork construction,
native areas to receive fill were scarafied, watered and compacted
NORTH COUNTY
COMPACTION
ENGINEERING, INC.
December 4, 1995
Project No. CE -5086
Page 3
to a minimum of ninety percent (90 %) of maximum density. Subsequent
fill soils were placed, watered and 'compacted in 6 inch lifts.
Benches were constructed in natural ground at intermediate levels
to properly support the fill. To determine the degree of
compaction, field density tests were performed in accordance with
ASTM D -1556 or D -2922 at the approximate horizontal locations
designated on the attached Plate No. One entitled, "Test Location
Sketch ". A tabulation of test results,',4nd their vertical locations
are presented on the attached Plate No.`�'Two entitled, "Tabulation of
Test Results ". Fill soils found to have ',a relative compaction of
less than ninety percent (90 %) were reworked until proper
compaction was achieved.
RECOMME nATIONS AND CONCLUZIUK
Continuous inspection was not requested to verify fill soils were
placed in accordance with current standard practices regarding
grading operations and earthwork construction. Therefore, as eco-
nomically feasible as possible, part -time inspection was provided.
Hence, the following recommendations are based on the assumption
that all areas tested are representative of the entire project.
1) Compacted fill and natural ground within the defined
building areas have adequate strength to safely support
the proposed loads.
2) Slopes may be considered stable with relation to deep
seated failure, provided they are properly maintained.
Slopes should be planted within 30 days of this report
with light groundcover (no gorilla iceplant) indigenous
to the area. Drainage should be diverted away from the
slopes to prevent water flowing on the face of slope.
This will reduce the probability of failure as a result
of erosion.
3) Continuous footings having a minimum width of 12
inches and founded a minimum of 18 inches below lowest
adjacent grade for one and two story, respectively, will
have an estimated allowable bearing value of 1800 lbs.
per square foot.
4) Footings located on or adjacent to slopes should be
founded at a depth such that the horizontal distance from
the bottom outside face of footing to the face of the
slope is a minimum of 8 feet.
NORTH COUNTY
COMPACTION
ENGINEERING, INC.
December 4, 1995
Project No. CE -5086
Page 4
5) Plumbing trenches should be backfilled with
nonexpansive soil having. ,a swell of less the 2% and a
minimum sand equivalent of 30. Backfill soils should be
inspected and compacted to a minimum of ninety percent
(90 %) .
6) Unless requested, recommendations for future
improvements (additions, pools, recreational slabs,
additional grading, etc.) were not included in this
report. Prior to construction, we should be contacted to
update condition and provide additional recommendations.
SST TENSION SLAB AND FOUNDATION
In our opinion, a post tension foundation system performs well with
regard to the effects of expansive soils. The following
recommendations and design criteria should be incorporated into the
design and construction of the system. The design should be
performed by a licensed engineer enkaged in this type of
construction and who has a minimum of 5 years experience.
Continuous footings having a minimum width of 12 inches and founded
a minimum of 18 inches below lowest adjacent grade will have an
allowable bearing pressure of 1800 lbs. per square foot.
Clayey soils should not be allowed to dry prior to placing
concrete. They should be watered to insure they are kept in a very
moist condition or at a moisture content exceeding optimum moisture
content by a minimum of 3 %.
Prior to pouring of concrete, North County COMPACTION ENGINEERING,
INC. should be contacted to inspect foundation recommendations for
compliance to those set forth.
During placement of concrete, North County COMPACTION ENGINEERING,
INC. and /or a qualified concrete inspector should be present to
document construction of foundations.
UNCER.TAINY AND LIMITATIONS
In the event foundation excavation and steel placement inspection
is required and /or requested, an additional cost of $160. 00 will be
invoiced to perform the field inspection and prepare a Final
Conformance Letter. If foundations are constructed in more than one
phase, $110.00 for each additional inspection will be invoiced.
N ORTH COUNTY
COMPACTION
ENGINEERING, INC.
December 4, 1995
Project No. CE -5036
Page 5
It is the responsibility of the owner and /or his representative to
carry out recommendations set forth in this report.
San Diego County is located in a high risk area with regard to
earthquake. Earthquake resistant projects are economically un-
feasible. Therefore, damage as a result of earthquake is probable
and we assume no liability.
We assume the on site safety of our personnel only. We cannot
assume liability of personnel other than our own. It is the
responsibility of the owner and contractor to insure construction
operations are conducted in a safe manner and in conformance with
regulations governed by CAL -OSHA and /or local agencies.
If you have any questions, please do not hesitate to contact us.
This opportunity to be of service is sincerely appreciated.
Respectfully submitted,
pMsl
North County
COMPACTION ENGINEERING, INC. ��� Q,OGEk
oQ� C <i -,
N .GE713
xp. 9.30 -97
Ronald K. Adams Dale R. Re
Q'
President Registered 0 � `��9393
Geotechnical'rp\\� 00713
RKA: kla
cc: (3) Submitted
(2 ) Filed
NORTH COUNTY COMPACTION ENGINEERING, INC.
SOIL TESTING S INSPECTION SERVICES
TEST PIT LOCATION PLAN
PROPOSED HEERS RESIDENCE
Lot #28 of Wildflower Estates
Encinitas, California
1" = 40'
18 Cut
37, 42,
"� @ 2.1
21- 2 /.
�} Driveway
Turnaround
20, Z3• 38. wl,
Pad Elevation =250
�2r
10. 14 . 45 34•
28.
�1•
9• 2H 29.
81 25, 19_ 40- 5.
22' Fill 5. 12 0
2:1
1. \
.(� I / . 26 30•
7. 17. 18.
6. 16.
ROJECT NO CE -5086 PLATE NO ONE
NORTH COUNTY
COMPACTION
ENGINEERING, INC.
TABULATION OF TE RES
TEST# DATE HORZ. Y RT - FIRU RRY DENSITY S -IL PERCENT
LOC. LSD wim LB. /C0. FT . TCYT-F, COMPACT IO
1 11/02/95 See 226.0 14- 1 109.4 II 92.0
2 " Plate 228.0 16.8 102.1 I 91.1
3 11/03/95 One 229.0 12.1 104.8 II 88.1
4 229.0 15.1 109.7 II 92.3
5 231.0 16.4 103.3 I 92.1
6 11/06/95 233.0 19.3 107.5 II 90.4
7 234.5 17.7 113.6 III 93.8
8 233.5 16.6 113.9 III 94.1
9 235.0 17.2 112.4 III 92.8
10 232.0 15.0 114.9 III 94.9
11 234.0 17.2 112.7 III 93.1
12 234.0 16.9 116.0 III 95.8
13 236.0 16.8 111.6 III 92.2
14 11/07/95 236.0 18.2 109.5 III 90.4
15 237.5 17.9 110.0 III 90.9
16 238.0 17.1 -110.9 III 91.6
17 239.0 18.7 , 109.4 III 90.3
18 240.0 17.4 112.6 III 93.0
19 238.0 18.6 109.9 III 90.8
20 239.0 16.7 111.4 III 92.0
21 11/08/95 240.0 17.3 112.2 III 92.7
22 242.0 16.7 111.9 III 92.4
23 240.0 18.6 113.4 III 93.7
24 241.0 15.9 110.7 III 91.4
25 242.0 16.5 114.6 III 94.7
26 244.0 15.4 1.13.9 III 94.1
27 11/09/95 246.0 17.8 109.3 II 91.9
28 248.0 16.7 112.5 II 94.5
29 246.0 19.5 108.9 II 91.6
30 11/10/95 245.0 17.3 111.7 II 93.9
31 " 245.0 16.1 110.9 II 93.3
32 11/13/95 246.0 17.6 113.0 II 95.0
33 248.0 18.2 114.5 II 96.2
34 245.0 16.6 116.1 II 97.7
35 246.5 18.1 115.5 II 97.1
36 11/14/95 245.0 16.0 116.8 II 98.2
37 247.0 17.2 114.7 II 96.4
38 248.0 17.0 112.0 II 94.1
39 11/22/95 248.0 18.2 115.7 IV 93.3
40 248.5 16.0 114.0 IV 91.9
PROJECT NO. CE -5086
PLATE NO. TWO (page 1)
NORTH COUNTY
COMPACTION
ENGINEERING, INC.
TABULATION-.-DE--TEST RESULTS
TEST# DATE HORZ. VERT, FIELD DRY DENSITY S C)IL PERCENT
L9C, LOC _ MOIST LB_ /CU T= Q011FAULM
41 11/22/95 See 249.0 15.8 112.2 IV 90.4
42 Plate 248.0 17.0 113.9 IV 91.9
43 One 249.0 18.6 111.9 IV 90.2
44 11/27 /95 250.OFG 12.1 115.0 IV 92.7
45 250.OFG 11.3 113.7 IV 91.6
REMARKS:
Test No. 4 is a retest of Test No. 3.
FG = Finish Grade
PROJECT NO. CE -5086
PLATE NO. TWO (page 2)
NORTH COUNTY
COMPACTION
ENGINEERING, INC.
TABULATION OF TEST RLUIM-
OPTIMUM MOISTURE /MAXIMUM DENSITY
SOIL DESCRIPTION TYPE MAX. DRY, ,DENSITY OPTIMUM MOISTURE
(lb /c u.'t.; ) (% dry wt) 11
Red Brown Clay I 112.'1 16.9
Yellow Brown
Gravelly Clay II 118.9 15.7
Red Brown Silty
Clayey Sand III 121.0 15.5
Orange Silty -
Gravelly Clayey Sand IV 124.0 13.5
EXPANSION POTENTIAL
SAMPLE N0, IV
CONDITION Remold 90%
INITIAL MOISTURE ( %) 13.7
AIR DRY MOISTURE (%) 10.0
FINAL MOISTURE ( %) 21.8
FINAL DRY DENSITY (pcf ) 111.6
LOAD (psf) 150
SWELL ( %) 5.2
EXPANSION INDEX 52
DIRECT SHEAR
SAMPLE N0, IV
CONDITION Remold 90%
ANGLE INTERNAL FRICTION 22
COHESION INTERCEPT (PCF) 300
PROJECT NO_ CE -5086
PLATE NO. THREE
NORTH COUNTY
COMPACTION
ENGINEERING, INC.
April 23, 1996
Project No. CE -5143
Todd's Enterprises
c/o Al Mayo & Roy Oakley
1772 Kettering
Irvine, CA 92714
Subject: Report of Certification of Compacted Fill Ground
Propo d Single Family Dwelling
Lot 2 Wildflower Estates
Encinitas, California
Gentlemen:
In response to your request, the following report has been prepared
to indicate results of soil testing, observations and inspection of
earthwork construction at the subject site.
Testing and inspection services were performed from November 22,
1995 through April 22, 1996.
Briefly, our findings reveal filled ground has been compacted to a
minimum of ninety percent (90 %). Therefore, we recommend
construction continue as scheduled.
SCOPE
Our firm was retained to observe grading operations with regard to
current standard practices and to determine the degree of
compaction of placed fill.
Grading plans were prepared by K & S Engineering of San Diego,
California.
Grading operations were performed by Whilock Grading of Vista,
California.
Reference is made to our previously submitted report entitled,
"Preliminary Soils Investigation ", dated May 15, 1995.
Approximate locations and depth of filled ground and extent of
earthwork construction covered in this report are indicated on the
attached Plate No. One entitled, "Test Location Sketch ".
P.O. BOX 302002 • ESCONDIDO, CA 92030
(619) 480 -1116
NORTH COUNTY
COMPACTION
ENGINEERING, INC.
April 23, 1996
Project No. CE -5143
Page 2
Grading operations were performed in order to create a level
building pad. Should the finished pad be altered in any way, we
should be contacted to provide additional recommendations.
The site was graded in accordance with recommendations set forth in
our previously submitted report.
The site was graded to approximately conform to project plans.
Actual pad size and elevation may differ. Finish grade operations
are to be completed at a later date.
LABORATORY TESTING
Representative soil samples were collected and returned to the
laboratory for testing. The following tests were performed and are
tabulated on the attached Plate No. Three.
1. Optimum Moisture /Maximum Density (ASTM D -1557)
2. Expansion Potential Test
SOIL CONDITION
Native soils encountered were silty -clays and gravelly- clays. Fill
soils were generated from the on -site excavation and imported.
The building site contained a transition from cut to fill.
However, cut areas located within the building pad area were over
excavated a minimum of 4 feet and brought to grade with compacted
soil.
Oversize material consisting of rock was hauled off -site and /or
used above grade for landscaping. Oversize material is defined as
rock and boulders in excess of 12 inches in size.
Expansive soils were observed during grading and exist within 24
inches of finish grade. Therefore, special recommendations will be
necessary to reduce the probability of structure damage.
The key was approximately 25 feet wide, a minimum of 3 feet in
depth and inclined into the slope. During earthwork construction,
native areas to receive fill were scarafied, watered and compacted
to a minimum of ninety percent (90 %) of maximum density. Subsequent
fill soils were placed, watered and compacted in 6 inch lifts.
Benches were constructed in natural ground at intermediate levels
NORTH COUNTY
COMPACTION
ENGINEERING, INC.
April 23, 1996
Project No. CE -5143
Page 3
to properly support the fill. To determine the degree of
compaction, field density tests were performed in accordance with
ASTM D -1556 or D -2922 at the approximate horizontal locations
designated on the attached Plate No. One entitled, "Test Location
Sketch ". A tabulation of test results and their vertical locations
are presented on the attached Plate No. Two entitled, "Tabulation of
Test. Results". Fill soils found to have a relative compaction of
less than ninety percent (90 %) were reworked until proper
compaction was achieved.
RECOMMENDATIONS AND CONCLUSIONS
Continuous inspection was not requested to verify fill soils were
placed in accordance with current standard practices regarding
grading operations and earthwork construction. Therefore, as eco-
nomically feasible as possible, part -time inspection was provided.
Hence the following recommendations ecommendations are based on the assumption
that all areas tested are representative of the entire project.
1) Compacted fill and natural ground within the defined
building areas have adequate strength to safely support
the proposed loads.
2) Slopes may be considered stable with relation to deep
seated failure, provided they are properly maintained.
Slopes should be planted within 30 days of this report
with light groundcover (no gorilla iceplant) indigenous
to the area. Drainage should be diverted away from the
slopes to prevent water flowing on the face of slope.
This will reduce the probability of failure as a result
of erosion.
3) Continuous footings having a minimum width of 12
inches and founded a minimum of 24 inches below lowest
adjacent grade for one and two story, respectively, will
have an estimated allowable bearing value of 1500 lbs.
per square foot.
4) Footings located on or adjacent to slopes should be
founded at a depth such that the horizontal distance from
the bottom outside face of footing to the face of the
slope is a minimum of 8 feet.
NORTH COUNTY
COMPACTION
ENGINEERING, INC.
April 23, 1996
Project No. CE -5143
Page 4
5) Plumbing trenches should be backfilled with non -
expansive soil having a swell of less the 2% and a
minimum sand equivalent of 30. Backfill soils should be
inspected and compacted to a minimum of ninety percent
(90%) .
6) Unless requested, recommendations for future
improvements (additions, pools, recreational slabs,
additional grading, etc.) were not included in this
report. Prior to construction, we should be contacted to
update condition and provide additional recommendations.
7) Completion of grading operations were left at rough
grade. Therefore, we recommend a landscape architect be
contacted to provide finish grade and drainage
recommendations. Drainage recommendations should include
2% minimum fall away from all foundation zones.
8) Expansive soil conditions observed during grading
operations will require special recommendations to reduce
structural damage occurring from excessive subgrade and
foundation movement. Therefore, we recommend foundations
be designed and constructed in accordance with
Recommendation 6B2 and /or 6B3 of our "Preliminary Soils
Investigation ", dated May 15, 1995.
9) Clayey soils should not be allowed to dry prior to
placing concrete. They should be watered to insure they
are kept in a very moist condition or at a moisture
content exceeding optimum moisture content by a minimum
of five percent (5%) .
Prior to pouring of concrete, North County COMPACTION ENGINEERING,
INC. should be contacted to inspect foundation recommendations for
compliance to those set forth.
During placement of concrete, North County COMPACTION ENGINEERING,
INC_ and /or a qualified concrete inspector should be present to
document construction of foundations.
UNCERTAINTY AND LIMITATIONS
In the event foundation excavation and steel placement inspection
is required and /or requested, an additional cost of $160.00 will be
invoiced to perform the field inspection and prepare a Final
NORTH COUNTY
COMPACTION
ENGINEERING, INC.
April 23, 1996
Project No. CE -5143
Page 5
Conformance Letter. If foundations are constructed in more than one
phase, $110.00 for each additional inspection will be invoiced.
It is the responsibility of the owner and /or his representative to
carry out recommendations set forth in this report.
San Diego County is located in a high risk area with regard to
earthquake. Earthquake resistant projects are economically un-
feasible. Therefore, damage as a result of earthquake is probable
and we assume no liability.
We assume the on site safety of our personnel only. We cannot
assume liability of personnel other than our own. It is the
responsibility of the owner and contractor to insure construction
operations are conducted in a safe manner and in conformance with
regulations governed by CAL -OSHA and /or local agencies.
If you have any questions, please do not hesitate to contact us.
This opportunity to be of service is sincerely appreciated.
Respectfully submitted,
North County
COMPACTION ENGINEERING, INC.
G ER,��
CID oGE713
p. 9 3
Ronald K. Adams Dale R. G�
President Register 19393
Geotechni Q 000713
RKA: kla
cc: (3) Submitted
(2) Filed
NORTH COUNTY COMPACTION ENGINEERING, INC.
SOIL TESTING & INSPECTION SERVICES
TEST PIT LOCATION PLAN
Driveway Violet
39 Ridge
i
46
40
\ 45 12' Cu
33 @ 2 :1
\ 43
/7 Pad Elevation = 201.0 4 9
33
23 44
2 /9 26 30 43
/2 3 S
4 37
9
LAG Test
28' Fill
@ 2:1 3 /� /5 25 47
/3 20 24 29
8 32
27 3/
28
/0
6 2/
/6 22
4 Approx.-Scale
LOT #26 OE WILDFLOWER ESTATES 7 1 = 35'
Encinitas, California
ROJECT NO CE -5143 PLATE NO ONE
NORTH COUNTY
COMPACTION
ENGINEERING, INC.
TABULATION OF EST RESULTS
TEST# DATE HORZ. VERT. EMU DRY DENSITY SOIL PERCENT
LOC. LOC, MOIST LB. /CII . FT . TYPE COMPACT ION
1 11/22/95 See 173.5 17.7 105.6 II 92.9
2 Plate 175.5 16.3 106.2 II 93.4
3 11/27/95 One 177.5 21.7 102.5 II 90.1
4 " " 178.0 20.5 103.8 II 91.2
5 11/28/95 179.0 17.7 111.2 II 97.8
6 176.0 18.1 105.3 II 92.6
7 11/29/95 178.0 16.8 107.2 II 94.2
8 182.0 17.1 103.9 II 91.3
9 183.0 18.3 105.2 II 92.5
10 180. 0 13.5 104.1 II 91.5
11 185.0 16.5 107.3 II 94.3
12 11/30/95 189.0 13.7 115.8 III 97.3
13 187.0 16.4 107.1 II 94.1
14 185.0 15.1 112.5 III 94.5
15 188.0 14.9 111.9 III 94.0
16 12/01/95 189.0 17.9 114.3 III 96.1
17 191.0 17.1 113.7 III 95.5
18 190.0 17.3 108.0 II 94.9
19 192.0 16.6 114.2 III 96.0
20 192.0 17.1 111.7 III 93.9
21 12/04/95 194.0 16.3 112.3 III 94.4
22 194.0 17.4 110.4 III 92.8
23 195.0 16.0 113.9 III 95.7
24 196.0 15.8 114.5 III 96.3
25 197.0 18.3 110.9 III 93.2
26 197.0 17.6 113.2 III 95.1
27 12/18/95 192.0 16.0 116.3 III 97.7
28 194.0 14.3 114.2 III 95.9
29 194.0 16.6 110.8 III 93.1
30 197.0 17.3 112.6 III 94.6
31 12/20/95 195.0 15.9 110.0 IV 93.4
32 196.0 16.3 111.7 IV 94.9
33 197.0 17.1 109.4 IV 92.9
34 12/21/95 195.0 15.8 109.3 IV 92.9
35 197.0 17.2 110.2 IV 93.6
36 198.0 11.2 103.8 IV 88.2
37 12/22/95 198. 0 18.0 108.7 IV 92.4
38 196.0 16.3 112.1 IV 95.2
39 197.0 17.2 109.4 IV 92.9
40 199.0 15.7 111.6 IV 94.8
PROJECT NO. CE -5143
PLATE NO. TWO (page 1)
NORTH COUNTY
COMPACTION
ENGINEERING, INC.
TABULATION OF TEST RESULTS
TEST# DATE RORZ. VERT. FIELD DRY DENSITY SOIL PERCENT
L9- LOC. MOIST LB. /CU. FT. TYPE COMPACTION
41 01/11/96 See 199.5 16.2 110.7 IV 94.1
42 Plate 200.0 16.5 113.7 IV 96.6
43 One 198.5 16.9 111.5 IV 94.7
44 198.0 17.4 111.0 IV 94.3
45 199.0 16.6 113.2 IV 96.1
46 200.0 18.1 113.4 IV 96.3
47 04/22/96 201.ORFG 09.2 122.2 V 96.6
48 201.ORFG 10.1 123.6 V 97.7
49 201.ORFG 08.4 121.0 V 95.7
REMARKS:
Test No. 37 is a retest of Test No. 36.
RFG = Rough Finish Grade
PROJECT NO. CE -5143
PLATE NO. TWO (page 2 )
e
NORTH COUNTY
COMPACTION
ENGINEERING, INC.
TABULATION---QE TEST RESULTS
OPTIMUM MOISTURE /MAXIMUM DENSITY
SOIL DESCRIPTION TYPE MAX. DRY DENSITY OPTIMUM MOISTURE
(% dry wt)
Red Brown Clay I 110.4 17.3
Orange Brown Sandy -
Gravelly -Clay II 113.7 18.1
Brown Tan Sandy
Clay III 119.0 15.5
Orange Brown Silty
Sandy Gravelly Clay IV 117.7 17
Light Brown Silty -
Sand (Import) V 126.5 10.0
EXPANSION POTENTIAL
SAMPLE N0, I II IV
CONDITION Remold 90% Remold 90% Remold 90%
INITIAL MOISTURE ( %) 16.9 18.1 16.9
AIR DRY MOISTURE M 14.4 14.0 .5.6
FINAL MOISTURE M 36.6 27.3 24.0
FINAL DRY DENSITY (pcf) 99.3 102.3 105.9
LOAD (psf ) 150 150 150
SWELL ( %) 16.4 6.8 6.3
EXPANSION INDEX 164 68 63
PROJECT NO_ CE -5143
PLATE NO. THREE
l
,
r
4
DOON
- : -
\ e _
\ \
II
o 0 0
Ix 0
- \ `:. -
Slidi
x
J
i
R \ \ i
Q .r
syby
od
ai r
LZZ w
y ' 111
l 9
\
\
,
K
°! HMI Q o ._. _ ) sw
nm
Nb
L
,
wti '
0
LSOd
Lib t,' Sr�Oa 6 X
S332l1
t :
,
p • Y! \\ rt \ \ �/ � J ,\ 1 ` ( ,Snag
./J A %4 N i od
,
4
r 1
3
y
,
�n
J
i
4
o } �
w.
,
Q
SNOOK Cl) \ \ 1
\ .ft
8'55Z ``r, i I \ C C C mot'• \ ` � s33ai y
�r
/ O
l -
s'zsz lmdEMIL IF Y 1 � ,•, �'? N
Z' LSZ ow O
pop
y , s
\ „ e
" �-
1 s3381
ow
0.
Isod
2
1
s,.
a -
�_ \ ZI v ;zel
n 'A -
8' i L t ow
®r
2 91-Z Coon
Y— SA00N
, a 000 s
`
9'L9L X oo'L>:Z + WOOL
If
6LZ >� X �' �" t `. L\ ( \ \ /� �t V l�
S1SOd 9'08Zr t y �' i - - \ ► tyL T % . \ r -
f -
,�
�,I C
9 k9
i '
! _
1
4 61(1