1998-5636 G
Street Address
. ------.----. _...-
'6'l~ç
I
~ /1?:rc:r
Serial #
Category
)~3~
/61
Description
Name
Year
Plan cK. #
NORTH CO(JNTY
COMPACTION
ENGINEERING, INC.
February 15, 1999
Project No. CE-5742
Whisper Winds Villa, LLC
1402 Oribia Rd.
Del Mar, CA 92014
Attn: Majid Kharrati
Subject:
Report of Certification of Compacted Fill Ground
Proposed Single Family Dwelling
515 Whisper Wind Lane
Encinitas, California
Dear Mr. Kharrati:
In response to your request, the following report has been prepared to indicate results of soil
testing, observations, and inspection of earthwork construction at the subject site.
Testing and inspection services were performed from January 19, 1999 through
February 2, 1999.
Briefly, our findings reveal filled ground has been compacted to a minimum of ninety percent
(90%). Therefore, we recommend construction continue as scheduled.
SCOPE
Our firm was retained to observe grading operations with regard to current standard practices
and to determine the degree of compaction of placed fill.
Grading plans were prepared by K & S Engineering of San Diego, California.
Grading operations were performed by Mike Loyd of Fallbrook, California.
Reference is made to a following previously submitted soils reports:
1.) "Preliminary Geotechnical Investigation" prepared by Barry
& Associates, dated June 19, 1989
2.) "Rough Grading Report" prepared by Barry & Associates,
dated March 23, 1993
3.) "Updated Geotechnical Investigation", prepared by Barry &
Associates, dated August 23, 1998
P.o. BOX 302002 if ESCONDIDO, CA 92030 * (760)480-1116 FAX (760)741-6568
NORTH CO(JNTY
COMPACTION
ENGINEERING, INC.
Project No. CE-5742
Page 2
4.) "Slope Stability Analysis" prepared by North County Compaction
Engineering, Inc., dated January 19, 1999
Approximate locations and depth of filled ground and extent of earthwork construction covered
in this report are indicated on the attached Plate No. One entitled, "Test Location Sketch".
Grading operations were performed in order to re-grade an existing building pad to
accommodate the proposed dwelling. Should the finished pad be altered in any way, we should
be contacted to provide additional recommendations.
The site was graded in accordance with recommendations set forth in the soils reports prepared
by Barry & Associates.
The site was graded to approximately conform to project plans. Actual pad size and elevation
may differ. Finish grade operations are to be completed at a later date.
LABORATORY TESTING
Representative soils samples were collected and returned to the laboratory for testing. The
following tests were performed and are tabulated on the attached Plate No. Three.
1. Optimum MoisturelMaximum Density (ASTM D-1557)
2. Expansion Potential Test (FHA Standard)
3. Direct Shear (ASTM D-3080)
SOIL CONDITIONS
The building site contained a transition from cut to fill. However, cut areas located within the
building area were over excavated a minimum of 3 feet and brought to grade with compacted
soil. Over excavation was carried a minimum of 5 feet beyond the exterior building perimeter.
Hence, no consideration need be given this characteristic.
Expansive soils were not observed. Therefore, no special recommendations are required.
During earthwork construction, native areas to receive fill were scarified, watered, and
compacted to a minimum of ninety percent (90%) of maximum density. The key was
approximately 15 feet wide, a minimum of2 feet in depth, and inclined into the slope.
NORTH CO(JNTY
COMPACTION
ENGINEERING, INC.
Project No. CE-5742
Page 3
Subsequent fill soils were placed, watered, and compacted in 6 inch lifts. Benches were
constructed in natural ground at intermediate levels to properly support the fill. To determine the
degree of compaction, field density tests were performed in accordance with ASTM D-1556 or
D-2922 at the approximate horizontal locations designated on the attached Plate No. One
entitled, "Test Location Sketch". A tabulation of test results and their vertical locations are
presented on the attached Plate No. Two entitled "Tabulation of Test Results". Fill soils found to
have a relative compaction of less than ninety percent (90%) were reworked until proper
compaction was achieved.
RECOMMENDA nONS AND CONCLUSIONS
Continuous inspection was not requested to verify fill soils are placed in accordance with current
standard practices regarding grading operations and earthwork construction. Therefore, as
economically feasible as possible, part-time inspection was provided. Hence, the following
recommendations are based on the assumption that all areas tested are representative of the
entire project.
1). Compacted fill and natural ground within the defined building areas have
adequate strength to safely support the proposed loads.
2). Slopes may be considered stable with relation to deep seated failure provided
they are properly maintained. Slopes should be planted within 30 days with light
groundcover (no gorilla ice plant) indigenous to the area. Drainage should be
diverted away from the slopes to prevent water flowing on the face of slope. This
will reduce the probability of failure as a result of erosion.
3). In our opinion, soil liquefaction at the site is unlikely to occur due to the
following on-site soils conditions:
A). Groundwater was not encountered at the time of grading.
B). Fill ground and loose topsoils were compacted to a minimum of
ninety percent (90%) of maximum dry density.
C). The dense nature of the formation underlying the site.
NORTH CO(JNTY
COMPACTION
ENGINEERING, INC.
Project No. CE-5742
Page 4
3). Temporary slopes to be retained and/or completed at a later date should be
considered unstable and may prove to be a detrimental condition. Furthermore,
we should be contacted to supervise backfill operations. Backfill materials should
consist of non-expansive soils (having a swell of less than 2%)'placed at a width
behind the wall equivalent to two-thirds of the retained height. Crushed rock (1
inch minus), approved by this office, may be an alternate method. All walls
should be provided with drains. Drains should consist of 4 inch perforated pipe
surrounded with crushed rock placed at a minimum of 1 cubic foot per lineal foot
and have a minimum fall of one percent (1 %). A structural engineer should be
contacted for a retaining devise recommendations.
4). Continuous footings having a minimum width of 12 inches and founded a
minimum of 12 inches and 18 inches below lowest adjacent grade for one and
two stories, respectively, will have an estimated allowable bearing value of 1500
pounds per square foot.
5). Footings located on or adjacent to slopes should be founded at a depth such
that the horizontal distance from the bottom outside face of footing to the face of
the slope is a minimum of 8 feet.
6). All foundations should be constructed in accordance with the Preliminary
Geotechnical Report prepared by Barry & Associates dated June 19, 1989.
7). Plumbing trenches should be backfilled with a non-expansive soil having a
swell ofless than two percent (2%) and a minimum sand equivalent of30.
Backfill soils should be inspected and compacted to a minimum of ninety percent
(90%).
8). Completion of grading operations were left at rough grade. Therefore, we
recommend a landscape architect be contacted to provide finish grade and
drainage recommendations. Drainage recommendations should include concrete
sidewalks placed on all sides of structures a minimum of 4 feet in width and have
a minimum fall of two percent (2%) away from foundation zones. To further
protect water penetration of the zone, rain gutters should be installed to divert
run-off. Landscape planter areas within 4 feet of the foundation should be avoided
and/or designed with sealed bottoms and a drain system.
9). Prior to construction of the proposed pool, the pool contractor should be
contacted for concrete and reinforcement design. Pool excavation spoil should be
hauled off-site or properly placed on site under the supervision of our firm.
NORTH CO(JNTY
COMPACTION
ENGINEERING, INC.
Project No. CE-5742
Page 5
Prior to pouring of concrete, North County COMPACTION ENGINEERING, INC. should be
contacted to inspect foundation recommendations for compliance to those set forth.
During placement of concrete North County COMPACTION ENGINEERING, INc. and/or a
qualified concrete inspector should be present to document construction of foundations.
Foundation recommendations presented in this report should be considered minimal. Therefore,
we recommend the project architect and structural engineer review this report to assure
recommendations presented herein will be suitable with regard to the type of construction
planned.
UNCERTAINTY AND LIMITATIONS
In the event foundation excavation and steel placement inspection is required and/or requested,
an additional cost of$170.00 will be invoiced to perform the field inspection and prepare a
"Final Conformance Letter". If foundations are constructed in more than one phase, $120.00 for
each additional inspection will be invoiced.
It is the responsibility of the owner and/or his representative to carry out recommendations set
forth in this report.
San Diego County is located in a high risk area with regard to earthquake. Earthquake resistant
projects are economically unfeasible. Therefore, damage as a result of earthquake is probable
and we assume no liability.
We assume the on-site safety of our personnel only. We cannot assume liability of personnel
other than our own, It is the responsibility of the owner and contractor to insure construction
operations are conducted in a safe manner and in conformance with regulations governed by
CAL-OSHA and/or local agencies.
NORTH CO(JNTY
COMPACTION
ENGINEERING, INC.
Project No. CE-5742
Page 6
If you have any questions, please do not hesitate to contact us. This opportunity to be of service
is sincerely appreciated.
Respectfully submitted,
North County
COMPACTION ENGINEERING, INC.
~ Æ:- a£--
Ronald K. Adams
President
RKA:paj
cc: (3) submitted
NORTH COCNlY COMPACTION ENGINEERING, INC.
SOIL TESTING
PROPOSED SINGLE FAMILY DWELLING
WHISPER WIND LANE
ENCINITAS, CA
1-- ---
/
..
\'"
"
"':::::..::
~
cl
TEST LOCA TION SKETCH
PROJECT No. CE-5742
PLA TE No. ONE
~
~
\
'"",
NO SCALE
.
,
NORTH CO(JNTY
COMPACTION
ENGINEERING, INC.
Test # Date Horizontal Vertical Field Moisture Dry Density Soil Percent of
Location Location % Dry Wt. LB Cu, Ft, Type Compaction
1 01/20/99 See 191.0 14,5 101.1 I 96,2
2 Plate 193,0 12.5 101.3 I 96.4
3 01/22/99 One 193.0 14.1 113,9 II 96,9
4 194.0 14,3 112.2 II 95.4
5 01/28/99 " 206.0 14.2 111.4 II 94,8
6 206,0 13,7 109.4 II 93.1
7 203,0 12.0 105.8 II 90.0
8 " 196,0 12.3 106.3 II 90.4
9 198.0 13,1 107,6 II 91.6
10 0 1/29/99 " 206.0 15,6 106.3 II 90,5
11 206,0 15,3 111.7 II 95,1
12 202,0 13.4 99.3 I 94,5
13 203,0 14,1 110,7 II 94.2
14 02/02/99 206.0 13.4 100.1 I 95.3
15 205.0 15,3 114.7 II 97,6
16 207.0 RFG 14.9 100,2 I 95.4
17 207.0 RFG 12,9 97.5 I 92,9
REMARKS:
RFG = Rough Finish Grade
PROJECT NO. CE-5742
PLATE NO. TWO
.
NORTH CO(JNTY
COMPACTION
ENGINEERING, INC.
SOIL DESCRIPTION IYffi MAX. DRY DENSITY OPT. MOISTURE
(LB. CD. FT) (% DRY WT)
Tan White Silty-Sand I 105.0 12.5
Beige Tan Silty Sand II 117.5 12.8
SAMPLE NO.
CONDITION
INITIAL MOISTURE (%)
AIR DRY MOISTURE (%)
FINAL MOISTURE (%)
DRY DENSITY (PCF)
LOAD (PSF)
SWELL (%)
EXPANSION INDEX
SAMPLE NO.
CONDITION
ANGLE INTERNAL FRICTION
COHESION INTERCEPT (PCF)
EXPANSION POTENTIAL
I
Remold 90%
12.3
7.1
12.3
94.5
150
0
Less than 5
DIRECT SHEAR
I
Remold 90%
30
100
PROJECT NO. CE-5742
PLATE NO. THREE
11-20-19955:25PM
FROM
Ðl/26/1~~~ Ð8;~S
. à' ' ,
'. '
COMPACTION ENG
Pt:Œ. 01
76Ð7416S68
NORTH COUNTY ,
C,OMPA CTI,Q IN
ENCHNEERINCi. INC. '
January 19, 1999
Projec~ No. C£. ,5742
, .
Whisper :Winds Villa" LLC
1402 OribiaRd.
Del Mar~' CA 92014
Attn: Majid Khaitati
Post..t" brand fax rransmittal memo 7671 '
To
Subjed: :
Slope 'Stability Analysis '
Proposed Northerly 1.S~ I, Cut Slope
Proposed, Single: F amUy DMU~ '
'1 S Whisper Wind laI18 ' ,
, EnCùU1!aS, Califomia
, DcarMr. ~barratj:
4t response to your request, we have performed a Slope Stability A,iJaJysìs for the: subject project.
It is our UnderstaridiD~ the existin& 2: 1 (horizonlll1 to:'Veniça1 -) çu~ slope l~ted along the
north pròptrty line wi 11 be fe-graded at mclina%íon of I, S : t . ' " .
'Our field mspection cf}anWliy ] S~ 1999, rm:al.cd tbatsoils, exposed in the face of the existing, 10
toot high, 2: 1 slòpe were comprised of ~ èem~ slightly 5ilty-wúfonn sandstoDcs
, bomogeneo,us in nat\IJ~. "
, 'Soil samples were obf~ from "the face of slope and retumed'to our laboratory Jor testing.
Dirœt Shear tests weI:e performed On remolded (90%) soil,sampla in~ with ASTM ,
, 'D-3080.;S4bseqœnttotesting, tbeon-síœ.soüs were fo~tOhave~angJeofiritema1 friÇtjon )
': ::fty 7.:= =:::::: =~ ûcUK ofsafety 9Í 1.5. and .
à seismW load of; 1 G. Our analysis revealed that the proJ'O~ 1.~: 1 cUt slope rc-grad.ed to a
maximum 'height of 12 feel will be, Stable with relation to deep Seated failure provided it' is
, properly maintaU1cd Positive drainage away fmm the top ofme sbould be provided. Slopes
$hould be planted as :iOOft as possible with lígh,t ground cover: indipous too the area. '
P. O. BOX JO2OÐZ * ESCONDIDO,.a" 92030 ~ (760)48t)a1116 FAX ("7~)741~
,'",' ",': ';,'
P.1
'";"",',,,
....,.,.'.~~
i.¿Î
:[1
i:!
XI
,':'~~r
';~
. '/~"\Q\
, /i¡t~
,it
,:;/~~~
./\:~
, ",T~~
.'~I
':6:~~
11-20-19955:26PM FROM
al/2~/1999 0S:45 76B7416568
,-
. '
.
i
NORTH COOl'O"Y, '
COMPACTION
ENG.NEERINCi, INC.'.-
, ' ,
CCJtPACTION ENG
, ,
, ' ,
Projeçt No.' CE-S 742
page 2 " '
P.2
PAGE 1:12
!:,
-""'~~
;'1
," ,<"~::s
""~~,'"
-,:'~:~1~
"":-'.,.~
"':':;/$
, """".tli.to.
"',,~!;~¡
"::;:i~:~
"""'!"1~
;'(1
":!?:f~~
,.'.'",ê'".:~,¡\j
, ":h~'~
"', 'i1Ô-~!¡
:1~
:,..~
í
'<':::î1
<':!;~
,.~~
'""f"~
,'if,
",-,~
:'<:;;:¡
'."oJ,,".
," \"':s-f'¡
".';"~1i
""::":;:;~)~
':, "~~'I" ,
, ' '.., ,.¡ >
"'.~.
".::'j~FI;<
,'","""~
, """!£,,
" ;\~~~
,I'
-~I
"":'::{~il"'~'
::::,L~%
-".'~':,:I
'i~J
""",,1:,1
" ,~.y~
'.'<~11
.~~
, "If you haYe'aDY questi,)ÙS, please dO not hGi.. to,çOD~ us:, 'l1û~ opPortunity to be of service:
ji siDœrc?ly 8W" è(.iated. " ',' " :'
,
, ' '
: ,a.e.speçtf\dly submitlel1~
" '
, '
',N~J1hCOuty , ,',
. ,ÇOMP~ctnON':EN~:¡eŒEBlNG,'lNc.,
",
~~~/. '
, Rooald K. Adams '
President!"
, '
'R1V\:paj
(~) 'submine(t
,çç;,
, .
.. ;
, "
, ,
..
..' ,
- .: '
" ..
..
...' ",
:," '1'.",,'
, ,'," ..' , .'
, ,
, "
,¡ ':
"',
'..' :
, .
, ,.
" "
'.
, '
" \',
, ,
,: '
,,'
'," ,
, '.
, ,.' '.
11-20-19955:26PM
131/213/113'3'3
138:45
Oo' ;'
t:
Ë
""-
VI
Co'
~
~
ç
¡ c I
: ~
¡ '§ -:::
: .~ ~ t"t..1
: § ~~~
:,~~ I
. -. .. 0.-.
; It. "õ
: ..::!. C
, 0 . \
: !: ~"
, c -. ~
: c= ~ f
L.;J '-
!- (/',
<: ".' ~ '-
(O ~:< <:
~'u.. U
e>:c;.; ~
O'Q. 0
~ .
C
....J' ,
~ :~.
L:.O \ -'
~:~ ':/'
<.;.'~ r'I
,~;;, .......
ir.
~
"V"
ï\ ~.
,,¡po-
~'\. a:
('t ~ ~
"'", :::
:I/í
11 : G
1.1.'
~' ~
.'
. I
I. I
¡ . ¡
I
.J
~'\
-'\
\1\
r{
'~',
~
"
.)
\9,
~¡
~ . ~~\t,
, ' I
~ . j ð o'
\J..u UJ: ,!-. . z;
o~'_~;,;~'¡~:':~ ',(9,'
".~'~';;~"~'~;':::G'~
~"g"~"õ::'f2' a:¡
"""'" U) 'U). c
"
'-J
~.
(\.
\;\
~
"
'-.,;'
FROM
POo3
76137416568
COMPACTION ENG
PAGE
134
:c
:~:
~.
<
C:
V:
¡ ': ¡
:::?~;
. ':"".,~
., ',r,~
¡~ì
OoOo ., .. ,.'.
"':N.';
; ,FZ
. 1, "'..,
~
¡ '~l ,C,
, I ,":'-';1
. , \:?,'"
~ .' :..r:~
I ¡;,~
,..-~~
I ."
',' t.:,
. ~ ,,{~~
; "
: ,\
I
.
J
I
I
. I
'. .
!
..:1
s:
"II'
:=.
¡ ,
I
¡
~
-
-
~ .1
I
I
~~'
~
<;
. c.
u;
c-.
-I
<:
E
z
,
,1
-
-
\,: ~JJ.,,}~ ~¡~~,
~ Y~'1~~~\.s~ '. ,
c-.-çr-..<;;;)COOQOOO
- T. pi) "I:' 5 c.::.I ~ c:: CI). 0 - C'I.: ~ ~ "'.
... -'-----
~
=
I
I
...) "
:E "I~
i~¡~
'-, I
~'"
- . I
~ r\ '
~~ ¡
~, I'
I
..
- - w w' ..
0" ..... .. '"
'. ,.. 0 .. .
-. on . '-" ,. ,.. 0
ow 'w 0' '. ..
, - - _. ... .' 0 ,. ,0.' .
J -
. 0.. .'0' ,-...... .. ,. u . .. , ..' .
. - . - . ..
=
,. .. ...
. .. .. .. .
...
,:
~ ~
~";~
. .
~. ~w.
" 0 ,. . ,. '.. ..0 .. - -
..
."""""""-
. J
, . I I
SLOPE i Ot:Stt3N
c. ~ - - ,.>? 'I L......:..
..,
pol,
I1J
c:
....
~
,
.....
v'
,
.,.. C9
..... ~
:'.;:; I
C9 I\)
,...... IS)
..... I
ú) ~
ú) <D
ú) <D
Ul
Ul
..
I\)
--..J
1)
~
Ln_O
.'
., >1\
it t', '
'< ......
to
.... ~
e' .~'
0
.... .
\C
CJ),t;¡
þf
""'
t-",
co
Q)
,
.:.¡
0
~
C9
, ... -. CD
. .
r>-
Ut
.....
C7'
C9
.....
~ TJ
en AJ
Ut 0
~ ~
~
1)
-t
H
~
PI
Z
(i)
r;
'11
~
œ
w
1)
þ.
,-
,-____~~I___- -
i~ ~D:r&. ~Äl1e
.: n J r-" -- .-
,I ~, h 1'1':
,I n ' : "VA ¡;;;
¡; ¡,'¡ 9
,," -
,: U~j L
li,
¡
OF t
W\.$~E 1<. WltJO
PA ~(é L '2...
1«::>/15/58
.
.
..
:j'"
,!!\
, '--
':;-;-...:
...."
:.f,,': .
.., ,',
>-,,',
TOWER
, ,
CONSULTING ENGINEERS
, ,;' -'"
'~'.~' .~( "~~.;;;
.' i'~.
.-.¡,:,;"
r"
¡ ,
..__...~-
c
~,
..
. '
L
~~
'".
"\,,'
. .
",;':i\1f
-'7~î~ql;~:,:
--,," -
'." 'c, '
." Pi:::'
A~lt~
'.:"-:~f~~:':'
i',¡'"
':::,:':':j~~.f~~,:, "
":.~,>~r
..
, -,' '.
'..;'. ',;:.
- ..
'..
'~.
- I
I
I
í
TOWER CONSULTING' "ENGINEERS
3007 ANDORRA WAY. OCEANSIDE CJ\IJlrORNIA !)205G
I' .
,.,.--"'U_-"". ..---_u"'"
,.---..-.,-... "'"
"--""""'.-
,-.._---~-~
~~"""""'~"......' !
5~T
Jo~. ~A~t
- t::B<>l~N ðF- ~N\ IL.'PIJEf2...- f.:e--TA\NIN G. vJ~.\A.
~--- l / ref.
'~r.f'-; 4-s- +"f.(¡ ~.1 ßp.Q(fILL
¥Iw, :-1t70o (7<; \
t WI :.- 2-C;; 0 '
f's :.- 2-0,00<::> is:
V\ -;. 2-~
Y\ o~ Pe-c..\A L INsf:&c.. 1\:>1'-"
Dp Tt-
'2. of 4
WI) ~y2o w,}:' ()
?AC-ŒL L
IQ(S/4€"
;{-
1
,1..7
F
11
..ft
\=.-.4G x.7x 7/z., -110;,
M :. 45" ^ 7"X ;0: 2'513 - ..Ç.}\ Ib
.ç'
, ., .. "
'I
T121 -z, CM-U~V !.t(0 c.r2.DvTE- D
w I#-s ß~tL.~ (è og~~o._c.-éd =-q LI.) ,
- - ',0'--'-"'0 . ,..-- - -------0"-0.. ----..-,..------------
~ :/ AJ -:.. - ,3>Lx \, S :...4 o-oA-~----------~-- - - .. ,..------- -_0--_, .._,- - -- --. - -
. nç:~5" (,~"2c>~1 \~;.,o~ ;) .~=...81Î'j ~l.~~.IG,. '
-; :--=f~~-_-~~~~~ - ~ :Nf= -: ~f~~~ ~ --OÇ-" .L~;ì_I_~~P 5;5,J~~~~=O': ' ".,'
'.- ,. --~s --_fvtX \~" :-.'2 ';> f:'~) 'L ',::-o--11?..-.-.<::.-2AI-OOD______- - _._-_..~~-,o.¥-~---
, . A~.)J "3lxIÓ~.~ÎIX 9 : . ,
---"'---'----__0_'_--"_-------' ---------""-----______0.__0____'_----'---'---- .-.....--- """--------"-----"----'-'----------"-""""'-
: , .: --C H-e L¡¿ ~ \if? ;...1'-_____5 m.:&ss.------,-----..,- , '" -- ,,- "-""------0" --_:.Ps~ -f!.:..
_h' -'-'----"-'---..- ----......-----...------------.--q¡:> V -- \\03 :- L\ \~._...(J4. --,\.o,~.
, ,_..._-~- - -, . . 'p.jj ,\~)I\gîÎ;<9 '
..-- (Æ:' ~ CtC ~ON 0 <;wxS <;. ~5'
, . . .. .. ... ~~-"v = lid 3 , ,- 1-8 I
. .. ~Jà /,'163)(1,5><. ,g7.,7x1
rJ, It .
. ---.".. ""-"""---,,u,-,,,
-----. ' -- .
_m: ---po_, u_:C\H?C¥- , o\)elL"N(U't\Ñ_~', --_-'n__h_- _m --
-. u_---_.._----~---_._~_._._.,--~.._-~-- ,..~---~-_o_~:r..~M...,-;_~4;-C!.'~ ~~_~m~Q~- ".. ,. -., _m___'._-,,-----~----_..._-,_.--~_...,. ._,
----. ~-:--;-_:_---_._.-- -.:---.., --_._____R...-M.l.;'._.-~-K~15~-^-./-5D_JC.2h..:!'~)x '2....5 ~-2hL~_.~_- --- -_u_----
- : --+--+.-;-,,-~., ,-; -- --:------¡--;--~-¡:--~8-4-~K-7-~L-~.._.~X~.._-~-.._.-58-8 .)(-~.'7.:_;z.L5""-G:,i_~____-
-~, : ..... . u ,..~-~ _: _.. ttO:rÎX I x Sí1z ~ J70X-4-15"::?4tS'----:.., -.
. --- ---- ¿~ F,-~ 8~'4 :..-!I ø 3~>i~~~-~-:.,.'...;~~~--""-' "i ~g~ .- :_-~":_~4:'4- --- ..--'
- , - 4- b()G ( ~ ~ t, J
~i-t1""
JùY;, N ~I--! ç-
\ ,
D~\-e.
~ ClF '1
'N \ S~ErL wnJD
f~~ teL- 2
lol5/9 ß
0\, ~:{~f,) or (AN\. fl.:"\.vJALÆ.. (&:;,:J\,\)
c-~ c (. II
~lIOII-J 6
, "2 .. . .:tf:
<? L.\ On.! G fbP, Lf ~ 4<;:( ~ - I ~'2..-G,
"2... -
. . . r k~lJ\. , z.
R.E<:>I~T'N' ForuE-; t~(¿~4$?+ ~ç~~.O)+ Z.sD(~ )
'2---
-= ß/51-r '5-:;1 7~?~ ð
. ,
-. ., . C¡,f~;. '2-?~~'-;: L4-1~.f15. .S~l.o,~,
, \, 2 c:,
, /"'" - _u -......................,.....,......-.........., """"'-- -.., .,. .... .
^;¡ '2.611rßo'lf7 Top-.¿)F-THE'f7:Jofl,..Jot;..o..o.71L-y....o,;---... '( t'~)"'"
,8 Ck-{(/ SoLID (Pf!.{)c.l1l?D -vJ/~s.(b#!.-s ~..l(P(:)lC. :.0\.-:,,';-_...
.._...- u.... . '--"0"_" .~~. . ........--., '~,..........-:.... .~. - ... .....,-.. .,....--.-. ..- ...- -., .
,... ,f;,...4S-(~'?~ .J,-=:.4Z.3....._---.-....---..,f-:.,bIX'15":;:,OO':>'lu_...--- ,. .
,'2-, , 'I ~)( S-
",':', fJ\:> 4-,~~ ;,4.~_~'-~' "~.;,I.íj~I~~":..:,'-~~:,~,'~~,:.~-~,'1).'~,"~.~.'.;"1,,'.', r~,' ~8;,~.~..
'. ¡': ; :' ',i' i:! ~;; i . :~(-Ol'-' '
..~_.. ", ":J-~ ~.... ~ I 0 X.'o:--. x-~-~~ ~~~-.J'5'5-..._"S\~=....---¿~~~--,~.~-~i_~~_=..-"~ ---=-=-~~~~....~~~:_~..-
~ '
'.. \2-..>(:5_-- - - _.....~ ---..--.. ~r&-\\o....._._.n..__:__--_.._-~. ...._...._,.. .._..._n_m____'_-"'-
. ~ ~-;.. Cð loX \ '2-. ,"::: . 714--l--~-4-2.04-0Q.9..- ~,,-- O"~ <-..
..._,?~x\Î5)'~ß[~~:;;.. .--...-"., -...--. - - -..., ..,
" (l
ftl-bV! D 17, x- ?o ~
~e'(
.... ""'--'-"-"--""'-'"
. _n ... ,.- .......-. ....... ,. - .
rorL\HE
\ST
Foùp.. . u> v(2..s,t: S
\h i j~"~ Ò..,:> 0 \dD GQ.QtJThD uvJ l-1ës B~S (Ji ~".o, ~ u
-n t2-.llt E .. -«. e~¡:~-O-f-,-ThE----~u..-._.- _~_'d': .. ~. .,.. 0 o~ ~ .
..., ..-'t/SCi- CZiI~-~c.-\Jl~ .b..ç.ot,,66~fE~.v'L 1j!5--j8~.._.ej,/-~~.ç, !.---.--..
,. f' II
; : . '.L.L . J-S
. _... ~ ",----_c----ü--'-:;-#::-4'-~gA(i.S-""'-@7~ ().{.:- l.L.ri,~vJfACC'-~"-""~--;- ;-- - -.-:--.-.-
'-' . f'V,.".".
.... - .
..... -... , --....
, ;'!
, . '
... .. .._, .., --'--_. "-'----'------..-----------..
"",,___,"d"""""
-_..... -
.. .. .... ...--..... .... .. '.._0
"
DAri€'"
4 of 4-
vJ lSf>€rz.- WI"'!)'
r~R eEL Z
lofSl98'
5tiT
Joß \JAHE
l/G"$fbN of ClttJF f<.ETß/tJl^f& w,4l-L (h -::.4/-)
EP,P, ~ 4;- tCC .{:..,JF- '2-:\ bA(~r-!:..t.
f -= 4 S ( 4 ~ );- '?ro o~
M.. ;.. ? C:.o Jl A:/3::> 4 f5 D #-+- I h
'2-
,
I.,~
/'
11<- '\ 8 (NÙ So L.ID 6 ~uiEÞ
wi H 4 B.A12- S. e I~/D'(' Cd;. '5")
J: . '2-)( .,'Ç :: ~ 0 D 2. ç
1'1,1(5
I ~
4-...0
'bbl
\, ç
I v.,- bPI/I,
~
+-W\: 4- ~o XI '2..
, ----\~~,s:--
, ~S\-' -
----+,:>--.;_4:~OXII2.. -: -ßS24-- <~~o~c
---- .-- -- ~,'2.-~,';Xt1obc5" - - ,
,Yl)-;. ~-Ç..(.OO2Ç)::- 10'-2-5 ~ J:; .5101 ) ~¥-z715"
-- -- ----p~i - - - -f~-i' -
x 1, ç;- I 4-4- - i... 2.t;o ,- ~ " 0 I \'.
u----- --- --------- -- -------,
-- -,.. ---- -
,I, ð. ~..
-- "H - --
"h -- ---------____--_H"U ------- .___m_u- '..
-- ..,____m___-__-- ---- -
..~--~ CJ\e;( ~-- " > K ¡OJ> P-, ~ ritE<; ~--=~~G~= iJ-- > ~~~¡,~-~:~: ';-~:E~~Z;~ - -~ ~-,-o,iC -
, b,:j~ \'2~'~o\xs: . , ,
- - -, '---______h____h______---
---"h--h,-----_----,h ------- --,-- - --- - -----'.- - -- -------------
- ~ I p, ~ l..n~
1'24t
'----------- ----- --
C- H ~('I'- ':> LA 0 oJ G"
C;f€:c..~_~ßD-"LD-__~~SL--____-'-:'_---_H_'--V------- - ~'o: - - _d, - ---~-~\'-'-----_u_-
-_._u_---~_:---- -~~~-~-':_~~=-=~~~~:s.~jJ u--~7:~1;~-1S~~~dX-~: ,6 -~--__:__,l_,o.~_._.
..C1{eL!.' ovett..TUP-IJINa. ,,- -. --------- ---- _3 ' -, ,.. '" - _n-
OIÍ-M.,:--+5(S": )~- 124'6 -.--
R.tv1. =-1-,5'xJ,? X!5D x-z..ç ;- 5(.,2. (ilkS): 703-
'2-
., 8'4-0\' 4-x I)(?::P ::' ' '?3fD {)"1)~-6bÐ-
- - __n_,,_u___h_-\JO.)ckJ(-4-'~~){2. = 'Z~ "(Z.'2S):--t95'----- ..
: 1'7--)It.~!.o~---: K'e,: ~,\.'2SX'\x\SO)(2. ,~ I '6X C2._}.;:n--~-7-5"--__h_m__-
'.
.,. _-'-_n____, -I? 0 ~ ~- ---. 'Z J ~ ~
---_.._------S~~O/~'6--~Fo~~- =-.4!; {~\r;L-).~-~~-~~-..-~---~ ------ "
, , '2..' ,--,'
. - -----, "n_- :--~~~Is1'NG -ñ~œ ~~-\;(¡?Ob)+~2.s"O'É-~_~__'-:h__L~__h'"
10'2-5 !.' !; '2- .
~If.~,. -=-/45"- :~..o'~'__:__h ' '.:.~q2.:+:~?;~:=.: 102.5 .
(,'bO .
- - -f/b;tllt)~- -11.-:x.-15'~~1?'(-- -----~-_:_~"~h _,_--_n_-----------
V;r tj;tt CHcI -~tIP-;'~~r~D ~ tJJ/it~8¡J~: _~L6;1 O~G._j;a_~.~~_- '-~-------:
()'?e-1=F-t ~~$ C? ltø"o.¿ {/-o1!.l:¿ONrAL ' -- . ,
'-h-"'n-----.------- - ,---
-..--. ,. -
. --- ---------------------- ----
-I'- u ~- ., \
_c2_._\-_--_':~-t=- () -AQ:.-:S --h)~ß-(), c. -V-S(tt -- Hn-
I :;;1 -C - ~, , , . --
--.0 - -_!>_--<"")~--_. _..!._g.)(.JctJ_D_l~g-ID'~__--_... -----~,---
-- 9../1'\ -- . v~AitJÅ~E:~'tSìe~ ~e..H
,?(' t.~ Rffbn.'I_~çÚ)H~.
I 'I
--- ~4 ~Ar2-<'::' -(? - Ú)--O. C. - -
-- - ---
0
I II
4-t
- 56
I II
7A'
Mß'j
- --- - ----
---- --- n
- m______--------u---- ---n__-_-
-- - -- --,----------------.-----
- ----- --,'--
- ----------- -------
- ------ ____--n--- ---- ------ ----~-1q11
-- ---- -- --
u---- --
--- - - --
_-d -- ----
-- -- - - ----------------------------
( II
I~
- 0-
-ør>
--- - ---- -- --
-0
-8
CÞ,
-;J./ '
-- -GL~~
- - - ----
--___n_- ----------- ----------------------- -------..-------
----------- ------------------
- - ---- ---------
. . ,
_3~~_~- ~~~-:- -
/,
~
- __n-----_H_--_- --
5 1-'0 u
f-4i 4- J.+bR(~D"nA.L
II -- - I I f<,'
g C I'll \J ?O(,_ID G ¡2Du \t:;: D l'~'M::\5Õo \
WA\£~ rgoó f\N6 Pf? Aec~IT,
'f
.ft- 4 ßæ-s (? Lb o,C, HÐeI"2... lTf
- - i,
.:ffSßA(LS @,(fe,o,c V6t.1.
2 _H:tL-4 ß.ðJlS
---;,-__--___m__--___-_____Uh - - ~SI"
/"'LGM tJ-~SðL.lD-~/4ðIJ7ED .(JM~lz;oo
- H -- n- --u ---
I'
=tt 4 BAilS --r¿> I go ,C,
-#:-- ~ú>tJT\
--___n,_____----- -------------- --
--, -- ---- --------------------_------__m-o
-- .. - --
u - -.
- -- - -- - -- - -- -- ----- - ----
No SCALE
( I.
~ß
I'" f\ -,l
, II
I -~ -
" I'
I ~?
- -- - -- -- ---- ---
6(/
~
('
p 0
^
C?
,
0
- -- --- -- ----
-- -------------,---------
--------- ..---- -------------------------
------'.u_-- ----------_uu----u-- ------ ---------
, 'I
--,..-, -":'..«>----- __-__n.. --
I /- II
'l- - '"
-2. _#4- ßI.~s Q)tJT - r .
" ( / ~\
~- (. M U )OL I 0 6~oIlTED f,., :/5ðo
-W1t TER P~ffNG-fB~ARLttT\
~ 4 ßI>.P-) @1'" O. (; HtJ((I:t;,
(I
-~ 4- ßÞ~) (? " 0\-(' VErLf.
--'DR.AltJþ..-G.8 S'iS1eM PEf.
t70ILS (l.E?fOl2T f-ێOHfA"
un --- __n__-
---_h- u..-
- ------ --_u_---------- - ---- li---"-
~ 4---ßÞ{2-8.@ I~.o.(-..
----------
! --~-+_c.o_tJr._--- u-- -- - - - _u_--
f ~
.._------- ----- -------
- hu.. ---
------------------- -...- --- -----
-- ---- ----------- --u----.. -
---------------
-..-.._-_.._-------------
- - u.. ..h- ,-
------- -- --
No CS£:,A,LE-
,---------------,,-'---_u_----..------- --------------
---
- - ---- ------------- _h - -____-_m- - -- un _u_-...---
--- -------..---u_-- -----
I
-------- -----------
-- ----------------------------------,----------,-------_..--- -
- --..---------------------- --------------- -
-- - ----- _n- ---------
- - - -- - -- --- - --- _u_- -_u- ..
-------..____h______u_-
- - - - ---
OCT-Ø6-~998 17:37 FROM
R,R. BRRRY & ASSOCIATES
TO
16192965564
P.Ol
, ~:" ;c'
;, ,
October 5. 1998
BARRY AND ASSOCIATI!$
GEOTECHNICAL ENGINëERING
p .0. Box 230348 '
.' Encinit8S, ,CA 9202~..o348
(760) 753.9940
; F~5-r¡; [ñì -fso n----~---r,"-:.\ì"
: I 0 ) r'=~-_IL_,_~J::~ ¡ " : :
,~' In," .. ;
, : ,i 9
, ",I ",L. ..
',:'1 ¡
~..
Whisper Winds Villa L~C
1402 orib1a Road
Del Max. Californ1a9.2014
Att: Mr. Majid Kharrat!
, ;
, ,
Subject:
Active ~ressure for Retaining Wall a.t,ba;~e :of cut slope
Parcel 2 of PM 17075 ' ;
Whisper W1ndDrive '
Encinitas"California " ,
:, '
Reta.inina Walls " ,;" ,
Retaining walls at the base Of the cut slope shoU!ð J6e designed in
accordance with the tolloWil'lg soil perimeters:' "
. ,;,
. ,
Soil TYD~
5quivalent
Fluid Pressure (PCF)
(Unrestrained Walls)
AdditiotlaltJriif6rm
pressure' (P:s~)
(Reetra1~Qd:~alls)
Native Soil
(Level Backfill)
2:1 backt11l
1. 5: 1
33
6xH~ ..'
45
65
, ....
*H~ He1ght of wall in feet
.. ..
Walls
shoUld be
adeQuately drained to prev~nt' ,build-up of'
hydrostatic pressures...
If you. have any questions. please call us at 76Ò.7S3..9940.
::,
'" ..
TOTAL P.01
"
i,
.. ¡..
i
I
I
I
!
. AUG-26-1998 13:37 FROM
. '
A. R. BARRY & ASSOCIATES
TO
P.01
~
16192965564
'. .
ej(. % -6. e..
Z\o&9V
BARRY AND ASSOCIATES
GEOTECHNIOAL ENGINEERING
P~O. Box 23Ò~48
Encinitas. CA 92023-0348 :
(~60) 753-994°\":" , '" \!:,'",R, [] WI,"', " ~ rn'-\
; i:\ ~ [C) LG U, 1!J l ~
I\Dlí ,
, Ii ,ì ;.v
-: \'\ n \! 2 j 19~8 \
:; \'! ',' "J \
',,\ "'_._'°:-:: :; \
August 23, 1998
WhisperWinðs Villa LLC
1402 Oribia ~oad
Del Mar, Ca11fornia92014
Att: Mr. Majid Kh~rrati
; ,
Subject:
UPDAT~D GEOtECHNICÞ~ INVESTIGATION
Parcel 2 of PM 17075
Whisper Wind Drive:
Encinitos, California
References:
1.
ROUGH GRAD!NG REPORT
Parcels 1, 2 and 3 ot
Parcell of PM 10526
Western Enð ot Whisper Win~ Drive
!ncinitas, California
Prepareð by Barry and Associates
Dated March 23, 1993
2.
, ,
" ,
'~RELIMINÀRY GEOTECHNICAL INVESTIGATION
Proþoseðsingle Family Residences
Parcell, PM 10526 '
Lo~ateð 'near tha western
terminus 'of 8th Street
Encinitas. California
Prepared by Barry anð Associates
Dated July 19, 1989
bear Mr. ~harra~i,
In response to your reqUest, 'we have reviewed the above referenced
report in regards ,to the re-grading and construction of a single-
t:am.ily residence. and garage for the subject property.
This
, ,
evaluation is based on a site inspection and review of vertinent
geo-:echnical data. No subsurface exploration or laboratory testing
Was conducted because of the limited scope ot this stUdy.
SITE CONDITIONS
Based on a visual inspectionot the subject property and the
¡::¡UG- 26-1998 13 ; 37 FROM
¡::¡ , R. EI=IRRY &. ASSOC I ATES
TO
1619296'55~
P.02
" '
August 23, 1998
W;O. # P-1622
þåge 2
adjacent properties. the site conðitioI1s remain'eSåênt1allY the
same as those ðisclos.ð in the referenced grading report.
PROPOSED GRAnING
Proposed grading will "include ~he lOWering of th~ existing house
pad by 3 feet. In addition the owner would like to increase the pad
area by trimming back the slope to a maximum of 1.5:1. We feel that
the format1onal soil discussed in the report will support a steeper
slope than 2:1. ho~ve~ at this point in time wewili'plan on a 2:1
cut slope with a 3 to 4 foot high retaining Wall ~upport1n~ a 3 to
4 foot vertical cut at "the base of the slope. If dui~ng grading the
formational material shows it will support a 1.~: l':~ Slo~ we will
provide a slope stability letter to the bu11ding:ðeÞartment.
CONCLUSIONS AND ~COMMENDAT~Qti~
General
.
".
Based
on
cur
review,'
the recommendations pres~nt~a
in
the
on the site.
ratereneed report are dornpa.t1ble with the geotechni~ål conditions
this office prior to the :r1nal plan approval fro~ the C.i ty of
Encin1tas, to insure that all the recornmenðat10nsp~eaented in the
The tinal:cuilding plans will have to ,be reviewed by
~eferençed report are incorporated into the plans.
Gradinq
.'
See grading specifications in rete:enc~ g.Otechnic~l report.
. ,
AUG-26-19'38 13:39 FROM
A. R. BARRY & ASSOCIATES
TO
16192965554
P.05
, .
" ",
~ A~\1U~t 23, 1998
, . W':'O.I ' p~ 1622
',' page: 3
Inspection and ~ðn;1tv Testirta
, ,
All t:ooting excavations should be inspected by a ,re~~esentative of,
" .
this firm prior to the placement Of steel.
Fill sijould be placed
while a reprasentat'ive'of thi:~ firm is present too1?$erve and test.
Should any unforeseen ~otechpical conditions be encountered during
',' , : , '. " '
the con5truction~øhase, additional recornrnendat~~ns maY,be
" '," ," :'
necessary. All of thë applicable recQnunendations ,11\ 'the: referenced
, , ""
geotechnicðl report sh?uld b$ implemented dùrinq ~he construction
~ ¡
phase. , : , .
, ' ", , ' '~ '
'.. ,.,'
:. ~,' ..
, ,
If YOU have any questions, please call us at (7~O)' :7~3~9940.
':, "
This opport'Jnity to be of sarvice is 9'!'eatly ap~r~c,1atElð.
. ;,:'
.; ,
, ' ,
I ~ , ;:
TOïR.. P,05
BARRY AND ASSOCIATES
GEOTECHNICAL ENGINEERING
P.o. Box 230348
Encinitas, CA 92023-0348
(760) 753-9940
Whisper Winds Villa LLC
1402 Oribia Road
Del Mar, California 92014
1
.1. .
Att: Mr. Majid Kharrati
Subject:
UPDATED GEOTECHNICAL INVESTIGATION
Parcel 2 of Parcell of PM 10526
Whisper Wind Drive
Encinitas, California
References:
Dear Mr. Kharrati,
ROUGH GRADING REPORT
Parcels 1, 2 and 3 of
Parcell of PM 10526
Western End of Whisper
Encinitas, California
Prepared by Barry and
Dated March 23, 1993
Wind Drive
Associates
2.
PRELIMINARY GEOTECHNICAL INVESTIGATION
Proposed Single Family Residences
Parcell, PM 10526
Located near the western
terminus of 8th Street
Encinitas, California
Prepared by Barry and Associates
Dated July 19, 1989
In response to your request, we have reviewed the above referenced
family residences
report in regards to the re-grading anå construction of a single-
and garage
for the
evaluation is based on a site inspection and review of pertinent
subj ect property.
This
geotechnical data. No subsurface exploration or laboratory testing
SITE CONDITIONS
was conducted because of the limited scope of this study.
Based on a visual inspection of the subject property and the
July 22, 1998
w.o. #P-1622
page 2
adjacent properties, the site conditions remain essentiall the same
as those disclosed in the referenced grading report.
PROPOSED GRADING
Proposed grading will include the lowering of the existing house
pad by 3 feet and re-grading of the existing cut slope to 1.5:1 in
the formational sandstone. This will extend the cut slope to the
north.
CONCLUSIONS AND RECOMMENDATIONS
General
Based
on
our
review,
the
recommendations
presented
in
the
referenced report are compatible with the geotechnical conditions
on the site.
The final building plans will have to be reviewed by
this office prior to the final plan approval from the City of
Encinitas, to insure that all the recommendations presented in the
referenced report are incorporated into the plans.
Gradinq
See grading specifications in referenced geotechnical report.
INSPECTIONS AND DENSITY TESTING
All footing excavations should be inspected by a representative of
this firm prior to the placement of steel.
Fill should be placed
while a representative of this firm is present to observe and test.
July 22, 1998
W.O. #P-1622
page 3
Should any unforeseen geotechnical conditions be encountered during
the
construction
phase,
additional
recommendations
may
be
necessary.
All of the applicable recommendations in the referenced
geotechnical report should be implemented during the construction
phase.
If you have any questions, please call us at (760) 753-9940.
This opportunity to be of service is greatly appreciated.
Respectfully
A.R. BARRY
ore
A.R. Barry, P.E.
Principal Engineer
.
, I
I
I
I
,
f
I
'..
August 19, 1993
CARDIFF GEOTECHNICAL
CONSULTING ENGINEERS AND GEOLOGISTS\..,....--2-:-, íf\\
\ \\j
Ii , ., A ¡9~8 I'! i
....-\ J
" ,? ' \ L GINEERING SER\'CES
i' '.\\1 \,:" \ . , EN CITY OF ENC\NITAS
~ ~ ~ ~ ~ ~~~~ \ '
~ at*'{' ~ c£J\\j\C:S
~t:.t\\Ñ~C\~~ ~
'i:-~ß\~ o'i: ~
Partne£.8h1þ
OBG, A California Limited
c/o Henry Tubbs
518 Whisperwind Drive
Encinitas, CA 92024
Subject:
ROUGH GRADING REPORT
Parcel 1 of PM 10526
Whisperwind Drive
Encinitas, California
Reference:
1.
ADDENDUM REPORT AND GRADING PLAN REVIEW
Parcel 1 of PM 10526
Whisperwind Drive
Encinitas, California
Prepared by Barry and Associates
Dated April 21, 1993
2.
ROUGH GRADING REPORT
Parcels 1, 2 and 3 of
Western end of Whisperwind Drive
Encinitas, California
Prepared by Barry and Associates
Dated March 23, 1993
3.
PRELIMINARY GEOTECHNICAL INVESTIGATION
Proposed Single-Family Residences
Parcel 1 of PM 10526
Located near the western
terminus of 8th Street
Encinitas, California
Prepared by Barry and Associates
Dated July 19, 1989
135 LIVERPOOL DRIVE. SUITE A . CARDIFF. CA 92007
(619) 753-3697. FAX (619) 753-4158
.
. '
Dear Mr. Tubbs:
In response to your request, we have performed field observations
and testing during the rough grading phase on the above referenced
property.
The results of our density tests and laboratory testing
are presented in this report.
Based on the results of our testing, it is our opinion that the
fill was placed in an adequate manner and compacted to a minimum
of 90 percent of the laboratory maximum dry density.
If you have any questions, please do not hesitate to contact us at
(619)
753-3697.
This opportunity to be of service is greatly
appreciated.
Respectfully submitted,
CARDIFF GEOTECHNICAL
j(~~
Mark Burwell
Geologist
J~~
Vithaya Singhanet, P.E.
Geotechnical Engineer
;~'
"
~¡
~
I
t
COMPACTION REPORT
Þiifcêl 1~of;PM;10526'
Whisperwind Drive-"
Encinitas, California
Prepared for:
Mr. Henry Tubbs
518 Whisperwind Drive
Encinitas, CA 92024
August 19, 1993
W.O. G-I04073
Prepared by:
CARDIFF GEOTECHNICAL
135 Liverpool Drive Suite A
Cardiff, California
August 19, 1993
W.o. IG-104073
Page 1
INTRODUCTION
This report presents the results of our observations and field
density testing on the subject property.
The project included the
cutting and filling of a previously graded hillside lot, in order
to develop a level building pad.
The t!9_~l!i)l.;L_-~~~:r;a~~~ti~nal" P~9
was ,undercut a miniumm. of 3.0 vertical"et and replaced with
compacted fill.
The results of our density tests are presented on
Table I.
The approximate locations of these tests are shown on
the enclosed Grading Plan, Plate I.
LABORATORY TEST DATA
The laboratory standard for determining the maximum dry density
was performed in accordance with ASTM D 1557-78.
Field density
tests were performed in accordance with ASTM D 1556.
The results
of
the
laboratory maximum dry density,
for the soil used as
compacted fill on the site, is summarized below:
Soil TvDe
DescriDtion
Maximum
Dry Density
(D.c.f. )
Optimum
Moisture (%)
A
Mixture of on-site
tan to brown silty
and fine grained sand
118.0
9.2
B
On-site deposits,
tan to brown fine
and medium-grained
sand
125.0
9.0
"
,~
'j,
i:
:'i
"
, '
August 19, 1993
W.O. IG-I04073
Page 2
GEOTECHNICAL CONDITIONS
Previous grading of the site gen~rated,~fill deposits .along ~~~H~F 1
s!?~e +n the southeasterJ1- and eastern ~t;..J:on of the lot.
t.œhe .
eJÇisting silty and fine-grained sand deposits were removed and
I
)
J
J
~
I
I
I
I
I
II
I
~
~
replaced as compacted fill, where encountered.
<underlying the
surficial
deposits,
dense
arkosic
sandstone
is present.
The
sandstone,
designated as Torrey Sandstone on published geologic
maps,
is well exposed along the 2: 1 cut slope in the western
portion of the site.
EXPANSIVE SOILS
The on-site deposits' are predominately granular deposits with a
potential expansion in the very low range.
DISCUSSION
The following is a discussion of the grading operations, as they
were performed on the site:
1.
All surface deleterious material was removed and disposed of
off-site, prior to the placement of fill.
2.
A minimum 12 foot wide key was excavated along the ba~e of
the proposed fill slope.
The key was extended into the
underlying
sandstone.
The
building
area
was
undercut
approximately 3.0 vertical feet below the proposed pad grade.
However, in the central portion of the pad, an undocumented
7.
8.
t
i-
Y
August 19, 1993
W.o. fG-104073
Page 3
fill
on-site
of
composed
materials
with
considerable
vegetation was encountered.
The buried fill was removed and
replaced with compacted fill.
was approximately 7.0 feet.
The maximum depth of removal
3.
Fill
excavated materials was
consisting of
a mixture
of
placed in lifts of about 6.0 to 8.0 inches thick.
4.
The fill was moistened as required, to achieve near optimum
moisture content, and compacted by track and wheel rolling
with heavy earth-moving equipment.
s.
The lli4.l1'..extends. a minimum of-5. 0 feet beyOAd,.the building
perimeter.
Fill slopes were overbuilt and trimmed'back to,a.
maximum gradient~of 2:1 (horizontal to vertical).
6.
The fill deposits have a potential expansion in the very low
range, within 3.0 feet of the building pad.
Based on selective testing, the fill was placed to a minimum
of
90
percent of
the
laboratory maximum dry density,
as
indicated by our test results.
The placement of additional fill deposits will be required
once the proposed retaining walls are completed.
August 19, 1993
W.o. IG-I04073
Page 4
CONCLUSIONS AND RECOMMENDATIONS
General
As per our discussion with Doug Logan of Logan Engineering, it is
our
understanding
that
the
proposed crib-type wall
along the
western side of the driveway will be changed to a conventional
masonry block retaining wall.
Additional changes include 25+
lateral feet of the proposed wall in the northeastern portion of
the site.
This wall will be relocated slightly southward in order
to obtain sufficient lateral distance from the base of the wall
footing to the face of the descending slope.
Foundations
Footings for the proposed structure should be a minimum of 12
inches wide and founded a minimum of 12 or 18 inches below the
lower
most
adjacent
grade
for one
and two
story
structures,
respectively.
A 12 inch by 12 inch grade beam should be placed
across the garage openi~g.
Steel reinforcement should consist of
\.
.,
four No. 4 bar~, two bars located 3.0 inches from the top of the
~,'
~..
~
g
;JJ'
,
footing and two bars
located 2.0
inches
from the base.
All
structural footings should be maintained a minimum of 8.0 lateral
feet from the face of the nearest slope.
Footings
founded a minimum of
12
or
18
inches
into approved
compacted fill should be designed for a bearing value of 1500
pounds per square foot.
Footings founded into competent sandstone
should be designed for a bearing value of 2000 p.s.f.
".
,..,
'!
The
bearing value
indicated
above is
August 19, 1993
W.O. #G-104073
Page 5
for the total dead and
frequently applied live loads.
This value may be increased by 33
percent. for short durations of loading, including the effects of
wind and seismic forces.
Resistance to lateral load may be provided by friction acting at
the
base
of
foundations
and
by
passive
earth
pressure.
A
coefficient
of
friction
of
0.35
may
be
used with
dead-load
forces.
A passive earth pressure of 250 pounds per square foot,
per foot of depth of fill or sandstone penetrated to a maximum of
1500 and 2000 pounds per square foot, respectively, may be used in
the design.
Slabs on Grade
Slabs
on grade
should be
a minimum of, 1.0 inches thick an~
reinforced in both directions with No.3 bars.placed 24 inches on
;
center.
The slab should be underlain by a minimum 4.0-inch sand
blanket
which
incorporates
a
minimum
6.0-mil
Visqueen
or
equivalent moisture barrier.
Utility Line Backfill
We recommend that all utilities be bedded in clean sand to at
least one foot above the top of the conduit.
The bedding should
be flooded in place to fill all the voids around the conduit.
On-
site granular material compacted to at least 90 percent relative
compaction may be utilized for backfill above the bedding.
, '
August 19, 1993
w.o. IG-I04073
Page 6
Retaininq Walls
The proposed walls which will retain a 2: 1 surcharge should be
designed to withstand an equivalent fluid pressure of 45 pounds
per cubic foot .
All retaining walls should be provided with an
adequate backdrainage system.
Backfill behind the walls should
consist of granular deposits compacted to a minimum of 90 percent
of the laboratory maximum dry density.
Temporary slopes excavated
in well-indurated sandstone should be trimmed to a gradient of
1/2:1.
Temporary
slopes
in
fill
should be trimmed to a 1: 1
gradient.
Drainage
All pad water should be directed away from foundations and around
the residence to area drains or the driveway.
All roof water
should be collected and conducted to the driveway or suitable
location
via
non-erodible
devices.
Pad water
should
not be
allowed to pond or flow over fill slopes.
CONSTRUCTION OBSERVATIONS
All
structural
footings
excavations
should be
observed
by
a
representative of this firm, prior to the placement of steel.
The placement of additional fill should be observed and tested by
a representative of this firm.
, .
August 19, 1993
W.o. IG-1O4073
Page 7
LIMITATIONS
This office assumes no responsibility for any alterations made
without our knowledge and written approval to the slope or pad
grade
on the subject lot,
subsequent to the issuance of this
report.
All ramps made though slopes and pads, and other areas of
disturbance which require
the
placement
of
compacted
fill
to
restore
them to the original
condition,
will
not be reviewed
unless
such
backfilling
operations
are
performed
under
our
observation and tested for required compaction.
ENCLOSURES. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .APPENDIX A
PLATE A
PLATE I
I ;
.m , .
APPENDIX "A"
LABORATORY TEST RESULTS
TABLE I
Field Dry Density and Moisture Content
Moisture Dry Relative
Test Test Content Density % Soil
No. Location Elev. % (pcf) Compaction. ~
1 See Map 188' 14.0 96.9 82* A
2 See Map 188' 13.8 94.7 80* A
3 See Map 188' 13.8 97.5 83* A
4 See Map 188' 12.2 107.1 91 A
5 See Map 190' 8.1 112.2 95 A
6 See Map 192" 8.8 114.7 97 A
7 See Map 194' 8.1 113.4 96 A
8 See Map 196' 8.1 112.2 95 A
9 See Map 198' 7.1 113.4 96 A
10 See Map 200' 9.8 118.6 95 B
11 See Map 202' 9.8 116.5 93 B
12 See Map 197' 10.1 112.1 95 A
13 See Map 199' 12.9 119.9 96 B
14 See Map 201' 11.3 109.9 93 A
15 See Map 202' 12.2 110.2 93 A
16 See Map Grade 11.6 115.0 92 B
17 See Map Grade 12.3 117.5 94 B
*
Failed test, area scarified and aerated, recompacted
. , I, ,
~ I a
I
, ,,'
,,--..,..,. -----""'"
, ..- .-
..' -'--'-'-"'-"~"",,"".'.,'.'-"-""-'" ::'.,
CONC. INTERCEPToR DRAI~'
, .
-....-.-.. - _... ,- .------... ., - " -- -...
. .-.. , ..-.- -.. - .
18" COMPACTED
".......,.....--.,.....,-'..---..,..-
. .... ...... .
Ô ()tÞ
1>11
¿) Þ ~
{)IJð
. ¡).4fJ .
1 0 D Þ(J
FABRIC ð 0"
, ð Þ
()
ð ()
tJo
ð
I> ()
Ó IJ
¿.J
ð ð
3/4 to CRUSHED 'ROCK OR . .
.-.
. ,
¡MARIDRAIN6000 OR EQUIVALENT
d. -----.-
, ...-.,...,------....--.. p. ........--.-.--"'"
PERVIOUS FILTER'
.._m""'"
4" DIA. PERFORATED PIPE
()
I> -0 ()
OR WEEP HOLES
I
i
I
:1
," , " .
." .... _. ....' -.-..
. -----,..-..-.
, I~.JBC ~~':n: I~l X ~ <G}
¡
~ ~ JI.a J1:n
N.T.S~
,PLATE
A
\
I
April 21, 1993
BARRY AND ASSOCIATES
GEOTECHNICAL ENGINEERING
P.O. Box 348
Encinitas, CA 92023-0348
(619) 753-9940
l ,,/,/ ,;'
>-'1\' ,r""--"-------'"." ,-'-', ! :,1 '.
Ii ,<I ~' " """ IUi
¡ I \ \ " ",'.
luuL ,: "', ~
\ ENGINEERiNlJ SEA' ICES
CiTY OF ENCINITAS
OBG, A California Limited Partnership
c/o Henry Tubbs'
518 Whisper Wind Drive
Encinitas, CA 92024
ADDENDUM REPORT AND GRADING PLAN REVIEW
Párcel 1 of PM 10526.
Whisper Wind Drive
Encinitas, California
Subject:
References:
1.
2.
Dear Mr. Tubbs,
This
has
report
ROUGH GRADING REPORT
Parcels 1, 2 and 3 of
Parcel 1 of PM 10526
Western End of Whisper Wi~d Drive
Encinitas, California
Prepared by Barry and Associates
Dated March 23, 1993
PRELIMINARY GEOTECHNICAL INVESTIGATION
Proposed Single Family Residences
Parcel 1, PM 10526
Located near the western
terminus of 8th street
Encinitas, California
Prepared by Barry and Associates
Dated July 19, 1989
been prepared
your request
and
presents
at
supplemental recommendations for the development of the site.
This
study is based on
a review of the proposed grading plan and
geotechnical data obtained during our previous investigation.
(lliffi ~ li U \lj ß{])
MAY 07 1993
ENGINEERING SERVICES
CITY OF ENCINIT AS
April 21, 1993,
w.o. #P-131S
Page 2
PROPOSED DEVELOPMENT
As indicated in reference No.
1, rough grading of the 1 ot w~
conducted during July~and August, 1990.
The development of the
parcel was conducted in accordance with a previous grading plan and
residential design.
The new grading plan'lior the development of the parcel was prepared
by Logan Engineering.
The plan indicates that a larger building
pad will be required in order to accommodate a new single family
residence.
Proposed grading includes a variable height 2:1 fill
slope constructed along the southeastern portion of the parcel and
a driveway along the western portion of the lot.
The base of the
existing 2:1 cut slope along the western portion of the site will
be retained by a variabl e height, up to 8.0 feet, gravi ty-type
wall.
GEOTECHNICAL CONDITIONS
Artificial Fill
Previous grading of the site has generated fill deposits along 2:1
slope in the southeastern and eastern portion of the parcel.
In
addition, the building pad was partially undercut and replaced with
fill deposits for the previous grading and residential plans.
The
fill deposits are composed of on-site materials and are classified
as silty and fine-grained sand.
These deposits have a potential
expansion in the very low range.
April 21, 1993
w.o. Ip-1315
Page 3
Formational Rock
The site is underlain by dense arkosic sandstone which has commonly
been designated as the Torrey Sandstone on published geologic maps.
The sedimentary rock is well exposed along the 2:1 cut slope in the
western portion of the parcel.
Groundwater
No evidence of perched or shallow groundwater tables was observed
on the site.
However, it is possible that minor seepage problems
may occur after construction.
These are usually minor phenomena,
often associated with over-irrigation and poor drainage control.
CONCLUSIONS
1.
Minor
eroslon
of
the
site
has
resulted
from
the
recent
prolonged
rains.
However,
no
evidence
of
deep-seated
instability was observed.
It is anticipated that the proposed
grading of the site will correct erosional damage.
2.
The proposed grading plans are acceptable from a geotechnical
viewpoint
provided
the
following
recommendations
are
implemented during the design and construction phases.
, .
April 21, 1993
w.o. #P-1315
Page 4
RECOMMENDATIONS
Gradinq
;Pr9þ()'s~d ;:fi 11 ~lopes ,shoulci bt:!provided with aminimurn 12-foot-wide
key along the base of the slope.
All 'fi 11 should be keyed and
benched into competent sandstone or previously placed fill.
The
building pad should be cut/fill transitions undercut to a minimum
of 3.0 vertical feet and replaced with properly compacted fill.
The fill should extend a minimum of 5.0 lateral feet beyond the
perirneter,of the foundation.
All fill should be placed in 6.0- to
8.0-inch lifts, moistened as required and compacted to a minimum of
90
percent of
the laboratory maximum dry density.
Excavated
sandstone is suitable for re-use provided it is cleaned of all
debris and large fragments which do not break up during compaction.
All
fill
and cut
s lopes should not
exceed a gradient
of
2:1
(horizontal
to ver:.:.,::al).
Additional
recornmendations will
be
provided during the grading phase.
Foundations
Footings for the pro?osed structure should be a minimum of 12
inches wide and founded a minimum of 12 inches or 18 inches below
the lower most adjacent grade for one- and two-story structures,
respectively.
A 12-inch by 12-inch grade beam should be placed
across the garage opening.
steel reinforcement should consist of
four No.4 bars, two bars located 3.0 inches from the top of the
footing and two bars
located 2.0
inches
from the base.
All
. .
April 21, 1993
W.o. Ip-1315
Page 5
s~ruc~ural footiqgs should be maintained a min~um of 8.0 lateral.
"e,
feet from the face of the nearest slope.
r.o~.~i~9~founded a minimum of 12 inches or 18 inches into approved
compacted fi 11 should be designed for a bearing val ue of 1500
pounds per square foot.
Footings founded into competent sandstone
should be designed for a bearing value of 2000 pounds per square
foot.
The beari~g value indicated above is for the total of dead and
frequently applied live loads.
This value should be increased by
33 percent for short durations of loading, including the effects of
wind and seismic forces.
Resistance to lateral load may be provided by friction acting at
the base of foundations and by passive pressure.
A coefficient of
friction of 0.35 should be used with dead-load forces.
A passive
earth pressure of 250 pounds per square foot per foot of depth of
fill or sandstone penetrated to a maximum of 1500 and 2000 pounds
per square foot, respectively, may be used in the design.
Slabs on Grade
Slabs
on grade
should be
a minimum of
4.0
inches
thick
and
reinforced in both directions with No.3 bars placed 24 inches on
center,.
The slab should be underlain by a minimum 4.0-inch sand
blanket which incorporates a minimum G.O-mil Visqueen or equivalent
April 21, 1993
w.o. #P-131S
Page 6
moisture barrier.
utility trenches underlying the slab may be
backfilled
with
the
on-site
granular
materials.
However,
sufficiently compacting the bac~fill deposits .i!iY.. damage or break
shallow utility lines.
As such, minor settlement of the backfill
in the trenches is anticipated.
In order to reduce the possibility
of cracks occurring, the slab should be provided with additional
reinforcement to þridge over trenches.
Retaininq Walls
The proposed wall, which will
retain a 2:1 surcharge, should be
designed to withstand an equivalent fluid pressure of 45 pounds per
cubic foot.
All
retaining
wall s shoul d be provided wi th an
adequate backdrainage system.
Backfill behind the walls should
consist of granular deposits compacted to a minimum of 90 percent
of the laboratory maximum dry density.
Temporary slopes excavateà
in well-indurated sandstone should be trimmed to 1/2:1.
Temporary
slopes in fill should be trimmed to a 1:1 gradient.
Drainaqe
All pad waters should be directed away from foundations and around
the residence to an approved location.
All roof waters should be
collected and conducted to the driveway or suitable location via
non-erodible devices.
Pad water should not be allowed to pond or
flow over fill slopes.
April 21, 1993
w.o. #P-131S
Page 7
Inspections and Density Testinq
All
structural
footing
excavations
should
be
inspected
by
a
representative of this firm prior to the placement of any steel.
All fill should be placed while a representative of this firm is
present to observe and test.
Plan Review
A copy of the final building plans should be submitted to this
office
for
review
prior
to
the
initiation
of
construction.
Additional recommendations may be necessary at that time.
UNFORESEEN CONDITIONS
Barry and Associates
assumes no
responsibility
for
conditions
encountered which differ from those conditions found and described
in the preliminary geotechnical investigation report.
LIMITATIONS
This
report
is
prese:1ted
with
the
provision
that
it
is
the
responsibility of the owner or the owner's representative to bring
the information and recommendations given herein to the attention
of the project's architects and/or engineers so that they may be
incorporated into pla~s.
If conditions encountered during construction appear to differ from
those described in this report, our office should be notified so
Apri 1 21, 1993
W.O. #P-1315
Page 8
that
we
may
consider
whether
modifications
are
needed.
No
responsibility for construction compliance with design concepts,
specifications or recommendations given in this report is assumed
unless
on-site
review
is
performed
during
the
course
of
construction.
The subsurface conditions, excavation characteristics and geologic
structure described herein are
based on individual
exploratory
excavations
made
on
the
subject
property.
The
subsurface
conditions,
excavation
characte::-istics
and
geologic
structure
discussed should in no way be const::-~e¿ to reflect any variations
which may occur among the exploratory excavations.
Please note that fluct~ations in the level of groundwater may occur
due to variations i~ ::-a:nfall, temperature and other factors not
evident at the time measurements were made and reported herein.
A.R. Barry and Associates assumes no responsibility for variations
which may occur across the site.
The conclusions and rec~~mendations of this report apply as of the
current date.
In time, however, changes can occur on a property
whether caused
by
acts
of man
or nature on this
or
adjoining
properties.
Additionally, changes in professional standards may be
brought
about
by
legislation
or
the
expansion
of
knowledge.
Consequently, the conclusions and reco~mendations of this report
may be rendered wholly or partially invalid by events beyond our
April 21, 1993
w.o. #P-131S
Page 9
control.
This report is therefore subject to review and should not
be relied upon after the passage of three years.
The professional judgments presented herein are founded partly
on our assessment of the technical data gathered, partly on our
understanding of
the
proposed
construction and
partly
on
our
general experience in the geotechnical field.
Our engineering work
and
the
judgments
given
meet
present
professional
standards.
However, in no respect do we guarantee the out~ome of the project.
If you have any questions, please do not hesitate to contact us at
(619) 753-9940
This opportunity to be of service is appreciated.
Respectfully submitted,
A. R. BARRY AND ASSOCIATES
J1(~~
Mark Burwell
Geologist
afZ~
A. R. Barry~ P.E.
Principal Engineer
¡:¡UG-26-1998 13:38 FROM
¡:¡. R. EJ=IRRY & ¡:¡SSOCI¡:¡TES
TO
1619'2965564
f
, ,
P.03
, ", ""'" ",' n
~ ~;;c;~
, .z.~°V'
, 4
SUbject:
ROUGH GRADING REPORT
Parcels, 1" ,2 and 3 ,of
parcel,' 1 0'£ :,PM 10526 ;
Wes't4arn ,', End 0 f Whisperw1nd
Encirii tas, ~, C'a11,forri1a
BARRY AND ASSOCIATeS
GEOTEOHNICAL ENGINEERING' , :" .
' P.O. Box 23Ó~48 '//;:~;---;:~~ ~~\
Enciniœs, CA 92023-034~/,;:'-"/' \'.;.:-~\,;/-:~ \~\
(7eO) 753-9940 \, ----- ,',.' \:)
, ~ I), '.: ':1, " 'öjO
'[.;.\
" (', .\ "', ¡ '; , ,\;.<;!,'
\",\ "-\J\C
\)""~\ ':';"",,',,:,,~,,;::,5t-,;~þ..S
, ~\.s?};~..c>._,
\ '. ~C'l'-)""",:;"IÌY, ',". -
\ ...' C\"'" ','
\, , . ~. '
. , ,
March 23, 1993, ,:
Ms. Novine Macð.onald.:'
1427 Valleda Lane
Encin1tas, CA 92024
, " ,
, ,
, I
Drive
Reference:
" ' ,
" 'PRBLIMiNARY GBO".t'ECHNICAL ¡NVESTIÒAT:tÓN .
Pz:oposed Single-f'and.ly Resiðenc:ei' "
Parcel~, PM 10526
LQoateã near the western
~~1~UB ot Stþ Str&e~
£n~init~s, cal1fornia
P~pared by Barry and Associates
Dated JUly 19, 1989
Dear Ms, Macdonald,'
.! ,
, ,
In response t,o 'your, rfi¡!quest, We have preþared a;,:t;'ough grading
report on the abOve :referenceð property. The rough grading Phase
was cond¡,¡,cteddurihgJuly and August. 1990. .'
Based on our recent gitä inspection and previous denS1ty testing in
1990, it is our opinion that the till was placed, 1~ ,an adequate
manner and was compacted to: a minimum of 90' pe~c.nt of the
laboratory maxírnum dr~"density. However. due tor6¿~ntprolongeð
rains, remedial gr~di~g of thé parcels will be n.c~s'arý.
" .
If YOU have any qU~st10hS, please do not hesitate t'ó ,contact us at
(ô19) 753-9940. " ",
Thi,s opportunity to be ot service is appreciated. '
.., ,
," ,
.. <-:
: :::,
..
, ,
: : '>¡ ",'
, ,;;.;
- ,,; , " ,,'....
, ,':";' ¡
~
. .
March 23, 1993
W.O. #G-1100
Page 2
INTRODUCTION AND SITE HISTORY
A preliminary geotechnical investigation on the above referenced
property was prepared by this firm in June,
1989.
The rough
grading phase for the three subject parcels was conducted during
July and August, 1990.
At that time, the project was placed on
hold.
The proposed drainage facilities and slope planting were not
completed.
As a result, erosion and minor sloughing occurred along
the exposed areas during the recent prolonged rains.
Remedial
clean up and erosion control was recently initiated on the site by
Mike Scott Grading.
The results of our density tests are presented on Table I.
The
approximate locations of these tests are shown on the enclosed "As-
Built" grading plan prepared by Logan Engineering.
LABORATORY TEST DATA
The laboratory standard for determining the maximum dry density was
performed in accordance with ASTM D 1557-78.
Field density tests
were performed in accordance with ASTM D 1556.
The results of the
laboratory maximum dry density, for the soil used as compacted fill
on the site, is summarized below:
Description
Maximum Dry Density
(pc f)
Optimum
Moisture (%)
Tan to brown fine- and
medium-grained sand
125
9.8
March 23, 1993
w.o. #G-1100
Page 3
GEOTECHNICAL CONDITIONS
The geotechnical conditions encountered during the grading phase
were
in
substantial
conformance
with
those
described
in
our
preliminary geotechnical report.
Existing fills were encountered
along the berm in the northern portion of Parcel 2 and the pad area
in Parcell.
Alluvial deposits are present along the northern
portion of Parcels 2 and 3.
Underlying the surficial deposits,
medium-grained arkosic sandstone is present.
This sedimentary unit
has commonly been designated as the Torrey Sandstone on published
geologic maps.
DISCUSSION
The following is a discussion of the grading operations, as they
were performed on the site:
1.
All surface deleterious material was removed from the proposed
fill pad area.
2.
A 12 to 15 foot wide key was excavated at least 2.0 feet into
the
underlying
sedimentary
rock,
along
the
base
of
the
proposed fill slopes.
The excavated materials were replaced
as compacted fill.
The fill was keyed and benched in to
sedimentary rock.
3.
All fill was placed in 6.0 to 8.0 inch lifts, moistened as
required
to
achieve
near
optimum
moisture
content
and
4.
March 23, 1993
W.O. #G-1100
Page 4
compacted by track rolling with heavy earthmoving equipment.
Where failing tests occurred, the area was reworked until 90
percent of the laboratory maximum dry density was achieved.
5.
The maximum depth of fill is approximately 15 vertical feet,
along the southeastern portion of Parcel 3.
6.
The
fill
a minimum of
placed
90
to
of
the
percent
was
laboratory maximum dry density,
as indicated by our test
results.
7.
The fill deposits are predominately granular deposits, with an
expansion potential in the very low to low range.
8.
The alluvial deposits in the northern portion of Parcels 2 and
3 were not removed and replaced as compacted fill.
This area
is designated as a non-structural fill.
CONCLUSIONS
1.
Based on our
site inspection,
no evidence of
significant
failures or instability was observed along the fill slopes.
However,
due to the recent prolonged rains,
erosion was
observed along the slope faces and along the cut/fill driveway
in Parcel 3.
Remedial grading will be required, in order to
correct the erosional features.
2.
It is likely that new grading plans will be prepared for each
of the parcels.
In lieu of remedial grading at this time, it
. ,
March 23, 1993
W.O. #G-ll00
Page 5
is suggested that corrective grading be combined with new
grading plans for each of the parcels.
RECOMMENDATIONS
1.
Revised or new grading plans for each of the parcels should be
submitted
this
office
for
review.
Pertinent
to
recommendations for remedial and new grading will be prepared
at that time.
2.
A copy of the proposed building plans should be submitted to
this office.
Additional recommendations for foundations and
retaining walls will be necessary.
LIMITATIONS
1.
This office assumes no responsibility for any alterations made
without our knowledge and written approval to the slope or pad
grade on the subject parcels, subsequent to the issuance of
this report.
All ramps made through slopes and pads,
and
other areas of disturbance which require the placement of
compacted fill to restore them to the original condition, will
not
be
are
reviewed
unless
such
backfilling
operations
performed
under
observation
for
required
and
tested
our
compaction.
Loose material cast over compacted slopes shall
negate our certification of slope face compaction, unless the
material is removed in accordance with our instructions.
AUG-26-1998
13:39
FROM
A.R.
BARRY & ASSOCIATES
TO
16192965564
"":~..
,
, ,
,
','
'"
.. d..
, .
. '
',;'
"
, ,.'"
, ., "
" . - " ",
M~~C:b\23" ,1993
W;.~Q t, #~¡-11ÒO '
~~. : ' EV¡ " , 1 "
':'fH,'r.:",i, '
please do not heaita~~t:òcóntact
, c
~ t,:, ~,¡'!; J.., '
:~. ¡
¡ ~, ; ",: I ,
service is, greatly a~p~ïa~èd.
: ,";' j
i
" j
¡
,,'.
, " :: ," ,"'.
I f you have any: qU~$t'~on$ .
753-9940.
(619)
, ,
'" ;',
.'
, 'rh1s
,: 'f',
" v"
opportuni ty: ,to 'Qe
, " .'.
of
. '
. ,
'" ,
. "
, '
, '
, ,',
~, I:'
," ': "
, ~ " .
dH ',',
" ,,', ~ c'
. , ,. "
~ , ;,' '.
-'
"" - '
, ) -- '.'
,', '
',', ,"",
; ; : :', ;:~:
"
" .
f'
, -
, ,
',',
.' ~,} ~';:':::
. ,¡ ';', ',',
:,~ : '..
, ;
, ..
- ,
, " ,,'
¡'
,: <', '
; ~ , "
,;
',0'
, ,
"
", ' :; >,::
'."'
" :','
:,:~,i~,~:::.
, ,
, ,
.-
. : ,
:
,0 , ~ ': ...
, ,
, ,
" .. ; / :'"
" , ",',
" ,
, .. ',; ':.,':
. ~ ~¡;~:.-
: i ~ . ~ =,:'
~HU?';"
~,~H¡' .'
(H H t: '
" , .. " '.' '
. ;,
"
P.04
us at
-. '
,.,
"
"
'.
. "
.; ,
"
i "
, -
.'
I, '
i
,,'
, ..
",
" "
, ,
'.
..', '
",
.
, .
, '
, ê
,j
:,'
"', ;
, ,
"
'" '..
, ,
. .
APPENDIX "A"
LABORATORY TEST RESULTS
TABLE I
Field Dry Density and Moisture Content
Moisture Dry Relative
Test Test Approx. Content Density %
No. Location Elev. % (pc f) Compaction
Parcel 3
1 See Map 175' 9.8 113.1 90
2 See Map 177' 10.1 114.8 92
3 See Map 178' 9.3 116.1 93
4 See Map 180' 9.4 115.1 92
5 See Map 182' 10.0 113.8 91
6 See Map 184' 9.2 114.6 92
7 See Map 186' 8.3 115.2 92
8 See Map 188' 9.8 114.8 92
9 See Map 190' 11.9 114.6 92
Parcel 2
10 See Map 200' 10.6 113.8 91
11 See Map 202' 10.1 114.2 91
12 See Map 204' 14.4 113.7 91
13 See Map 206' 12.2 114.8 92
Parcel 1
14 See Map 195' 10.1 113.1 90
15 See Map 197' 11. 2 114.7 92
16 See Map 199' 12.1 115.2 92
17 See Map 201' 9.8 116.1 93
SOUTHERN CALIFORNIA
February 12, 1991
SOIL
AND
Mr. Denton Kimball
c/o Scott Richards
2093 San Elijo Avenue
Cardiff, California 92007
Report No.1
SUB J EC T: R e p 0 r t 0 fIn -. p 1 ace Den s i t Y T est s, Sewer T r e n c h
Backfill, \vhispering Winds Drive and Rancho Santa Fe
Road, Olivenhain area of San Diego County, California.
Gentlemen:
. In accordance with your request, this report has been prepared
to present the results of the in-place density tests performed
in the sewer trench backfill, at the subject site. These tests
were performed by Southern California Soil & Testing, Inc.
between December 27, 1990 and January 31, 1991.
Field density tests were performed by our firm in accordance
with ASTM D 1556-82. The tests were performed at various
locations
in
the
sewer
trench backfill.
Test
locations
were
chosen by our field representative. The results and locations
of the field tests are provided on the attached plates.
Maximum dry density determinations were
representative samples of the soils used in
backfill according to ASTM D 1557-78, Method A.
performed on
the compacted
The results of
these tests were used in conjunction with the field density
tests to determine the percent of relative compaction of the
compacted backfill material.
6280 RIVERDALE STREET. SAN DIEGO. CA 92120 . 619-280-4321, FAX 619-280-4717. P.O, BOX 600627, SAN DIEGO, CA 92160
678 ENTERPRISE STREET. ESCONDIDO, CA 92029 . 619-746-4544, FAX 619-746-6579
SCS&T 9021151
February 12, 1991
page 2
If you should have any questions after reviewing this report,
p.lease do not hesitate to contact this office. This
opportunity to
appreciated.
be
of
I?rofessional
service
is
sincerely
Respectfully submitted,
SOUTHERN CALIFORNIA SOIL & TESTING, INC.
Charles H. Chris~ian,
R.G.E.
#00215
Supervisor
,...-:t ,-?
~~
"r.
C:-"b£.~
CHC/OH/MH/Vp
c c: ( 4 ) S u bm i t t e d
(1) SCS&T, Escondido
. 08 NAME:
Sewer Trench Backfill
N-PLACE DENSITY TESTS, ASTM D1556-82
JOB NO: 9021151
PLATE NO: 1
---------------------------------------------------------~------------------
, EST
:"JO.
DATE
12-27-90
12-27-90
12-27-90
12-27-90
12-27-90
12-28-90
12-28-90
12-28-90
12-28-90
1 ø,
1-7-91
11
1-7-91
12
1-7-91
l-7-91
14
-_-Î-91
13
1-7-91
16
1-8-91
17
1-8-91
18
19
1-8-91
1-8-91
20
1-8-91
21
1-9-91
22
1-9-91
LOCATION
ELEVATION MOISTURE DRY DEN. SOIL REL.COMP.
(feet,MSL) (percent) (p.c.f.) TYPE (percent)
Private Driveway
Main, Station 16+40
Private Driveway
Main, Station 15+00
Private Driveway
Main, Station 14+60
Private Driveway
Main, Station 14+00
Private Driveway
Main, Station 13+25
Private Driveway
Main, Station 19+00
private Driveway
Main, Station 18+20
Private Driveway
Manhole #7,
Station 17+38
Rancho Santa Fe Road
parkway, Main,
Station 1+15
Whisperwi~d Drive
Manhole #4,
Station 10+86
Whisperwind Drive
Main, Station 9+25
Whisperwind Drive
Main, Station 10+25
Whisperwind Drive
Main, Station 11+10
Whisperwind Drl~e
Main, Station 11+80
Private Driveway
Manhole #5,
Station 12+66
Private Driveway
Lateral, Station 19+32
private Driveway
Lateral, Station 18+61
Retest of S4
Rancho Santa Fe Drive
parkway, Main,
Station 2+30
Rancho Santa Fe Drive
parkway, Main,
Station 3+20
Whisperwind Drive
Lateral, Station 11+75
Whisperwind Drive
Lateral, Station 11+75
169.Ø
162.0
154.5
153.0
151.0
189.5
181.0
176.5
116.0
135.0
119.0
129.5
136.0
142.0
147.5
193.0
170.0
153. ø
117.5
119.5
142.0
143.5
13.ó
11.1
14.3
9.9
11.1
16.3
13.6
11.1
14.9
14.9
15.3
8. 7
14.9
16.3
14.3
17.6
17.6
13.6
14.3
14.9
11. 1
14.9
114.5
110.3
114.6
101.6
111.3
113.5
113.3
108.3
106.7
112.2
113.0
108.1
1Ø9.8
1;:38.4
108.6
116.7
115.0
110.2
106.9
104.6
109.0
109.6
1
96.4
1
92.8
1
96.5
1
85.5
1
93.7
1
95.5
1
95.4
1
91.2
2
92.7
1
94 .4
1
95.1
1
91.0
1
92.4
1
91. 2
1
91.4
1
98.2
1
96.8
1
2
92.8
92.9
2
90.9
1
91.8
1
92.3
JOB NAME: Sewer Trench Backfill JOB NO: 9021151
PLATE NO: 2
IN-PLACE DENSITY TESTS, ASTM 01556-82
-----------------------------------------------------------------------------
TEST DATE LOCATION ELEVATION MOISTURE DRY DEN. SOIL REL.COMP.
~O. (feet,MSL) (percent) (p.c.f.) TYPE ( percent)
523 1-9-91 pr i va te Driveway 152.Ø 14.9 101.8 1 85.7
Manhole #6,
Station 14+32
S24 1-10-91 Rancho Santa Fe Road 120.5 19.0 106.7 2 92.7
Parkway, Main,
Station 3+10
S25 1-10-91 Rancho Santa Fe Road 119.0 11.1 107.5 1 90.5
parkway, Main,
Station 3+30
S26 1-10-91 Rancho Santa Fe Road 121.0 16.3 115.6 1 97.3
parkway, Main,
Station 4+10
S27 1-11-91 Retest of S23 152." 14.9 113.2 1 95.3
828 1-14-91 Rancho Santa Fe Road 120.0 14.9 115.k3 1 96.8
Par kwa y, Main,
Station 4+50
S29 1-18-91 Rancho Santa Fe Road 118.5 13.6 99.6 1 86.5
parkway, Main,
Station 4+10
530 1-18-91 Rancho Santa Fe Road 120.0 16.3 114.8 1 96.6
parkway, Main,
Station 4+70
531 1-19-91 Rancho Santa Fe Road 123.0 14.9 111.5 1 93.9
parkway, Main,
Station 4+75
S32 1-18-91 Rancho Santa Fe Road 124.0 13.6 112.9 1 95.0
parkwa y, Main,
Station 5+00
533 l-21-91 Rancho Santa Fe Road 119.0 13.0 107.9 1 90.8
parkway, Main,
Station 5+20
534 1-21-91 Retest of S29 118.5 15.6 111.8 1 94.1
S35 1-22-91 Rancho Santa Fe Road 120.0 10.5 109.1 1 91.8
Par kwa y, Ma in,
Station 5+90
S36 1-22-91 Rancho Santa Fe Road 122.0 11.1 109.8 1 92.4
parkway, Main,
Station 5+60
S37 1-24-91 Rancho Santa Fe Road 120.0 10.5 109.2 1 91.9
parkway, Main,
Station 6+45
S38 1-24-91 Rancho Santa Fe Road 123.1,3 11 .1 112.4 1 94.6
parkway, Main,
Station 6+70
539 1-24-91 Rancho Santa Fe Road 119.5 9.9 106.4 3 88.7
parkway, Main,
Station 7+15
S4Ø 1-24-91 Retest of S39 119.5 11.1 108.7 3 90.7
", OB N AM E :
Sewer Trench Backfill
~-PLACE DENSITY TESTS, ASTM D1556-82
JOB NO: 9021151
PLA TE NO: 3
----------------------------------------------------------------------------
" EST
~O.
DATE
1-25-91
1-28-91
43
1-28-91
44
1-28-91
45
1-29-91
46
1-29-91
47
1-29-91
48
49
50
1-30-91
1-3Ø-91
1-30-91
51
1-30-91
52
l-3Ø-91
53
1-31-91
LOCATION
ELEVATION MOISTURE DRY DEN. SOIL REL.COMP.
( fee t , MS L) (pe r c e n t) (p. c . f .) T Y P E ( pe r c e n t )
121.:3
Rancho Santa Fe Road
parkway, Hain,
Station 7+60
Rancho Santa Fe Road
parkway, Main,
Station 8+00
Rancho Santa Fe Road
parkway, Lateral,
Station 8+58
Rancho Santa Fe Road
parkway, Main,
Station 8+40
Rancho Santa Fe Road
parkway, Manhole #3,
Station 9+05
Rancho Santa Fe Road
parkway, Lateral,
Station 7+60
Rancho Santa Fe Road
parkway, Manhole #2,
Station 6+18
Retest of S45
Retest of S44
Rancho Santa Fe Road
parkway, Lateral,
Station 6+92
Rancho Santa Fe Road
parkway, Lateral,
Station 6+92
Rancho Santa Fe Road
parkway, Manhole #1,
S"tation 4+40
Rancho Santa Fe Road 199.Ø
parkway, Private Drive,
Station 19+90
119.0
120.0
121.5
118.0
120.0
121.0
118.0
121.5
119.0
122.5
117.5
13.6
13.6
13.0
11.1
16.3
16.3
13.6
14.9
16.3
15.6
13.6
16.3
11 . 7
110.5
110.2
108.7
105.9
104.4
107.9
109.0
110.4
110.9
110.5
108.6
114.1
109.5
3
3
3
1
3
3
1
1
1
1
1
1
1
MAXIMUM DENSITY AND OPTIMUM MOISTURE DETERMINATIONS, ASTM 1557-78
-----------------------------------------------------------------
SOIL
TYPE
1
2
3
METHOD
DESCRIPTION
A
Light Brown, Silty SAND (SM)
A
Light Green, Clayey, Silty
Sand (SC)
A
Brown, Silty, Sand (SM)
OPTIMUM
MOISTURE
(percent)
12.5
14.9
10.1
HAXIMUM
DENSITY
( pc f)
118.8
115.1
119.9
92.2
91.9
90.7
89.1
87.1
90.0
91.8
92.9
93.4
93.0
91.4
96.0
92.2
K&S ENGINEERING
Planning Engineering Surveying
HYDROLOGICAL ANALYSIS
FOR
WHISPER WIND PARCEL 2
IN
CITY OF ENCINITAS
- --.-------...-..... ..
í~ r-
I~
0 ~-,...-
WI
L_..,
F t\, (, '.'
,j
IN 9801B
.---.'" '
July 21, 1998
~(/9L
DAT /
r Court, Suite 200.San Diego, California 92108. (619)296-5565 . Fax (619)296-5564
'"
r'
I
TABLE OF CONTENTS
1.HYDROLOGY DESIGN MODELS
2.HYDROLOGIC CALCULATIONS .......................... APPENDIX A
3.TABLES AND CHARTS ................................ APPENDIX B
4. HYDROLOGY MAPS ................................... APPENDIX C
..
1.
HYDROLOGY DESIGN MODELS
A.
DESIGN METHODS
THE RATIONAL METHOD IS USED IN THIS HYDROLOGY STUDY; THE RATIONAL
FORMULA I S AS FOLLOWS:
Q = CIA, WHERE: Q= PEAK DISCHARGE ¡N CUBIC FEET/SECOND *
C = RUNOFF COEFFICIENT (DIMENSIONLESS)
I = RAINFALL INTENSITY IN INCHES/HOUR
A = TRIBUTARY DRAINAGE AREA IN ACRES
*1 ACRE INCHES/HOUR = 1.008 CUBIC FEET/SEC
THE OVERLAND FLOW METHOD IS ALSO USED IN THIS HYDROLOGY STUDY; THE
OVERLAND FLOW FORMULA IS AS FOLLOWS:
To= [1. 8 (l.l-C) (L) .5] / (S%) 1/3
C = RUNOFF COEFFICIENT
L = OVERLAND TRAVEL DISTANCE IN FEET
S = SLOPE IN PERCENT
To= TIME IN MINUTES
B.
DESIGN CRITERIA
- FREQUENCY, 100 YEAR STORM.
- LAND USE PER SPECIFIC PLAN AND TENTATIVE MAP.
- RAIN FALL INTENSITY PER COUNTY OF SAN DIEGO 1993 HYDROLOGY
DESIGN MANUAL.
C.
REFERENCES
- COUNTY OF SAN DIEGO 1993, HYDROLOGY MANUAL.
- COUNTY OF SAN DIEGO 1992 REGIONAL STANDARD DRAWING.
- HAND BOOK OF HYDRAULICS BY BRATER & KING, SIXTH EDITION.
APPENDIX A
(2. HYDROLOGIC CALCULATIONS)
OFF-SITE HYDROLOGY
SAN DIEGO COUNTY
RATION AL-HYDROLOGY
PROGRAM PACKAGE
Rational Hydrology Study
Date: 7-21-1998
*USER SPECIFIED HYDROLOGY INFORMATION*
Rational method hydrology program based on
San Diego County Flood Control Division
1985 Hydrology Manual
Stonn Event(Year) = 100,00
Map data precipitation entered:
6 HOUR, Precipitation(Inches) = 2.900
24 Hour Precipitation(Inches) = 5,200
Adjusted 6 Hour Precipitation (Inches) = 2,900
P6/P24 = 55.8 %
San Diego Hydrology Manual "C" Values Used
Runoff Coefficients by RATIONAL METHOD
+++++++++++++++++++++++++++++++++++++++++++++++++++++++++++++++++++++++++++
Process &om Point/Station 1.000 to Point/Station 2,000
u* INITIAL AREA EVALUATION ***
Decimal Fraction Soil Group A = .000
Decimal Fraction Soil Group B = ,000
Decimal Fraction Soil Group C = ,000
Decimal Fraction Soil Group D = 1.000
RURAL (lots> 1/2 acre) runoff coefficient = .4500
Area Type is: RURAL(Greaterthan 1/2 Acre)
Time of concentration computed by the Natural
Watersheds nomograph, (App, X-A)
TC = [11.9*Length(Mi)^3)/(Elevation Change)]^.385*60(MINIHR)
+ 10 ßÚn,
Initial Subarea Flow Dist. = 670.00
Highest Elevation = 321.00
Lowest Elevation = 225,00
Elevation Difference = 96,00
TC = [(11.9* .1269**3)/( 96.00)]**..385 = 2.475
+ 10 Min. = 12.475 Min.
100.00 Year Rainfall Intensity(In,/Hr,) = 4,237
Subarea(Acres) = 3,20 Subarea Runoff{CFS) = 6.10
Total Area(Acres) = 3,20 Total Runoff{CFS) = 6.10
TC(MIN) = 12.47
+++++++++++++++++++++++++++++++++++++++++++++++++++++++++++++++++++++++++++
Process &om Point/Station 2.000 to Point/Station 3,000
u* PIPEFLOW TIME (USER SPECIFIED SIZE) u*
Upstream point elevation = 216,00
Downstream point elevation = 206,00
Flow length(Ft.) = 200,00 Mannings N = .015
No.ofpipes= 1 Requiredpipeflow(CFS)= 6.10
Given pipe size (In,) = 24,00
Calculated Individual Pipe flow (CFS) = 6,10
Nonnal flow depth in pipe = 6,05 (In.)
Flow top width inside pipe = 20.84 (In.)
Velocity = 9,821 (Ft/S)
Travel time (Min,) = .34 TC(min,) = 12.81
+++++++++++++++++++++++++++++++++++++++++++++++++++++++++++++++++++++++++++
Process &om Point/Station 4.000 to Point/Station 2.000
... INITIAL AREA EVALUATION ...
Decimal Fraction Soil Group A = ,000
Decimal Fraction Soil Group B = .000
Decimal Fraction Soil Group C = ,000
Decimal Fraction Soil Group D = 1.000
RURAL (lots> 1/2 acre) runoff coefficient = .4S00
Area Type is: RURAL(Greaterthan 1/2 Acre)
Time of concentration computed by the Natural
Watersheds nomograph. (App. X-A)
TC = [l1.9.Length(Mi)^3Y(Elevation Change)]^.38S.60(MIN/HR)
+ 10 min.
Initial Subarea Flow Dist. = 300.00
Highest Elevation = 326.00
Lowest Elevation = 27S,OO
Elevation Difference = S1.00
TC = [(11.9. .0568"3Y( 51.00)]"..38S = 1.248
+ 10 Min, = 11.248 Min.
100.00 Year Rainfall Intensity(1n./Hr.) = 4.529
Subarea(Acres) = .50 Subarea Runoffl:CFS) = 1.02
Total Area(Acres) = .50 Total Runoffl:CFS) = 1.02
TC(MIN) = 11.25
+++++++++++++++++++++++++++++++++++++++++++++++++++++++++++++++++++++++++++
Process &om Point/Station 2,000 to Point/Station S,OOO
... PIPEFLOW TIME (USER SPECIFIED SIZE) ...
Upstream point elevation = 216.00
Downstream point elevation = 201.00
Flow length(Fl) = 125.00 Mannings N = ,OIS
No. of pipes = I Required pipe flow (CFS) = 1.02
Given pipe size (In.) = 24.00
Calculated Individual Pipe flow (CFS) = 1.02
Nonnal flow depth in pipe = 2.0S (In.)
Flow top width inside pipe = 13.42 (In,)
Velocity = 7.852 (Ft/S)
Traveltime (Min.) = ,27 TC(min,) = 11.51
End of computations.,.
TOTAL STUDY AREA(ACRES) = 3,70
ON-SITE HYDROLOGY
SAN DIEGO COUNTY
RATION AL-HYDROLOGY
PROGRAM PACKAGE
Rational Hydrology Study
Date: 7-21-1998
*USER SPECIFIED HYDROLOGY INFORMATION*
Rational method hydrology program based on
San Diego County Flood Control Division
1985 Hydrology Manual
Stonn Event(Year) = 100,00
Map data precipitation entered:
6 HOUR, Precipitation(Inches) = 2,900
24 Hour Precipitation(Inches) = 5,200
Adjusted 6 Hour Precipitation (Inches) = 2.900
P6/P24 = 55,8 %
San Diego Hydrology Manual "C" Values Used
Runoff Coefficients by RATIONAL METHOD
I
+++++++++++++++++++++++++++++++++++++++++++++++++++++++++++++++++++++++++++
Process ITom Point/Station 1.000 to Point/Station 2,000
..* INITIAL AREA EVALUATION ..*
Decimal Fraction Soil Group A = ,000
Decimal Fraction Soil Group B = ,000
Decimal Fraction Soil Group C = ,000
Decimal Fraction Soil Group D = 1.000
SINGLE FAMILY runoff coefficient = ,5500
Initial Subarea Flow Dist. = 15.00
Highest Elevation = 215.00
Lowest Elevation = 206,80
Elevation Difference = 8,20
Time of concentration calculated by the Urban
Areas overland flow method (APP X-C) = 1.00 Min.
TC = [1.8*(1.1-C)*DIST ANCE^,5Y(% SLOPE^( 1I3)J
TC = [1.8*(1.1- ,5500)*( 15.00^.5Y( 5.46^(113)}=
100,00 Year Rainfall Intensity(In./Hr,) = 4.884
Subarea(Acres) = ,03 Subarea Runoff(CFS) = .08
Total Area(Acres) = .03 Total Runoff(CFS) = .08
TC(MIN) = 10,01
1.006 USE TC=IO MIN.
+++++++++++++++++++++++++++++++++++++++++++++++++++++++++++++++++++++++++++
Process from Point/Station 2.000 to Point/Station 3.000
..* PIPEFLOW TIME (USER SPECIFIED SIZE) ..*
Upstream point elevation = 205.30
Downstream point elevation = 204,85
Flow length(Ft.) = 45,00 Manning¡¡ N = ,013
No. of pipes = 1 Required pipe flow (CFS) =
Given pipe size (In,) = 4,00
Calculated Individual Pipe flow (CFS) = ,08
Nonna! flow depth in pipe = 1.82 (In.)
Flow top width inside pipe = 3.98 (In,)
Velocity = 2,090 (Ft/S)
Travel time (Min,) = ,36 TC(min,) = 10.36
,08
+++++++++++++++++++++++++++++++++++++++++++++++++++++++++++++++++++++++++++
Process ITom Point/Station 2,000 to Point/S1.'ltion 3,000
*** SUBAREA FLOW ADDITION
***
100,00 Year Rainfall Intensity(In,/Hr.) = 4,775
Decimal Fraction Soil Group A = .000
Decimal Fraction Soil Group B = .000
Decimal Fraction Soil Group C = .000
Decimal Fraction Soil Group D = 1.000
SINGLE FAMILY runoff coefficient = .5500
Subarea(Acres) = .04 Subarea RunofJ(CFS) =
Total Area(Acres) = .07 Total RunofJ(CFS) =
TC(MIN) = 10.36
,11
.19
+++++++++++++++++++++++++++++++++++++++++++++++++++++++++++++++++++++++++++
Process ttom Point/Station 3.000 to Point/Station 4,000
*** PIPE FLOW TIME (USER SPECIFIED SIZE) ***
Upstream point elevation = 204,85
Downstream point elevation = 204.40
Flow length(Ft) = 45,00 Mannings N = .013
No. of pipes = 1 Required pipe flow (CFS) =
Given pipe size (In,) = 4,00
Calculated Individual Pipe flow (CFS) = ,19
Normal flow depth in pipe = 3,19 (In,)
Flow top width inside pipe = 3.21 (In,)
Velocity = 2.485 (Ft/S)
Travel time (Min.) = .30 TC(min,) = 10.67
.19
+++++++++++++++++++++++++++++++++++++++++++++++++++++++++++++++++++++++++++
Process ttom Point/Station 3,000 to Point/Station 4,000
*** SUBAREA FLOW ADDITION ***
100.00 Year Rainfall Intensity(In./Hr,) = 4,687
Decimal Fraction Soil Group A = .000
Decimal Fraction Soil Group B = .000
Decimal Fraction Soil Group C = .000
Decimal Fraction Soil Group D = 1.000
SINGLE FAMILY runoff coefficient = .5500
Subarea(Acres) = ,02 Subarea RunofJ(CFS) =
Total Area(Acres) = ,09 Total RunofJ(CFS) =
TC(MIN) = 10,67
.05
,24
+++++++++++++++++++++++++++++++++++++++++++++++++++++++++++++++++++++++++++
Process from Point/Station 4,000 to Point/Station 5,000
*** PIPEFLOW TIME (USER SPECIFIED SIZE) ***
Upstream point elevation = 204.40
Downstream point elevation = 204,09
Flow length(Ft.) = 31.00 Mannings N = ,013
No, of pipes = 1 Required pipe flow (CFS) =
Given pipe size (In.) = 6,00
Calculated Individual Pipe flow (CFS) = ,24
Normal flow depth in pipe = 2.72 (In,)
Flow top width inside pipe = 5,97 (In,)
Velocity = 2.738 (Ft/S)
Traveltime (Min,) = ,19 TC(min.) = 10.86
.24
+++++++++++++++++++++++++++++++++++++++++++++++++++++++++++++++++++++++++++
Process from Point/Station 4,000 to Point/Station 5.000
*** SUBAREA FLOW ADDITION ***
100,00 Year Rainfall Intensity(In,/Hr.) = 4,634
Decimal Fraction Soil Group A = .000
Decimal Fraction Soil Group B = ,000
Decimal Fraction Soil Group C = ,000
Decimal Fraction Soil Group D = 1.000
SINGLE FAMILY runoff coefficient = ,5500
Subarea(Acres) = ,03 Subarea RunofttCFS) =
Total Area(Acres) = ,12 Total RunofttCFS) =
TC(MIN) = 10.86
.08
,31
+++++++++++++++++++++++++++++++++++++++++++++++++++++++++++++++++++++++++++
Process from Point/Station 5,000 to Point/Station 6.000
*.. PIPE FLOW TIME (USER SPECIFIED SIZE) *..
Upstream point elevation = 204,09
Downstream point elevation = 203.83
Flow length(Fl) = 26,00 Mannings N = .013
No, of pipes = 1 Required pipe flow (CFS) =
Given pipe size (In.) = 6.00
Calculated Individual Pipe flow (CFS) = ,31
Nonnal flow depth in pipe = 3,21 (In,)
Flow top width inside pipe = 5.99 (In.)
Velocity = 2,936 (Ft/S)
Traveltime(Min.)= .15 TC(min,)= 11.00
,31
+++++++++++++++++++++++++++++++++++++++++++++++++++++++++++++++++++++++++++
Process from Point/Station 5.000 to Point/Station 6,000
..* SUBAREA FLOW ADDITION ..*
100,00 Year Rainfall Intensity(In./Hr.) = 4,594
Decimal Fraction Soil Group A = ,000
Decimal Fraction Soil Group B = ,000
Decimal Fraction Soil Group C = .000
Decimal Fraction Soil Group D = 1.000
SINGLE FAMILY runoff coefficient = .5500
Subarea(Acres) = .02 Subarea RunofttCFS) =
Total Area(Acres) = .14 Total RunofttCFS) =
TC(MIN) = 11.00
.05
,36
+++++++++++++++++++++++++++++++++++++++++++++++++++++++++++++++++++++++++++
Process from Point/Station 6,000 to Point/Station 7.000
..* PIPEFLOW TIME (USER SPECIFIED SIZE) ***
Upstream point elevation = 203.83
Downstream point elevation = 203.48
Flow length(Ft.) = 35,00 Mannings N = ,013
No, of pipes = 1 Required pipe flow (CFS) =
Given pipe size (In,) = 6,00
Calculated Individual Pipe flow (CFS) = .36
Nonnal flow depth in pipe = 3.52 (In,)
Flow top width inside pipe = 5,91 (In,)
Velocity = 3,042 (Ft/S)
Traveltime(Min,)= ,19 TC(min,)= 11.19
.36
+++++++++++++++++++++++++++++++++++++++++++++++++++++++++++++++++++++++++++
Process from Point/Station 6,000 to Point/Station 7.000
*.. SUBAREA FLOW ADDITION ***
100,00 Year Rainfall Intensity(In./Hr,) = 4.543
Decimal Fraction Soil Group A = .000
Decimal Fraction Soil Group B = .000
Decimal Fraction Soil Group C = ,000
Decimal Fraction Soil Group D = 1.000
SINGLE FAMILY runoff coefficient = .5500
Subarea(Acres) = ,03 Subarea RunofttCFS) =
Total Area(Acres) = ,17 Total RunofttCFS) =
TC(MIN) = 11.19
.07
.44
+++++++++++++++++++++++++++++++++++++++++++++++++++++++++++++++++++++++++++
Process from Point/Station 7,000 to Point/Station 8,000
..* PIPEFLOW TIME (USER SPECIFIED SIZE) ..*
Upstream point elevation = 203.48
Downstream point elevation = 203.16
Flow length(Fl) = 32,00 Mannings N = .013
No, of pipes = 1 Required pipe flow (CFS) =
Given pipe size (In,) = 6,00
Calculated Individual Pipe flow (CFS) = .44
Nonnal flow depth in pipe = 4,00 (In,)
Flow top width inside pipe = 5.66 (In.)
Velocity= 3,162(Ft/S)
Traveltime(Min,)= ,17 TC(min,)= 11.36
.44
+++++++++++++++++++++++++++++++++++++++++++++++++++++++++++++++++++++++++++
Process from Point/Station 7.000 to Point/Station 8.000
n* SUBAREA FLOW ADDITION *n
100.00 Year Rainfall Intensity(In./Hr,) = 4.500
Decimal Fraction Soil Group A = ,000
Decimal Fraction Soil Group B = ,000
Decimal Fraction Soil Group C = .000
Decimal Fraction Soil Group D = 1.000
SINGLE FAMILY runoff coefficient = .5500
Subarea(Acres) = .02 Subarea Runoffl:CFS) =
Total Area(Acres) = .19 Total Runoffl:CFS) =
TC(MIN) = 11.36
,05
.49
+++++++++++++++++++++++++++++++++++++++++++++++++++++++++++++++++++++++++++
Process from Point/Station 7,000 to Point/Station 8.000
*n CONFLUENCE OF MINOR STREAMS ***
100,00 Year Rainfall Intensity(In,/Hr.) = 4.500
ALONG THE MAIN STREAM NUMBER: I
The flow values used for the stream: 1 are:
Time ofconcentration(min,) = 11.36
Rainfall intensity (in.lhrl) = 4.50
ToL'l1 flow area (Acres) = ,19
Total runoff(CFS) at confluence point =
.49
+++++++++++++++++++++++++++++++++++++++++++++++++++++++++++++++++++++++++++
Process from Point/Station 9,000 to Point/Station 10,000
*n INITIAL AREA EV ALUA nON n*
Decimal Fraction Soil Group A = .000
Decimal Fraction Soil Group B = .000
Decimal Fraction Soil Group C = .000
Decimal Fraction Soil Group D = 1.000
SINGLE FAMILY runoff coefficient = ,5500
Initial Subarea Flow Dist, = 35.00
Highest Elevation = 207,67
Lowest Elevation = 206,70
Elevation Difference = .97
Time of concentration calculated by the Urban
Areas overland flow method (APP X-C) = 4,17 Min.
TC = [1.8*(1.1-C)*DIST ANCE^,5)1(% SLOPE^(l/3)]
TC = [1.8.(1.1- ,5500).( 35,OO^,5)1( 2,7^(l/3))= 4,17 USE TC=1O MIN.
100,00 Year Rainfall Intensity(In./Hr,) = 4,886
Subarea(Acres) = .02 Subarea Runoffl:CFS) = ,05
Total Area(Acres) = .02 Total Runoffl:CFS) = ,05
TC(MIN) = 10,00
+++++++++++++++++++++++++++++++++++++++++++++++++++++++++++++++++++++++++++
Process from Point/Station 10,000 to Point/Station 11.000
.n PIPEFLOW TIME (USER SPECIFIED SIZE) ...
Upstream point elevation = 203,64
Downstream point elevation = 203.41
Flow length(Fl} = 23.00 Marmings N = .013
No, of pipes = 1 Required pipe flow (CFS) =
Given pipe size (In,) = 4.00
Calculated Individual Pipe flow (CFS) = .05
Nonnal flow depth in pipe = 1.45 (In.)
Flow top width inside pipe = 3.85 (In.)
Velocity = 1.875 (Ft/S)
Travel time (Min.) = .20 TC(min.) = 10.21
,05
+++++++++++++++++++++++++++++++++++++++++++++++++++++++++++++++++++++++++++
Process ftom Point/Station 10,000 to Point/Station 11.000
*** SUBAREA FLOW ADDITION ***
100.00 Year Rainfall Intensity(In./Hr.) = 4.823
Decimal Fraction Soil Group A = ,000
Decimal Fraction Soil Group B = .000
Decimal Fraction Soil Group C = .000
Decimal Fraction Soil Group D = 1.000
SINGLE FAMILY runoff coefficient = .5500
Subarea(Acres) = .05 Subarea RunofI{CFS) =
Total Area(Acres) = .07 Total RunofI{CFS) =
TC(MIN) = 10.21
,13
,19
+++++++++++++++++++++++++++++++++++++++++++++++++++++++++++++++++++++++++++
Process from Point/Station 11.000 to Point/Station 8,000
*** PIPEFLOW TIME (USER SPECIFIED SIZE) ***
Upstream point elevation = 203.41
Downstream point elevation = 203.16
Flow length(Ft) = 25,00 Marmings N = .013
No, of pipes = 1 Required pipe flow (CFS) =
Given pipe size (In,) = 4.00
Calculated Individual Pipe flow (CFS) = ,19
Nonnal flow depth in pipe = 3,20 (In,)
Flow top width inside pipe = 3,20 (In.)
Velocity = 2.486 (Ft/S)
Travel time (Min.) = .17 TC(min.)= 10.37
,19
+++++++++++++++++++++++++++++++++++++++++++++++++++++++++++++++++++++++++++
Process from Point/Station 11.000 to Point/Station 8,000
*** CONFLUENCE OF MINOR STREAMS ***
*** Compute Various Confluenced Flow Values ***
---
100.00 Year Rainfall Intensity(In,/Hr.) = 4.772
ALONG THE MAIN STREAM NUMBER: 1
The flow values used for the stream: 2 are:
Time of concentration(min.) = 10,37
Rainfall intensity (in./hrl) = 4,77
Total flow area (Acres) = ,07
ToL'l1 runoff(CFS) at confluence point =
,19
Confluence infonnation:
Stream runoff Time Intensity
Number (CFS) (min,) (inch/hour)
----------------------- --
1 .49 11.36
2 ,19 10,37
QSMX(l) =
+ 1.000* 1.000* ,5)
+ ,943*1.000* .2)
.664
QSMX(2) =
+1.000* ,913* ,5)
+ 1.000* 1.000* ,2)
4.500
4,772
.632
Rainfall intensity and time of concentration
used for 2 streams,
Individual stream flow values are:
.49 .19
Possible confluenced flow values are:
.66 ,63
Individual Stream Area values are:
.19 .07
Computed confluence estimates are:
Runoff{CFS) = ,66 Time(min.) = 11.363
Total main stream study area (Acres) = ,26
+++++++++++++++++++++++++++++++++++++++++++++++++++++++++++++++++++++++++++
Process from Point/Station 8,000 to Point/Station 12,000
... PIPEFLOW TIME (USER SPECIFIED SIZE) ...
Upstream point elevation = 203,16
Downstream point elevation = 202,86
Flow length(Fl) = 30,00 Mannin~ N = .013
No, of pipes = 1 Required pipe flow (CFS) =
Given pipe size (In,) = 8.00
Calculated Individual Pipe flow (CFS) = .66
Nonnal flow depth in pipe = 4.23 (In.)
Flow top width inside pipe = 7.99 (In.)
Velocity = 3.544 (Ft/S)
Traveltime (Min.) = .14 TC(min,)= 1LSO
,66
+++++++++++++++++++++++++++++++++++++++++++++++++++++++++++++++++++++++++++
Process from Point/Station 8,000 to Point/Station 12.000
... SUBAREA FLOW ADDITION ...
100.00 Year Rainfall Intensity(In./Hr,) = 4.464
Decimal Fraction Soil Group A = .000
Decimal Fraction Soil Group B = .000
Decimal Fraction Soil Group C = ,000
Decimal Fraction Soil Group D = 1.000
SINGLE FAMILY runoff coefficient = .5500
Subarea(Acres) = ,03 Subarea Runoff{CFS) =
Total Area(Acres) = .29 Total Runoff{CFS) =
TC(MIN) = 1LSO
.07
,74
+++++++++++++++++++++++++++++++++++++++++++++++++++++++++++++++++++++++++++
Process from Point/Station 12,000 to Point/Station 13,000
... PIPEFLOW TIME (USER SPECIFIED SIZE) ...
Upstream point elevation = 202.86
Downstream point elevation = 202.41
Flow length(Ft.) = 45,00 Maruùn~ N = .013
No, of pipes = 1 Required pipe flow (CFS) =
Given pipe size (In,) = 8,00
Calculated Individual Pipe flow (CFS) = ,74
Nonnal flow depth in pipe = 4.52 (In,)
Flow top width inside pipe = 7.93 (In,)
Velocity = 3,634 (Ft/S)
Travel time (Min,) = ,21 TC(min,)= 11.71
.74
+++++++++++++++++++++++++++++++++++++++++++++++++++++++++++++++++++++++++++
Process from Point/Station 12.000 to Point/Station 13,000
... SUBAREA FLOW ADDITION ...
100.00 Year Rainfall Intensity(In,/Hr,) = 4.413
Decimal Fraction Soil Group A = .000
Decimal Fraction Soil Group B = .000
Decimal Fraction Soil Group C = ,000
Decimal Fraction Soil Group D = 1.000
SINGLE FAMILY runoff coefficient = .5500
Subarea(Acres) = ,01 Subarea Runoff{CFS) =
Total Area(Acres) = .30 Total Runoff{CFS) =
TC(MIN)= 11.71
,02
.76
+++++++++++++++++++++++++++++++++++++++++++++++++++++++++++++++++++++++++++
Process ffom Point/Station 13.000 to Point/Station 14,000
*u PIPEFLOW TIME (USER SPECIFIED SIZE) u*
Upstream point elevation = 202.41
Downstream point elevation = 201.60
Flow length(Fl) = 38,00 Mannings N = ,013
No, of pipes = I Required pipe flow (CFS) =
Given pipe size (In.) = 8,00
Calculated Individual Pipe flow (CFS) = ,76
Nonnal flow depth in pipe = 3.67 (In,)
Flow top width inside pipe = 7.97 (In.)
Velocity = 4.869 (Ft/S)
Traveltime(Min.)= .13 TC(min.)= 11.84
.76
+++++++++++++++++++++++++++++++++++++++++++++++++++++++++++++++++++++++++++
Process ffom Point/Station 13.000 to Point/Station 14,000
*u SUBAREA FLOW ADDITION ***
100.00 Year Rainfall Intensity(In./Hr.) = 4,382
Decimal Fraction Soil Group A = .000
Decimal Fraction Soil Group B = ,000
Decimal Fraction Soil Group C = ,000
Decimal Fraction Soil Group D = 1.000
SINGLE FAMILY runoff coefficient = ,5500
Subarea(Acres) = .03 Subarea Runoff{CFS) =
Total Area(Acres) = ,33 Total Runoff{CFS) =
TC(MIN) = 11.84
,07
.83
+++++++++++++++++++++++++++++++++++++++++++++++++++++++++++++++++++++++++++
Process ffom Point/Station 13.000 to Point/Station 14.000
u* CONFLUENCE OF MINOR STREAMS ***
-----
---
100,00 Year Rainfall Intensity(In,/Hr.) = 4,382
ALONG THE MAIN STREAM NUMBER: 1
The flow values used for the stream: 1 are:
Time of concentration(min,) = 11.84
Rainfall intensity (in./hrl) = 4.38
Total flow area (Acres) = .33
Total runoff(CFS) at confluence point =
.83
+++++++++++++++++++++++++++++++++++++++++++++++++++++++++++++++++++++++++++
Process ffom Point/Station 15.000 to Point/Station 16,000
u* INITIAL AREA EVALUATION ***
Decimal Fraction Soil Group A = .000
Decimal Fraction Soil Group B = .000
Decimal Fraction Soil Group C = ,000
Decimal Fraction Soil Group D = 1.000
SINGLE FAMILY runoff coefficient = ,5500
Initial Subarea Flow Dist. = 30,00
Highest Elevation = 204,00
Lowest Elevation = 203.40
Elevation Difference = .60
Time of concentration calculated by the Urban
Areas overland flow method (APP X-C) = 4.30 Min,
TC = [1.8*(1.1-C)*DlST ANCE^.5)/(% SLOPE^(I/3)]
TC = [1.8*(1.1- ,5500)*( 83,OO^.5)/( 2,O^(113)])= 4.3
USE TC= 10,0 MIN.
100.00 Year Rainfall Intensity(In./Hr.) = 4,871
Subarea(Acres) = .03 Subarea RunofJ{CFS) =
Total Area(Acres) = .03 Total RunofJ{CFS) =
TC(MIN) = 10.05
.08
.08
+++++++++++++++++++++++++++++++++++++++++++++++++++++++++++++++++++++++++++
ProcessûomPoint/Station 16,OOOtoPoint/Station 14.000 I
... PIPEFLOW TIME (USER SPECIFIED SIZE) ...
Upstream point elevation = 201.90
Downstream point elevation = 201.60
Flow length(Ft.) = 30.00 Mannings N = .013
No. of pipes = 1 Required pipe flow (CFS) =
Given pipe size (In,) = 4.00
Calculated Individual Pipe flow (CFS) = ,08
Nonnal flow depth in pipe = 1.81 (In.)
Flow top width inside pipe = 3.98 (In.)
Velocity = 2.089 (Ft/S)
Travel time (Min.) = .24 TC(min,) = 10.29
.08
+++++++++++++++++++++++++++++++++++++++++++++++++++++++++++++++++++++++++++
Process &om Point/Station 16,000 to Point/Station 14.000
... CONFLUENCE OF MINOR STREAMS ...
... Compute Various Contluenced Flow Values ...
100,00 Year Rainfall Intensity(In,/Hr.) = 4,797
ALONG THE MAIN STREAM NUMBER: 1
The flow values used for the stream: 2 are:
Time ofconcentration(min,) = 10,29
Rainfall intensity (in./hrl) = 4,80
Total flow area (Acres) = .03
Total runoff(CFS) at confluence point =
,08
Confluence infonnation:
Stream runoff Time Intensity
Number (CFS) (min,) (inch/hour)
1 ,83 11.84
2 ,08 10.29
QSMX(I) =
+ 1.000.1.000. .8)
+ ,913.1.000. ,1)
.908
QSMX(2) =
+ 1.000. .869. .8)
+1.000.1.000. .1)
.806
4.382
4.797
Rainfall intensity and time of concentration
used for 2 streams,
Individual stream flow values are:
,83 .08
Possible contluenced flow values are:
.91 .81
Individual Stream Area values are:
,33 .03
Computed confluence estimates are:
RunofJ{CFS) = ,91 Time(min,)= 11.841
Total main stream study area (Acres) = ,36
+++++++++++++++++++++++++++++++++++++++++++++++++++++++++++++++++++++++++++
Process &om Point/Station 14.000 to Point/Station 17,000
... PIPEFLOW TIME (USER SPECIFIED SIZE) ...
Upstream point elevation = 201,60
Downstream point elevation = 189,50
Flow length(Fl) = 43.00 Mannings N = .013
No. of pipes = 1 Required pipe flow (CFS) =
Given pipe size (In.) = 8,00
Calculated Individual Pipe flow (CFS) = ,91
Nonnal flow depth in pipe = 2.03 (In.)
Flow top width inside pipe = 6.97 (In.)
Velocity = 12.995 (FIlS)
Traveltime (Min.) = ,06 TC(min.) = 11.90
,91
+++++++++++++++++++++++++++++++++++++++++++++++++++++++++++++++++++++++++++
Process &om Point/Station 14.000 to Point/Station 17.000
..* SUBAREA FLOW ADDITION ***
100.00 Year Rainfall Intensity(In.IHr.) = 4.369
Decimal Fraction Soil Group A = .000
Decimal Fraction Soil Group B = .000
Decimal Fraction Soil Group C = .000
Decimal Fraction Soil Group D = 1.000
SINGLE FAMILY runoff coefficient = .5500
, Subarea(Acres) = .06 Subarea Runofi{CFS) = .14
Total Area(Acres) = .42 Total Runofi{CFS) = 1.05
TC(MIN) = 11.90
+++++++++++++++++++++++++++++++++++++++++++++++++++++++++++++++++++++++++++
Process from Point/Station 1.000 to Point/Station 18,000
*** INITIAL AREA EVALUATION ***
Decimal Fraction Soil Group A = .000
Decimal Fraction Soil Group B = ,000
Decimal Fraction Soil Group C = .000
Decimal Fraction Soil Group D = 1.000
SINGLE FAMILY runoff coefficient = ,5500
Initial Subarea Flow Dist. = 105,00
Highest Elevation = 215,00
Lowest Elevation = 198.76
Elevation Difference = 16,24
Time of concentration calculated by the Urban
Areas overland flow method (APP X-C) = 4,07 MiD.
TC = [1.8*(1.1-C)*DIST ANCE^,5)1(% SLOPE^(1I3)]
TC = [1.8*(1.1- ,5500)*( 310.00^,5)1( 15.46^(113)])=
100.00 Year Rainfall Intensity(In.IHr.) = 4,875
Subarea(Acres) = .12 Subarea Runofi{CFS) = .32
Total Area(Acres) = .12 Total Runofi{CFS) = ,32
TC(MIN) = 10,04
4.07 USE TC=10 MIN,
I
+++++++++++++++++++++++++++++++++++++++++++++++++++++++++++++++++++++++++++
Process from Point/Station 19,000 to Point/Station 20,000
*** INITIAL AREA EV ALVA TION ***
Decimal Fraction Soil Group A = ,000
Decimal Fraction Soil Group B = .000
Decimal Fraction Soil Group C = .000
Decimal Fraction Soil Group D = 1.000
SINGLE FAMILY runoff coefficient = .5500
Initial Subarea Flow Dist. = 95,00
Highest Elevation = 204,00
Lowest Elevation = 188,25
Elevation Difference = 15,75
Time of concentration calculated by the Urban
Areas overland flow method (APP X-C) = 3,78 Min,
TC = [1.8*(1.1-C)*DISTANCE^,5)1(% SLOPE^(1I3)]
TC = [1.8*(1.1- .5500)*( J05.00^,5)1C 16,6^(113)])=
100.00 Year Rainfall Intensity(In,IHr,) = 4,885
Subarea(Acres) = .08 Subarea Runofi{CFS) = .21
Total Area(Acres) = .08 Total Runofi{CFS) = ,21
TC(MIN) = 10.00
J,78 USE TC=10 MIN,
End of computations,..
TOTAL STUDY AREA(ACRES) =
,62
(3.
APPENDIX BI
TABLES AND CHARTS)
1-1 EG{j~TION
F~~I Tc. (I/¡L. J) ..384"
$"""IJ lë. 7lm6 J CIJ/1&6/11n2T/M
~IJIJIJ L. L6~/h D~ wQ¡ltI'r,sohtl'd
II" /)¡A"6r,/1C6 in ,,1,vtZIÚ:Jn tZ./M9
31J1J1J e!'/'t>c¡l/y.. SIIJØf!t 1//16 (.fe!'" ..9NCnmx )(.8) ¡;.
L. 't:
M//6S r4!' 4!' I' N~;s Mi/1vle!'s
2""'" 4 24tJ
.31J
, 5ð()()
..
~~IJ
"
J()()I) "
"
"
2()(}(} "
la()() "-
Iii""
141J()
I~""
lOOt) 7
9IJO
B()() Ii
71J1J
¡PI) S
sot) II-
~PI)
.3
f
. I
as
/1)
3ðO
oS
21)()
IIJIJ
NOTE
~-~-_-...-~
IFOR NATURAL WATERSHEDSj
21J I ADO TEN MINUTES TO .
(1COMPUTED TIME OF CON-j
CENTRATION.
~ ~.::III: =- -==-"""""-
IIJ
5
20()
H
L
.3
¿o
/81)
2
l21J
IIJO
'1)
8()
70
IiO
I
so
'J . - '-.; < ,~.:,-:1
," t
" .,.,.~;
f
SAN 01 EGO COUNTY
DtPARTMENT OF SPECIAL DISTRICT SERVICES
DE SIGN MANUAL
APP'ROVED ,3./-/' /~~
7é
NOMOGRAPH FOR DETERMINATION
OF TIME OF CONCENTRATION (Tc)
. FOR NATURAL WA TERSHEOS
,
DATE I~ /II~ 1
APPENDIX X-I /
"... _1n PP1l c:
SAN DIEGO COUNTY
DEPARTMENT OF SPECIAL DISTRICT SERVICES
-"-""~-i> . _.. DESIGN MANUA~.
-"'.';4A~PROVEO ;/../ . 't"i"':~ L,L...-r' tl .r:-.
. .
,
I .
i
i
.
;
.-.--.
.
i.
-..
.~
WQ/~,..sht::d O/v,d'c "\
.---- --- - ~ ----J
_..-
,#
/#
./
~
..---- -
/
,-
---.
'"'- '-- ' ,
--- ~#
~
"--
---- -
-
L
W¿:z/"r.shed
/)ivia'ø
TO,
H
J
L
L
I
.I
/lr~a /9" . /lrea. ':8.
COMPUTATION OF EFFECTIVE SLOPE
FOR NATURAL WATERSHEDS
'.
- ,
~ ,
APP.ENDIX X- F'
. /
, IV-A ./
, DATE
.-
.---
,338
-.
8
DEPARTMENT OF SANITATION So.
FLOOD CONTROL
1t5'
30'
15 '
'"\
,-1-
Its'
.,....f'4 It,
u.s. DEPARnU:Nlr OF COMMERCE
"AT'ONAL OC:"ASIC: ^"o A":o\O:âI'IIENIC AO308I1UIITRATION
, '
~PICI~L STUDIES lutA~C:II. O'f,CK 0,. IIjONOLOGY. NATIU:IIAL Wa::ATIlItR SEICVlCE
. 301 -
....
.... '
,
~
.
I W.
I,S'
JO'
....'
1178
II ~i 1
JO'
l!i'
11(,.
w
...
"
'--"'.
,- .TV OF SAN DIEGO
~_.ART"ENT OF SANITATION &
FLOOD COtlTROL
.~
"
. "51
,. --\.
I
301 I
I
151 ~
I
338
"
"51
---....-. -~...- - ;.,.;.~,.~, .
u.s. DEPARnlEN r OF COMMERCE
IIATlO:tAL OCEANIC AltO AT. OSPIIEIIIC AO....:tISTRATION
. .,aCIALITVDIKI..A:'ft'H, ornc. or II UROLOGY, NATIONAl. .EATtlE. IIRYJCE
30'
...
....
.
:a-
.
...
1181
451
)01
IS'
1178
'.51
)01
15 .
1168
HIGHWAY DESIGN MANUAL
810-11
f'
1000
I-
W
W
U.
Z
-
\
u.i 600
0
Z
c(
I-
en
-
e 400
-oJ
W
>
c(
a:
l-
e
z 200
c(
-oJ
a:
w
>
0
800
o. rsil
.
Figure 816.6A
Overland Time of
Concentration Curves
- -f,!-
~
(>
Q:
if
fO-
~""'"
-
N!
0-
¡¡j
I
1/
~
T7
"'"'
To - 1.8(1.1-C) (L)1/2
0 - [S(100)]1/3
\
ff-
fI
1-, - ..
I
fO - CtJ! -
<'v(Q
7- 91 to
7r o';:/-
J ~
o'
IJ
II
If
v
11
J
,-
, I
a
a. 'a
v~;' o~~
0;. .,0
. ....,.
t.,.. If)
..,~.
1/
'0.
"
~
.... I
.s þo
I.;'
;'
"
I.;'
~
....
JIUluary,lQ87
II
en
w
I-
::;)
~
~
80 ~
...r .
!
W '"
>
c(
a:
60 I-
u.
0
w
~
I-
40 e
z
c(
-oJ
a:
w
>
20 0
.9' =-
.iJ_5
0
Where:
C = Runoff Coefficient
L = Overland Travel
Distance in feet
S = Slope in ft.lft.
To == Times in minutes
.
.
::
en"
I
s:
C
.,
""
.,
I'D
n
-'I.
oa
~ 15) This line is the intensity-duration curve 'for
6.0 ~ the location being analyzed.
5.S o.
5.0 ,:J~...,
4.5 -
4.0 ~. '¡APPlication Fonn:
3 5 n ,
. ij;0) Selected Frequency
3.0 ~.
2.5 il) P6. in.. P248
'--...
INTENSITY-DURATION DESIGN CH^RT
'" ,
~ - ..,:--.,::-:,'..:' '.'
." -. ..'. .. ,
m - ,.-,
~ - - ..
Þ-4 - ..
'><"~ .. ~ - - -
)ole
M 1-1-1-1-1-..,..
.llllli
..'
If
1--1"1-.. ,.
,.-
M
< I-f-+~f +
.:..a
.'1 15 20
30
40 50 1
2
, 3
4
5 6
Directions for ^pplication:
1) From precipitation MapS detennine 6 hr. and
24 hr. amounts for the selected frequency.
These maps are printed in the County Hydrology'
Nanual (la, 50 ~nd 100 yr. maps included in the
Design and Procedure Manual).
2) Adjust 6 hr. precipitation (if necessary) so
that it is within the range of 451 to 65% 0'
the 24 hr. precipitation. (not applicable
to Desert)
3) Pl)t 6 hr. precipitation on the riDht'$id~
of the chart. .
4) Draw a line through the point parallel to the:
plotted lines. I
yr.
*
. P6 8
P24
in.
1*
2) Adjusted *P68
3) tc. min.
4) I 8 in/hr.
*Not Applicable to Desert Region
APPENDIX XI
T\I .. 1..
(
TABLE 2
RUNOFF COEFFICIENTS (RATIONAL METHOD)
DEVELOPED AREAS (URBANt
Coeffi~~...f
Soi I Group (1)
Land Use
A ! C D
Res i dent i a I :
Sing I e F am i I Y .40 .45 .50 .55
Multi-Units .45 .50 .60 .70
Hob i 1 e homes .45 .50 .55 .65
Run I (1ots greater than 1/2 acre) .30 .35 .40 .45
Conmerci a1 (2) .70 .75 .80 .85
80% Impervious
Industrial (2) .80 .85 .90 .95
90% Impervious
NOTES:
(I) Soil Group m~~s are available at the offices of the Department of Public Works.
(2)Where actual conditions deviate significantly from the tabulated impervious-
ness va1ues of 8004 or 90%, the values given for coefficient C, may be revised
by multiplying 8004 or 90% by the ratio of actual imperviousness to the
tabulated "imperviousness. However, in no case shall the final coefficient
be less than ~.50. For examp1e: Consider commercial property on 0 soi I. group.
Actual imperviousness
. 5004
Tabulated imperviousness. 80%
Revised C . 50 x 0.85 . 0.53
80
IV-A-9
.,.
\
APPENDIX IX-B
: Rev. 5/81
(
...
'.,
f
.
Average Values of Roughness.Coefficient (Manning's n)
Type of Waterway
1.
Closed Conduits (1)
Steel (not lined)
Cast Iron
Aluminum
Corrugated Metal
Corrugated Metal
Corrugated Metal
Corrugated Metal
Concrete RCP
Clay (sewer)
Asbestos Cement~ Pvc:..
Dr~in Tile (terra cotta)
Cast-in-place Pipe
Reinforced Concrete Box
(not lined]
(2) (smooth asphalt quarterlining)
(2) (smooth asphalt half lining)
(smooth asphalt full lining)
2.
Open Channels (1)
a.
Unlined
Clay Loam
Sand
b.
Revetted
Gravel
Rock
Pipe' and Wire
Sacked Concrete
Lined ,
Co"frete (poured)
Air\ Blown Mortar (3)
Asphaltic Concrete or Bituminous Plant Mix
c.
d.
Veg~tated (5)
Grass lined, maintained
Gra~s and Weeds
Grass lined with concrete low flow channel
3.
Pavement and Gutters (1)
¡
Concrete
Bituminous (plant-mixed)
. ..' >'\
"T"
- ,
, ,
Roughness
Coefficient (&
I
.
. ,
0.015
0.015
.021
0.024 .
0.021
0.018
0.012
0.012
0.013
0.011
0.015
0.015
0.014
0.023
0.020
0.030
0.040
0.02S
0.025
0.014
0.016
0.018
- .035
.045
.032
O.OlS
0.016
APPE.~DIX XV!, .\
I
.
'.
. .,
E....lt f. Brltlr Ind HorlCI Willilms IUnl
HANDBOOK OF
I j
.
.
;
Table 7-14. Values of K' for Circular ('hannds in tJ)(, Formula
I
, K'
Q = - d~!JS1'.:
It
D - depth or watt'r
d - dialllc'tc-r or channcl
: I .00 I .
.01 .02 .03 .04 .0.'> .06 .07 .08 .09
_1__. ..- -
,
.0 .00007, .00031 .00074' .00138, .00222 .00328 .00455 .OOfiO4' .00775
.1 .00967 .0118 .0142 .0)(i7 ,0195 .0225 .0257 .0291 .0327 .03(;(;
I) . 04,Ofi .0448 .().I!}2 .0537 ,058,:) .0034 .0086 .0738 .07H3 .0849
,..
.3 .0907 .09fi6 .1027 .1089 .1153 .1218 .1284 .1352 .1420 .] 4!JO
.4 .1561 .1633 .1705 .1779 .1854 .1929 .2005 .2082 .2160 .2238
.5 .232 .239 .247 .255 .2fi3 .271 .279 .287 .295 .303
.6 .311 .319 .327 .335 .343 .350 .358 .3(ifi .373 .380
.7 .388 .395 .402 .401' .416 .422 .429 .435 .441 .447
.8 .45j .458 .463 1.-&68 ...73 .477 .481 .485 .-&88 ..a91
.9 .49.a .496 .497 ..&98 ..&98 .498 .496-.'. .494 ..a89 .483
1.0 .463
.,
,:" .
:.a~. :
'0 . ..'
""': ., ~ 1 -
.' .,.. ... ~(; .
:
., .
.
. 't.
.
-
:
1
,
APPENDIX C
( 4 .
HYDROLOGY MAP)
....-
'. "..- ."'., '..'"
[
~ [
[
~
(
'"
~ (
~
[
[
(
(
/
A .
�k to
r
X
f
A 4
ol t,A
AL
�EXI - nNo OPER' SPACE
S
EASEMENT PER P.M. NO, 17075
8" DITCH
TYPE 8 BROW DITCH!
C4
PE
.1111I ' Now
PER 0 R D-75
N 16*W. 1 E
it
Now
f f___ TF t No woo wow it 4 f P4..-
NNW.
WOOL-
"RETAINING WALL,�R
BULL�TA-222 ------
ViiiiIiii PVC 0 1.0% 206.80
IE 2,05-30
ff 20# 70
FS
FS 200-96 200
lu 206.80
204.85
' 45 # 04 P
vc 0 1-.0%
011
0.
IE 204.60
FL, 199.77
T)TE 8' BROV DiTOi TO 206.40
PER D-75 1 E 204.40
IS ZU4.N FS 204.50
198.76
mono
�4
Fill 07,667
Fl. 203 35
PA 207,600
FL 203.35
A
tic
TO R06.40
10
SCALE. 1
JE 204.09
FL 2 �FL 203. 3
Ic 0 1.
26 1-6 1 0 1.
Lix
<
L4
TW 205.00
TW 205
.00
203.40'
IE 201.90
TO 206.60 RE NO WALL
IE 203.41
RU 222
sop
2 0
VATE ROAD EASEMENT
-Ile
1E 202,4t
EXISTING, OPEN SPACE'
EASEMENT PER P.M. Nt �5 Ac
2V 20'
7i
2(*.40
TIC 206.50
1 3.83
P
IE 203-16 .........
0 1.0% 45
P
---------------- -
EX T. EAS
ENT,:TO.SDG&E`, PER DOC. REC. 9-11-90
AS F/P
A
203.40 TO
ILI IF 201.67-
C.O.
IE 203.68
43' P VC 0 x
kip
D 0 lip.
0
10
0
0 0 TG 206
0
1E 20148
0occ) TO 206.
0
2
IE 202-86
Oil? Aes
�
EXIVNGI SPACE�
'EASN N
E0 PER M. 17075
4
dbwgw
> -now now#
17*33'23'
W 199-93
1 > is
IE 189-50
;6
TYPE 8 BROW DITCH
PER 0-75
00 0 190
>
MCE
R TANT NO
SECTION 4215/4217 OF TH E GOVERNMENT
CODE REOUIRES A DIG ALERT IDENTIFICATION
NUMBER TO BE ISSUED
"PERMIT TO EXCAVATE" WILL BE VALID.
PER YOUR DIG ALERT I.D. NUMBER CALL
UNDERGROUND SERVICE ALERT
P d e enc
f on
TOLL I
IAJID FORE YOU DIG
RAT1+
gy,
c
DESIGNEQ DRM _KED
DATI N_ H M
'REVISION �APPROVED -REFERENCES, DATE BENCHMARK SCALE- COMMUNITY DEVELOPMENT CITY OF ENCINITAS ENGINEERINGr
DEPARTMENT DRAWING NO.
QESMP110N COUNTY BENCH MARK NO. PLANS PREPARED, UNDER SUPERVISION r OF: RECOMMENED APPROVED
GRADING AND EROSION CONTROL PLAN FOR:
_CHIS. so
r OC wn IN TOP OF
N/k
HEADWALL HORIZ'ONT&: T DATE
13Y.- BY.
u )knoN -S.W. CORNER EL C
AMINO DEL N(ATE W
- C.E. NO. 48592
HISPER WIND RARCEL 2
WORK PRWECT NO. SHEET 2 OF
EXP, 06-36-2000 'TPM '89-140
''NL
& RANCHO SANTA FE ROAD.. A
VEPTI AL: DATE:
By: DATE:
KAMAL S� 'SWEIS
00: C.S.D WRTICAL.CONTRM.
2
119.476 U.S.C. &
woo"
-7
q �
7: -v
or
T V
,j f
_11 I—M MM
N _7 7
;wA
411 71
l A
I _4
3
_4 " 11t, -
b
A ,'
o 9L**6LI o*s*n W(a
W E / P I
3
-OV-90
ON 133 IMNOO NOLL83A 0TO NM =03
rOSd A80M 00OZ :A8
72 :3.Lvvta :31Va -WO1183A
JO Z 133HS sl;�
940 L v4d `GVOH M VINVS OH3NVH It
*ON 3*0*8
Z699* 31VON,130 ONYWO 13 MN800 AS, V
A — :A 'WIN
OZ180H
V/N
-NOW= Q N Im <A 3 d Sl HM :3iva
JO dOl NI OS *SIHO-VLOO 30
Z rl
> 'ON )18V14 HON38 AINnO3
NVI
(13AO8ddV
d '108IN00- NOIS083 aNv DNICWO (13N3 Mn8 :-40 NOISIM3dns 8�aNn O�8vd d SNV1d
03AO8ddV,
3-438
A8VVqH:DN3e NOISLA38
cc Z C>
.1N3V1d0 AiNmmo 31VOS S3ON38 31VO
# S'lVA08 03>103HO !A13 NMV?j 0 :,kG 03NOI
A 0 AJL
18
N ONIMV80 N3TUJVd3G ON 33NION3
zj �ixvo J
C) 010 n0 38OJ38 SAVC1 ONIMOM OMI
C-4
C1 dW
1871V 30VS,81
to , L
f -nVO 838rinN '(FI 1831V oia 8noA 83d
- IVA 38 T1 M
VAVOX3 01 11IN83d
v
3NO-4313 c3n S1 38 01 8313y4nN
N31� 010 V S38inO38 3000
N011YOWU N301 I
1N3V4N83A09 3HI -_0 L LZ*/g LZ* NOLL03S 133HIS 01 NNHa 01 9LOL L Md
IA011Y OJL VQGG 'O*V ONLLSIX3 00 lrl�
1308Vd
9LOL 1. Fid
T1V14'MSV1dS�-8OJ
'N114 ZZ GL-a 83d
H
311a MOH8 8 MAI
00* 0 -99131 slob
t , � , .11 - Mcut S
of
066t-U-Ot G <==3
77-1
d2ft
imista NOLLY It ft� Amos*
999--*19_06 # d/J SV 3080038
1INys jjia� vo 01 IN3VMV3 'ISIX3
MAN%
6t /0-W
L oON_ d, 83d NIM!
30*415,
CD
N3dO ONLLSIX3
10
R '14 H3d
33VdS MO 00NIL IX3
f
S3N)K)I 9970Z 31
Tw SVI& NOLMS U 09*90Z 01
-a 93d IDNV18 SWU 13AV80
07=1
OV90Z
Z 3doki.
WSM Ssm Ilow EXL"
`ONLLI3N OMMS 39VO Lt
a3OVld
*NO1133s aN lwm jjo im 31383MOO z
3L3WNO3 a30V1d HIV 3d 009Z. "HI ey Isd 009Z
99* 31 \ XSZ 0 OAd (SMIS RLos)
OtToz 01
30(13 (13ND131141 .9
Sy
�vj
08 t-6 "038 *3W Od
01i IN3r43SV3 ISIX3 t
%03 0 W ,9 .19
9tT0Z 31
09*90Z Di MTOZ 31
0z 01
OV9
N d dIN3R3SV3
10Z OZ SiOLV d
133V�S N3 ONLLSIX3.
.9
INIPOSY3 GVOH 4 *'tOi 3 1
*9(
H31I(J OINI a3SM3 TO -Zt 0 a33V 2F ATTYOLL83A CC d SVVG
*ff ONOI .2t HIM T M HSY1dS
ISd 009Z---'
Id 8'
31380NOO G30Y 010Z 31
C&
09*90Z 01
0 0
*20 GSHM
mva oINISHYS 38"3 *3*0 Z L 0
��83d IWM 5NINIVA8
MUS V TrY01 3A a33V1d OZ A
00 S 00 MI IM TTVM HSVIdS S
ONOI t S
S
Wild 81V IS
OAd s 11"N— 31MON00 02- d 009Z
Toz 3
%t
C196coz OV90Z 01
06 TOZ IJ
9LOL L. Md
0z 00 -it/
130`8V d
00 *I
'60W 3f
3WMS 03 V OV90Z 91. o G*O= cr) C4
0 _Z GVd
010
Voi-So 'ON ONNYma- w vwr_-t- 101HISIG NOLLUNYS JJ108VD 83d MYR 8303S L910 TJ
m S3
00
00
9L *96 L ELL ff S3 ()9*+OZ Si
0 0
0*4#0Z. 31 1 wNM %Z 0-%-G 83d
0V90Z 01. Ham mose'v,3dAl
now
*0Z 31
09*
.
'(dAI) SNY1d lf MOMS aNV-ifslii�mv
%03 0 3Ad
S3d 38Y 0N1(nn8'RII41V&-TMM ONINIVIM
"*"Z. 31
W90Z 01
'LLOUO-19 CV3 w?j -Now- I 7�,
SY MR '01 HOHYM MSW-�8 ID&Sla 831YM 33S 1WM_,W013S SOA MINI MLoo d'
UIL
96*OOZ SJ
3SV3 ISIX3 *00Z AGOZ SA
WdIDINI`114 NIVHN3Ar1O 01 It 3M 01-**OZ
9-3 as�k Sz
"e-i0q 0 3Ad 11teV
No W d
-4 -mom
uu
- 90Z A
CA
MLOZ
M W90Z
3cK IS a33SOS
dH GCO 1Z L:z
................... ........
0 DA a t'" t tl t z
H
IL
>
aim
3 0t,29.91 N
6"W WMwft-- OEM
- NM ZZ 4L
'U OZ' 10Z 9L_ �G H3110 *088 8 3cLkI
3M M314
LO—M-1.00-3 C6 IX3 (M MO 83d S3L V
IvHa 01 H31 H011a MA 3dAI tz
33US 01 N
1z
MOJW O.L ASM - 0 - Y !)NtLsr.<3 Inb ino C)
OD
9LOL k *ON Wd Od I CA
33VdS N3dO ON S
9Z90 L 4'd 30 Z 1308Vd
l rno 0_�
SEA
'n
F: Z,
7 W-
4
7�
§!
glA v
A 'AtW
A
1 1 '56
4
J* co
C> cn JO 1331AS 'ON 133rO8d XNOM
''A
*dX3
In v *o*s*n wru�
rn 'OON' dV N 07:31VC! 000Z_05�_90 ki L I AIM
m -. :3XV10 W3' S N
c') c io&Lw* woumA as*o -mug �ii
Z699�*
ILI
Oz Z 130�J cJ CINIM �93 IHM TVON 3A ViWS %ONY8 V
0 m �: �t,i;,
W3 0
Z M Ilya 31HON TA ON1rW3 13 83NNOO /A 'S
VINOZ180H
OZ V/N
*80-4 NVI& 1081NOO'NOIS083 ONV DNICV85
A dQ1
03A 8dV 03143YU40338 "JO, NOISIA83dns 830Nn (138Vd38d SM9d M m- 11HO-CLOO 3a
r 'ON )WR HON38 AINnO3 'Mla Mm
"ON \ONIMV�R] A -JYU�Wd3G. ONP433NION] SVIINION3, JO 10 SIVA08ddV -1VOS,
"79 (135101P *M3 C13N01 AIINnmoo
W3 N iN3r4dO13A30
0 S30 3
- A'V 3TV0 S30N383.43N 3.Lva mmoaddv
31VU
31Va
31VG
Nq
ROLZ6 Ta 060IG uos�
C:
*A19 (13M31&18
4
wwo - &a
3
1831V 301ARBS GNno8o83ClNn 7 )a rM3 M 8
SAVO ONIMOM OMI WZ OPS 1A03 JgluaO MRIN 109L M-961(619)
va nOk 38OJ31 40 0 01 1 / '11YO 838yqnN 1 1831V 010 NnOk 83d
dW 13181SICI ,NOLLVIINVS -101
sia 831VM WdI3INnm I
NIVHN3A NOU33IONd
38U :SVIINION3
uiuw
'011VA 3e IIM VAVOX3 01 IIN83d
nS
V 38OA38 03TISSI 313 01 N38vm 6 ulkg" 6 L1IJ99u1 6 u3 6 Id
NOIIVDIJLLN301 183" V 010 V S38inO38 30'00 _7VSOdSIG 3HJL 01' -110S
AW -40 8018d 833"N3 )u* a. 833NfON! S
IN3NN83AOO 3Hi 0 LLZ*/91Z* NOLL03S
3H.1 RONA 038n33S 38 7WHS 111-1, S18830 - 1 JO _WAO8ddV
'a3SV"8 -40 NOUV30
AiQjn33s.-
`S18830 AIIHOISNn NOW 3383 30NV8V3ddV 03HSINI-4 GNV
- WVVOO St' jq
3alot.] 1W1kKMN OW M13 iumn 0 6mdvosaw IN3NVr483d 3HI.
1:V3N V HIIM
-038V310 N338 3AVH
1 ONIMSO(LkH 383HM SV38y 80j ' M dV3SCNV1 AIINMN83d Sl 33M8d 3HI LVHJL SV38V 3HI 3AV31 01 SV OS
801
3V8INO31 3HI A13
NOIIVgWl
:31VO MIS- 3HI -4-40 JO, G3S0dSI0 3SIM83HIO NO G
itiNn HM080 SnO8OM V 30IA0Sd 01 (13NIVINfVri 38 TIVHS SY38V 3 33SO
a a ?IMH'' 311d 6 03103110
Al
IV1831VIA4
OO/OM *dX3 N "TO 31eVNOII33reo 83HIO CINY. 4 SSVN0 *Hsn8a 'S338JL.TTY *91,
03
*HAO8!� HOA SNOUICIN MIA 3CIA08d 01 STOS 3NIIVS ONMA03. AX3 :03NOIS
80 ONIHOY31 'IN3vusn(1V Hd 1IOS 30 NOI1J0GV 3HI 30NVNfG80
S134/ S WK
13
F "POOIW9 NVO8000Y
o
IV 40
*a313 033S 031V8(UVS ONIG"D 3HJL HILIM, 30 NV Cl3aNnO8 318TIVHS S3dO1S
"1000
1 , j .. I -.1. � 1 1 11. dOl CNV 301 3HI "-io a3SOdSIO (INV (13AOY438 38 IIVHS 03N3SOOI
ION, Ing dMVa V 3aIAO8d I - I I Ir I 3V40038
*SNO OIS LW1rvNVGr43 80 NOLLVAVOX3 80
01 WISION 1IOS 30V-48nS 3HI ONLLsnmy v
.01 318VII 38V HOIHM S3d
IN IS 11OL4101dS (INV SWId , ONICIV80 3HIW (33SOdX3
0 103ro8d
11 IVHI OS S1IOS 3HI "DNINOVINOD I 83-liVN 31SVM 83HIo -aNv SIOO8 'S3NOiS TIV - 'NOIIIONOO 30 O�
3HI :A8 ONIINVId 8oj moviins si a31VNOd8O0N1 N3381: �AVH i331`08d SIHI NOJ I8Od38 Silos - jHJL NI 03an-10NI
- 18 N ONV
0-4 S311nIGISNOdS38 M -40 A80M -40 833NION3 SV '3Y4 3A31138
IV3N V NI IJ31 CINV A80M, -40 833NION3 3HJL A13 03.iO38K] SV �03Y414181
'VHI MUM aNy SNVId DNICIVNO 3S3H1 a3M31A38 3AVH I
ION SNOUVON3W40038
INO M31A38 V 01 C13NIANOD SI SVJLINION3 -30 Alto 3HI 8
S3W ONY A,
N 0.
isn dn *38a ION -nm im sy3w-, mo CINV 031NVId '03d0 313 *11VHS SIN21miNverG OW SNOIIVAV X3
N
SNOIIVOI-41 33dS SbNIMV80 103ro8d JO X03HO 3HI IVH1 (INVIS83ONn I 9 *38OV4N3H18rU *833NION3 Alto 3HI'JO 3OLUO 3H.L 01
03111mens 'N338�SVH
WHI 83d331S S3dO1S ONI)MM 'SNO1.1VC1N3AVYO038 M, HAM 'Aams SiHI pow andmoo, 8o S3dOIS 3HI *SNO1133S SSO80
10480ANn a NV S3ov_48nS HIOONS 3onco8d o.L.
d3?A
(INV
3CIVND HSINU 01 (13VYV4181 (INV im 38 TIVHS S3dO - nu aNv no
ro
031 AW AS a31W1d 38 01 30vjHns 3HI'9NIN3Hwo8
'SNOUVOIA133ds HIIM
'SG8V"NV1S IN388m HIIM IN31SISNOD Sl NVS30 3HI IVH1 _CINV '3000 los -40
;T
SNOISS3JGId GNV SS3NISn8 3HI JO COL9 N01103S NI 03NIAG SV 133ro8d. NO110381 AM 830Nn 80 3VY A8
SIHI NIHIIM A31VA38d SNOUICINOD. IIOS 3 HI. -4 0 xams aNv 0NI1dmvS V 30NYONODOV 10181S NI 1113 3HI I0Vdr4O3
ONY 831VM Id
3HI A NDIS30 3HI N3AO 308VHD 31SISNOdS38 CrAS1083X3 3AVH I IVHI.'
-A ONIC33S08am 0i 8ordd a3Wd38d 39 TIVHS (13(133SO8CM 39 01 Svr3W CIV38dS '30V
*103ro8ci SIHI 80J ANOM JO 833NION3 3HI YW I IVHI 38V1030 13383H f 1YH1 A311830 A8383H 'SOfNVHO3Y4 IIOS G311ddV JO (1131-4
3HI NI SS3Nisn13 01 A,11'118[SNOdS38 S,8013V8INO0 3HI 38 1IVHS 11 'IN3083d JO
-01 031:DVdY400 N3H1 GNV S3HONI 9 JO HId30 V 01 CIA418VOS
*380Y 83d-S8I 009 JO 31VS 31-11 1Ya3nddv %gt DNIOG 717VdIONINd 'VIN80-411VO JO 31VIS 3Hi -40 833NION3 IIA13
38 IIVHS Silos G3SOdX3 3HI 'ONno8o- w8mvN R813 31evins
0`1831SP93N V A 8f'�J 'O"OZ *31V-flnS 31VHdSOHd rmINORW 30 DNLLSISNO3 83znua3u :30�JVHD 3`181SNOdS3�1 JO
NOIJLV8VIO30.1 os wAni-w cNv nu 3SOO1. *030YI&
I S 38 OJL Sl 1113 3HI HOIHM NOdn 3ov_mns, 3HI VY08z! NOIN81NOO 3HI A13
WHI SS31 ON WHONncl XTNOINY43' iS S NIDN3 S (13AOr438 319 TIVHS IVI831VN 3 CINY 83J-LVYY 31EIVI303A
TW
*1IOS 3111 OINI AVSIS 3HI A %09
IS mov-4 -n3MS NO 30VANINHS OJL 3na Am"m S31.LuNvnb 3N ABA wiN3V431 V 833
MR Sl 03sn si mvmN3Hm -- meivm iesu cr3nddV Aiwwrvaam 'SNOLiV0IJ133dS (18VONVIS HIIM 33NVGNO30V NI 030Y1d
38 71VHS 111-4
vniov 'SISV8'_1V0fJL38O3Hi V NO 031Ylnolvo) %k71N0
803 'Iwd 80 iv 'uniusenS 38 kVF4 (MV&S) Hoinri 9 3dki "380V
N3d *SG1 OOOgZ NVH1 SS31 ON 30 31VN 3HI IV 03nddV Hbinm CINV (13111-4 3e 01 C]38Vd38d N 71VHS 031IL4
38 01 SV38V T1V
S3 od8nd IIN83d 80J 031VV41IS3 38V SMuNvno >18OMHJL8V3 :3.LbN 3dAI
*(131"IVISNI
"MM H
IS081 OW
- 1081NOD NO
SY1dS
*8O1N%IN00 3HI -40:NOLL383SIO 3141 IV A88MS MM08aH: ISMS 3AVH S3NnSV3R 30V'NrV8G IN21N0183d'
Nd'
3Hi 01 030CIV 38 M SIN3N 9NU3M DIXOI-OlMd-NoN *r SV 31M411 Hons IIINn SV3NV 03aV8D IHS38A -40
NOISON3 1N3A3
7 7'
em s38nsv3y4 W103YUN 3AVI IIVHS GNV 31ISAHI NO A80M (13HSINI-4 0
so8vk ojeno 0 I8OdX3 *S83NfVINOO OrYS NO CrAN18d 80
"Ol 03H�V.U'y 0yj NOIIM11830 3aminmy aw clow jo 80 S3li83dO8d 0NtNlOrQV 01 30Vr4Va aI0AV ONY 831VM 3ov-48ns
IONINO
N31AGAVd, *D*V,
IN3RIgVeIM VIN80AND 3HI HIM S83NfV1NO3 G3N3dONn NI I1VHS 3H *8MVM JO DNIONOd N3A38d (INV 30VNIVNa 3AIIISO
sa8vA ojeno OXI, d 3GIAONd
useor 3HI 01 03180dSNVa 38 TIVHS S1VJ831VR C133S TY. *1 01 S3ov_4sns (131VAVOX3 IIV 3CY80 183dO8d IIVHS
NOIOVNINOD .3HI T
'ON1033SONGkH 38OJ38 f)NUSYDOY088 80 ON111180,
oteno 00CL
AG HN113 AW klddV (INV MROVS ONIXL4 N390UN V :3
sn
0* a
INI 813HI 8o-4 38V SN
V HIM 031Y1n3ONI 32 ism N01103sens sm jo ,V,, rGIJ *H US80S' 83d dW 03aN3 OIJLVA�OX3. aNV S.LN3)4>fN'V
IAG 7W IVH1 (INV S1.8Od38 S110S 3HI JO SNOUVON3W40338 3HI HDM, 30NY080
`S38n13n8IS WIN30IS38;
*S31iliNvno A8OMH1HV
H
80 Imis onend v 831U13 140�U 31131SLA ION SF� NI amon8ISNOO 383M SNOUVAVOX3 (INV SiN3r4ANVf3IN�I'T1V 'NOINIdO'
SI
1VM
a 83d I
NI 1VHI CINV NOISIA83dns SIH 830Nn 80 V41H A3 3CIVr4 383M SIS3.1 (I
*ZOZ6 V3 "SVIINION3 d3a33SO8%H ON138 Y3W 31-11 MHM SNOI1VX1 NO (1311YIP40
NV
*!D
*80 ONIM83dSIHM gtg 38 AVIII N01133SGnS, S1fU -40 J OW I 'Cl 'D S143b SNOIIVA83SE30 IVHI 31VIS TTVHS
3H SNOI1V83dO ONKN80 .40 N01131dr403
IH 80V8 OMI),8
M ONV
NOdn `IVI83JLvN 111-4 ANY -4o Aineviins 3HI 3NIY483i3a Ill
V031OHd8OAIG,JO 380V �Bd '81 Z/ I *J OV13aNVS
NONS .40 Ewwo) mnssAw 40 380V 83d 'Sfn - 3, (3381n038 SV Sl?3Od38'SIIOS imens 1IVHS 3H 'S3HON381 30'
NOII0Vd'vYOD
-nIr -a as8as �Ilcl H
:SS380CIV 3.1.19 "A 4 Y37111113V 30 380Y 83d ISM 3110 MOW.13m 3dA1
O NOII3Vdr400 GNV IN3Vq30V1d NO11VAV0X3
VOIN80AM V10 1OOH3S 3 JO 3NOY 83d *S8I CT *0 80 TWHS 3H 'NO11338K] SIH 830N(I NO
833NION3
3nos3i 088OZ -40 380V 113d 'S81 OZ - 9 S'1IOS 03wrivno v Ae amsm aw a
I x 0 NISYS H31.V3 3A83SSO 39 IWHS !DNICIV80 11V 'ZI
�M013 3SO8 JO 380Y 83d *S81 OZ
6 SNO11V83d0 DNI&80
*OLZ6 VO 4 0031a NVS WHI SS31 ON JO ISISNO3 TIVHS XlYf M3S 3"dr 30VN"G Hons S31AIIN30 OHM 8'13NION3 IIA
338iS V4IVd 19 1. c :0NIMO11OJ 3HI TIV JO ISISNO3 TIVHS X114
13 3HI, .40 38n.LVNDIS aW 3.1ya
*HAM (13033SO80H 3HI JO; HIM080 3HI�NOJ - L - m3i rinr4LLdO 3111'� 3H1 G '03MOMO-4 3e - 11VHS IN31AGIViS
smi - ,,Nyid , a30V80-SV'03H0V11V
o"n VmA CNIM83dS1HM
0
IV 1IOS 3HI JO 13A31 38nisiOV4 3HI NIVINWN TMS NOUVOIN81 Z, 8nOINO3 'HSINIJ !9NI0VN0 03AO8ddV 3HJ.
HJUM 30NY0180ANOD
*833NION3 IYUNVISWIS N 03r480383d N338 SVH 0-9299 'ON IIN83cl 83GNn ONIOV80
4'33JL111N83d/83NM
_WffiVR 3Hi JO 8310VWHO
A113 3HI S (13AO8ddY SV
3dOIS IIIJ, 3HI :DNIIVIS G30tA08d 3e IWHS NOUVOW118 Sv Nv "AiiNnO]IS
33 a3GY89
JLWISIS38 NOIS083 3HI 01 3na NOIS083 oi n3 re ns ION' .10 3SYT38 IVNIJ 80AINV _WAO8ddV DNIC"D IVNIJ 01
8018d ine
*SV38V 111J NI 1HO13H NI 38ON 80 J333 338HI v 3dOIS
'SVIINION3 JO-,WO 3HI NI 4 94OLL dVY4 1308Vd JO Z 1308*d-I Idr IVNU NOdn'
SI 3cJ01S SS3'1Nn 'sudy im NI J-HO13H NI 38om 8o j33-q g 1110483d ONICW80 3H.1 N30Nn ANOM 3141 J0 N0113
400.
'VINNO-41'WO -40 31VIS "onta NVS -40 kiNnoa.
*NOII"3dO !DNnnVH 3HI 01 SGSV038
:38V 3141 N3HM 83d331,� 80 0V3IiN3A 01 IVINOZ18014) V9
HIM, 3SOdY41 AYM 811NION3 "0 3HI SIN31AI38inO38 (INV SNO1110NOD
030"D 3 71V 01 011 �WH13 c_�14(133SOb
�N iVHI S3d01S
Nn IW HJUM k'ldrqoo T1VHS 83d013A3G 3111 '31no8 InVH 03SOdO8d 3HI;
IHonAvd
SIHI NIHIIM 31tS Nouon8ISNO3 03SOdO8d
LO L, �41
now3io as
In 810 ONnnvH 01 8018d 4 0t��`
(* *n iijj qo 3rinioA C8
b bs) IiIj j o V38V 033S08aAR� TWHS
-- - �:�, �', : :,80J 833NION3 okil0 3HI r4ONJ WAO8ddV 3A13038 aw o migns
111-4 Jo *S`1V1831VV4
:NO1168OS3
LZT 0) c 1,9C Hic!3(1, 3CVH�l 0
NV 01 S'lVI831VY4 NOuon8ISNO3 80 1
b
- anOINO3 ONUSIX3 *OLLZ:
S) S 92L (*Ij *bs) ino io v3w 103 40
no CIMM, .,?33dSIHM
HId30 30"3AV (IV
( -n no, -40 3rqn-loA IN30IS38d 11V8 -T29' (090 ON ITTY3 S 30NVAOV NI S8nOH 9*
ISV31 IV Alto 3HI Hilk
3311110483d GNV 8013V81NO
111-4 JO 1HO13H IVOI183A
!DNICW80 1 833NION3 Silos '833NION3 IIA13 '80103dSNI A,110
SVH ON1133VI
*311S 3HI _qo unievis aNV NOII:DVdyyoor 3HIM 3stAov aw ONI(IV8038d V 11Nn 30N31AV403 _nVHS _SNOI1V83d0.!DNIClV8
- 6
SI :IN3S38d 3IdO3d ONIM 1 - 10.
am ON1133N 3CJV8038d 3HI
3Nn A1821cI08d
zd
_'THi (INV #L ino JO HId3G IV31183A r4nY41XVr4 3HI 0 4 3HI HAM MIS NO 013H N3313
OBNAS :(IN3031
0 ON
*(S3dO"lS 17 3CIVY4 NVN - DNUSIX3 Wcln100. ONIM180 TW 63Aq 3SIA83dns 01 '03NfVJ.38 38 IIIA 80 N336 SVH 'SkVCIIOH
GRIN0003
9NIISIX3 iS3d33IS 3HI 1 8 AII0 0 NV
SXVaNns sAvaan1VS NO NON, *14*V OV4 CJNV 'VY'd OV9AO S8AOH 31,11
_IS1001030 NO 8:33NION3 S11OS (13831SID38 V IVHI AJ11830� A8383H (3M) t
IVHS AOWdn000 wrinH, 80-4 38monais v
*NOIIVA83SNOO .40
40
VIN8 JS In (z/ _-nVH-3N0 NIHIIM DNIIV?A3dO Wlridm]l ONV DNIOVHO *9
S ON `1V.1N3F4NO81Am 031VOIJI 1 830 S 1143NIWd3d 0-4nVO' JO 31VIS 3HI jO,':AOO80NV4 1081NOO A311110 3
(INV. NOISON3 -3HI -40 �ZO'W N01103S HJLIM 30NVONOOOV NI 03TIVSNI
`SNOuvino38- a w smsv�i , sc8V0NV1S
Ott-69 Vydl JO 0-1,91,0 NVId ONICY80 SVIINION3 JO "kilo WdUS 03HONnd HIIM 03mevis- 38 TtVIHS - SUOIS, 3HI 'g L N313r43AON,,.
.01 8 KIM, 0W okUAS IV83(13A aNV 31VIS "IV001 17vF 01 ONW480ANOO
*IVAOIA43m aNV N01103M, O 38 018d (30V83AO3, Z06) S3dOIS 030VND 40 30VNaAO3 3AIJO
3-4-43 80-4 3'1131SNOdS38 38 IIVHS, (INV 'ON180HS' !DNion IS301A30 A3AVS
80M 'I"W. *OOLZ-2C9(O91.) :3NOHd 'NOII33dSNI 301A08d 01: _11VA S3dOIS (13033SO8akH -40 NOUVNIIA4830 (nnOHS *01, 11V
NfViNfVY4 GNv ion8iSNOO 'NDIS30. _nVHS 801OV81NOO 3HI
80-4 STTV0 NO 301ION SNnOH *Z 3AID 71VHS 8Oi0V8INO0 3HI T
*11YANY8 HOV3,831AV (13AOY43N 39 T7VHS S18MG
*80,GAN
.:SDNIMV 30N3N3J36'. ns
83HIO aNV IIIS U00 N3383d A180-4 S(1330X3 ISVO380-4 A,11118V808 aNV1 C13SN3011 V 80 833NI%4 IIAIO� (1383
iSIO38 V:',k8 a30VId38 CINY
(Og40 *-3NOHd #103rONd SIHI NO >180M ANV ONINN103EI 01 8018d N" AV�d (9) 3AI-4 3HI N3HM, VO ONIA80M HDV3 -40 ON3
3HI IS (13AONls3a 80 03138nISIO S1 HOIHM >18VY4
3NOS ON smnOH 9* 30IJJO S.833NION3 kilo 3H AJIION. _1IVHS 8010"INOD *Z IV '30"9qd NI 38 T1VHS NMOHS S3oiA3a 3ALL03IONd
31EIVAOIA438 TN '6 )WV IVH1 31191SNOdS38 - 313, 71VHS 83dOI3A3G 3HI *9
3NO3 3HI IV 3dOIS '36-13YJ 3HI Y408-4 omay8o OJL !DNIISIX3