1997-4929 G/I
Street Address
? IftJl
¡
t( VO c¡ 'l
Category
Serial #
qc¡~ ]i)5 /VI up¡ fh !) D
Name Description
11'1 tt
Plan ck. #
Year
recdescv
" 8
---4f/IJIIJ SHEPARDSON
~ ENGINEERING ASSOCIATES INC.
e>
8
: :',
f':.;":"'h-L~,':" "
, l- 1 "
, ,
August 1, 1997
\ '< "~I ,;: '-
S.E.A. 96171-01
Magdalena Ecke Family YMCA
c/o Good and Roberts
1090 Joshua Way
Vista, CA 92083
ATTENTION: Terry Peterson
SUBJECf:
Report of In-Place Density Tests
Minor Grading, Retaining Wall Backfill, Storm Drain
and Sewer Trench Backfills
Fitness Center Addition - Ecke Family YMCA
Vista, CA
Gentlemen:
This report presents the results of the relative compaction tests taken during the minor grading of
the subject site as tested by Shepardson Engineering Associates, Inc., on June 3, 1997. The testing
was performed at the request of Terry Peterson, Project Superintendent for The plans for Good and
Roberts. The plans for the project are titled "Expansion of Ecke YMCA, 200 Saxony Rd.", dated
May 28, 1997, prepared by Nolte and Associates, Inc. Also included in this report are the results
of the relative compaction tests taken in the retaining wall backfill, storm drain and sewer trench
backfill. The testing of the pavement subgrade and base will be reported at a later date following
completion.
The Geotechnical Investigation Report prepared by this office for the subject site is titled "Report
of Geotechnical Investigation, the Gymnasium and Fitness Center Addition, Magdalena Ecke
YMCA, Encinitas, CA", dated October 29, 1996.
The project consists of minor fills on the order of 112 to 1 foot in depth. The grading contractor for
the project was Willert Construction, Inc. Prior to the placement of fill materials, the site was
brushed and cleared of debris. The native ground was then scarified to a depth of 1 foot, moisture
conditioned to near-optimum moisture content and compacted.
Shepardson Engineering Associates, Inc.
.
August 1, 1997
8
-2-
8
S.E.A. 96171-01
Field density tests were performed in accordance with ASTM D1556-90 and/or ASTM 2922-91.
Moisture content was determined for each density sample. The results and location of the tests are
given on the attached figures. Representative samples of the tested material were obtained for
laboratory tests. Laboratory tests, to determine maximum density and optimum moisture
relationship, were performed in accordance with ASTM 1557-91, Method A or C. The results of the
laboratory compaction tests are shown on the attached Plates.
All tests were taken on a random basis. The tests, as reported herein, were performed in accordance
with the above-stated procedural methods and within acceptable standards of care. No other
warranty is expressed or implied.
Please do not hesitate to contact this office, if you have any questions regarding this report.
This opportunity to be of service is sincerely appreciated.
Respectfully submitted,
SHEPARDS 'N ENGINEERING ASSOCIATES, INC.
cc: (4) Addressee
Enclosures
Shepardson Engineering Associates, Inc.
.
.. 8 8
S.E.A. 96171-01
COMPACTION TEST SUMMARY
MAGDALENA ECKE YMCA
GRADING
Elevation Dry Relative
or Depth Density Compac-
Test of test Moisture (lbs/ Soil tion
No. Date Location (ft.) (%) cu.ft.) Type (%)
1 6/3/97 New building pad EG. 9.4 117.3 1 92
2 6/3/97 New building pad F.G. 9.8 114.8 1 90
!
I
I
F.G. = finished grade
Shepardson Engineering Associates, Inc.
.
" 8 8 S.E.A. 96171-01
COMPACTION TEST SUMMARY
MAGDALENA ECKE YMCA
RETAINING WALL
Elevation Dry Relative
or Depth Density Compac-
Test of test Moisture (lbs/ Soil tion
No. Date Location (ft.) (%) cu.ft.) Type (%)
1 6/11/97 Allen Block 154 9.8 117.3 1 92
Retaining Wall
2 6/11/97 Allen Block 155 10.6 114.8 1 90
Retaining Wall
3 6/12/97 Allen Block 157 10.2 116.6 1 92
Retaining Wall
4 6/12/97 Allen Block 158 9.5 116.8 1 92
Retaining Wall
5 6/12/97 Allen Block 160 11.0 118.5 1 93
Retaining Wall
6 6/12/97 Allen Block 160 9.8 112.9 1 89 (7)
Retaining Wall
7 6/12/97 Allen Block 160 10.3 115.6 1 91
Retaining Wall
8 6/13/97 Allen Block 153 10.5 114.9 1 91
Retaining Wall
9 6/13/97 Allen Block 154 9.5 115.6 1 91
Retaining Wall
10 6113197 Allen Block 155 8.7 118.4 1 93
Retaining Wall
11 6/16/97 Allen Block 162 11.6 116.8 1 92
Retaining Wall
12 6/16/97 Allen Block 162 9.5 115.1 1 91
Retaining Wall
13 6/16/97 Allen Block 158 10.8 117.3 1 92
Retaining Wall
14 6/16/97 Allen Block 160 11.2 116.4 1 92
Retaining Wall
( ) Retest no.
Shepardson Engineering Associates, Inc.
.
, 8 8
S.E.A. 96171-01
COMPACTION TEST SUMMARY
MAGDALENA ECKE YMCA
STORM DRAIN
Elevation Dry Relative
or Depth Density Compac-
Test of test Moisture (lbs/ Soil tion
No. Date Location (ft.) (%) cu.ft.) Type (%)
1 5/22/97 12" RCP storm drain 160 10.3 114.8 1 90
removed in pad
2 5/22/97 12" RCP storm drain 159 9.3 119.3 1 94
removed in pad
3 5/22/97 12" RCP storm drain 160.5 10.9 115.3 1 91
removed in pad
4 5/22/97 12" RCP storm drain 161 10.4 117.0 1 92
removed in pad
5 5122/97 12" RCP storm drain 162 10.0 116.2 1 92
removed in pad
6 5/22/97 12" RCP storm drain 162 11.0 114.6 1 90
removed in pad
7 5/22/97 12" RCP storm drain 163 9.7 117.7 1 93
removed in pad
8 6120/97 S.D. Box west of 150 11.1 115.4 1 91
tennis courts
9 6/20/97 S.D. Box west of 152 10.4 117.8 1 93
tennis courts
10 6/30/97 12" RCP east of 158 10.3 116.2 1 92
tennis courts
11 6130197 12" RCP east of 161 11.4 117.5 1 93
tennis courts
F.G. = finished grade BOE = bottom of excavation ( ) Retest no.
Shepardson Engineering Associates, Inc.
I
þ'
8
8
S.E.A.96171-01
COMPACTION TEST SUMMARY
MAGDALENA ECKE YMCA
6" SEWER TRENCH BACKFILL
Elevation Dry Relative
or Depth Density Compac-
Test of test Moisture (lbsl Soil tion
No. Date Location (ft.) (%) cu.ft.) Type (%)
1 7/9/97 6" sewer, southern 158 9.5 118.7 1 93
end of new building
2 7/9/97 6" sewer, southern 161 10.8 112.5 1 89 (6)
end of new building
3 7/9/97 6" sewer, southern 159 10.0 114.9 1 91
end of new building
4 7/9/97 6" sewer, southern 162 11.4 115.2 1 91
end of new building
5 7/9/97 6" sewer, southern 163 9.1 119.2 1 94
end of new building
6 7/9/97 6" sewer, southern 161 10.5 115.4 1 91
end of new building
EG. = finished grade
BOE = bottom of excavation
( ) Retest no.
Shepardson Engineering Associates, Inc.
.
MAXIMUM DENSITY AND OPTIMUM MOISTURE CONTENT
ASTM: 1557-91
Maximum Optimum
Soil Type Description Density Moisture
( pcr) (%)
1 Dark yellow brown clayey sand 127.0 10.0
2 Import base material 132.5 7.0
-
--~ SHEPARDSON
;8' ENGINEERING ASSOCIATES INC
Gto/tehnical Consul/an/s:
E"gi"ttrs-Gtologis/s
Date
July 1997
Project No. 96171-02
MAGDALENA ECKE FAMILY YMCA
Summary of Compaction Curves
Plate
SEA R 2~O Rev: 'n8
8
¡fin,'; !'¡Ihi"'cf"\",
I¡;:~i'i('('i' C;(,:/I'.'~i',!,
( ,(
! i ,".'
May 26, 1998
S.E.A. 96171-02
...
Magdalena Ecke Family YMCA
c/o Good and Roberts
1090 Joshua Way
Vista, CA 92083
ill ŒJ~V :4° ~ Œ @
ATTENTION: Mr. Jack Good
ENGINEERING SERVICES
CITY OF ENCINITAS
SUBJECf:
Report of In-Place Density Tests
Pavement Subgrade, Base, Curb and Gutter, Additional
Retaining Wall, Storm Drain and Sewer Trench Backfill
Reference:
Report of In-Place Density Tests
Minor Grading, Retaining Wall, Backfill, Storm Drain,
and Sewer Trench Backfill
Dated August 1, 1997
Gentlemen:
This report presents the results of the relative compaction tests taken on the pavement subgrade,
base, and curb and gutter on the subject site, as tested by Shepardson Engineering Associates, Inc.,
from May 27, 1997 through April 24, 1998. The testing was performed at the request of Terry
Peterson, Project Superintendent for Good and Roberts. The plans for the project are titled
"Expansion of Ecke YMCA, 200 Saxony Road" dated May 28, 1997, prepared by Nolte and
Associates, Inc. Also included in this report are additional tests performed on retaining walls, storm
drain, and sewer trench backfills. This report covers the final geotechnical testing for the project.
Previous testing results are presented in the above referenced report.
Field density tests were performed in accordance with ASTM D1556-90 and/or ASTM 2922-91.
Moisture content was determined for each density sample. The results and location of the tests are
given on the attached figures. Representative samples of the tested material were obtained for
laboratory tests. Laboratory tests, to determine maximum density and optimum moisture
relationship, were performed in accordance with ASTM 1557-91, Method A or C. The results of the
laboratory compaction tests are shown on the attached Plates.
Shepardson Engineering Associates, Inc.
8
8
May 26, 1998
-2-
S.E.A. 96171-02
All tests were taken on a random, post-compaction basis. The tests, as reported herein, were
performed in accordance with the above-stated procedural methods and within acceptable standards
of care. No other warranty is expressed or implied.
Please do not hesitate to contact this office, if you have any questions regarding this report.
This opportunity to be of service is sincerely appreciated.
Respectfully submitted,
SHEPARDS N ENGINEERING ASSOCIATES, INe.
William E. is, .E. 293
Senior Geotechnical EngineerNice President
cc:
( 4) Addressee
Enclosures
Shepardson Engineering Associates, Inc.
8 8 S.E.A.96171
COMPACTION TEST SUMMARY
MAGDALENA ECKE YMCA
RETAINING WALL
Elevation Dry Relative
or Depth Density Compac-
Test of test Moisture (lbs/ Soil tion
No. Date Location (ft.) (%) cu.ft.) Type (%)
1 6/11197 Allen Block 154.0 9.8 117.3 1 92
Retaining Wall
2 6/11/97 Allen Block 155.0 10.6 114.8 1 90
Retaining Wall
3 6/12/97 Allen Block 157.0 10.2 116.6 1 92
Retaining Wall
4 6/12/97 Allen Block 158.0 9.5 116.8 1 92
Retaining Wall
5 6/12/97 Allen Block 160.0 11.0 118.5 1 93
Retaining Wall
6 6/12/97 Allen Block 160.0 9.8 112.9 1 89 (7)
Retaining Wall
7 6/12/97 Allen Block 160.0 10.3 115.6 1 91
Retaining Wall
8 6/13/97 Allen Block 153.0 10.5 114.9 1 91
Retaining Wall
9 6/13/97 Allen Block 154.0 9.5 115.6 1 91
Retaining Wall
10 6/13/97 Allen Block 155.0 8.7 118.4 1 93
Retaining Wall
11 6/16/97 Allen Block 162.0 11.6 116.8 1 92
Retaining Wall
12 6/16/97 Allen Block 162.0 9.5 115.1 1 91
Retaining Wall
13 6/16/97 Allen Block 158.0 10.8 117.3 1 92
Retaining Wall
14 6/16/97 Allen Block 160.0 11.2 116.4 1 92
Retaining Wall
( ) Retest no.
Shepardson Engineering Associates, Inc.
-02
8 -2- 8 S.E.A. 96171-0
Elevation Dry Relative
or Depth Density Compac-
Test of test Moisture (lbs/ Soil tion
No. Date Location (ft.) (%) cu.ft.) Type (%)
15 10/24/97 Maintenance Bldg. 158.0 10.7 114.7 1 90
Retaining wall
backfill
0
16 10/24197 Maintenance Bldg. 159.0 11.5 115.3 1 91
Retaining wall
backfill
17 10/27/97 Maintenance Bldg. 160.0 10.8 117.5 1 93
Retaining wall
backfill
18 10/27/97 Maintenance Bldg. 162.0 11.4 114.8 1 90
Retaining wall
backfill
19 10128/97 Maintenance Bldg. 161.0 10.5 119.2 1 94
Retaining wall
backfill
20 10/28/97 Maintenance Bldg. 164.0 11.7 115.6 1 91
Retaining wall
backfill
21 10/28/97 Maintenance Bldg. 158.0 12.6 115.2 1 91
Retaining wall
backfill
22 10/28/97 Maintenance Bldg. 161.0 10.3 116.8 1 92
Retaining wall
backfill
23 10131197 Maintenance Bldg. 163.0 11.2 115.2 1 91
Retaining wall
backfill
24 10/31/97 Maintenance Bldg. 163.0 10.0 117.5 1 93
Retaining wall
backfill
25 2126/98 Maintenance Bldg. 157.0 13.2 115.2 1 91
Retaining wall
backfill
26 2/26/98 Maintenance Bldg. 157.0 12.8 115.6 1 91
Retaining wall
backfill
( ) Retest no.
Shepardson Engineering Associates, Inc.
----- --
2
8 -3- 8 S.E.A. 96171-02
Elevation Dry Relative
or Depth Density Compac-
Test of test Moisture (lbs/ Soil tion
No. Date Location (ft.) (%) cu.ft.) Type (%)
27 2127198 Maintenance Bldg. 159.0 12.0 118.1 1 93
Retaining wall
b~kfill
28 2/27/98 Maintenance Bldg. 159.0 11.8 117.7 1 93
Retaining wall
backfill
29 2/27198 Maintenance Bldg. 161.0 12.8 116.2 1 92
Retaining wall
backfill
30 2127198 Maintenance Bldg. 161.0 12.3 115.6 1 91
Retaining wall
backfill
I
( ) Retest no.
Shepardson Engineering Associates, Inc.
. 8 8
S.E.A.96171-02
COMPACTION TEST SUMMARY
MAGDALENA ECKE YMCA
CURB AND GUTTER
~
Elevation Dry Relative
or Depth Density Compac-
Test of test Moisture (lbsl Soil tion
No. Date Location (ft.) (%) cu.ft.) Type (%)
1 3/18/98 Access road to Final grade 9.3 124.6 1 98
maintenance building of curb &
gutter
2 3/18/98 Access road to Final grade 11.6 119.1 1 94
maintenance building of curb &
gutter
3 3/18/98 Access road to Final grade 9.5 119.5 1 94
maintenance building of curb &
gutter
4 3/18/98 Access road to Final grade 7.1 119.1 1 94
maintenance building of curb &
gutter
5 3/18/98 Access road to Final grade 11.9 114.7 1 90
maintenance building of curb & (10)
gutter
6 3/18/98 Access road to Final grade 12.5 113.4 1 89
maintenance building of curb & (9)
gutter
7 3123/98 Access road to Final grade 4.5 129.1 3 93
maintenance building of curb & (12)
gutter
8 3123/98 Access road to Final grade 4.2 130.7 3 94
maintenance building of curb & (16)
gutter
9 3123/98 Access road to Final grade 4.1 129.5 3 93
maintenance building of curb & (10)
gutter
10 3123/98 Access road to Final grade 5.0 129.7 3 93
maintenance building of curb & (15)
gutter
. 8 8
-2- S.E.A.96171-02
Elevation Dry Relative
or Depth Density Compac-
Test of test Moisture (lbsl Soil tion
No. Date Location (ft.) (%) cu.ft.) Type (%)
11 3123/98 Access road to Final grade 4.6 128.9 3 92
maintenance building of curb & (14)
gutter ~
12 3/23/98 Access road to Final grade 4.2 130.0 3 93
maintenance building of curb & (13)
gutter
13 3125/98 Access road to Final grade 6.3 132.2 3 95
maintenance building of curb &
gutter
14 3125/98 Access road to Final grade 6.0 132.6 3 95 .
maintenance building of curb &
gutter
15 3125/98 Access road to Final grade 6.1 122.0 3 95
maintenance building of curb &
gutter
16 3125198 Access road to Final grade 6.6 132.5 3 95
maintenance building of curb &
gutter
( ) Retest no.
Shepardson Engineering Associates, Inc.
8 8 S.E.A. 96171-02
COMPACTION TEST SUMMARY
MAGDALENA ECKE YMCA
SUBG RAD EIBASE
Elevation Dry Relative
or Depth Density Compac-
Test of test Moisture (lbs/ Soil tion
No. Date Location (ft.) (%) cu.ft.) Type (%)
-,
1 5127/97 Parking lot S.G. 6.1 123.4 1 97
north of bldg.
2 5127/97 Parking lot S.G. 5.9 121.1 1 95
north of bldg.
3 6/5/97 Parking lot S.G. 7.6 123.5 1 97
north of bldg.
4 6/5/97 Parking lot S.G. 8.2 121.5 1 96
north of bldg.
5 6/5/97 Parking lot S.G. 6.8 117.9 1 93
north of bldg. (7)
6 6/5197 Parking lot S.G. 6.1 119.0 1 94
north of bldg. (8)
7 6/5197 Parking lot S.G. 8.8 121.2 1 95
north of bldg.
8 6/5/97 Parking lot S.G. 9.2 122.2 1 96
north of bldg.
9 6/5197 Parking lot S.G. 10.2 125.4 1 98
north of bldg.
10 6/5/97 Parking lot S.G. 10.4 124.5 1 98
north of bldg.
11 6/6/97 Parking lot Base 7.7 122.8 2 93
north of bldg. (17)
12 6/6/97 Parking lot Base 7.9 121.9 2 92
north of bldg. (18) I
13 6/6/97 Parking lot Base 8.9 128.0 2 97
north of bldg.
14 6/6/97 Parking lot Base 7.6 127.4 2 96
north of bldg.
15 6/6/97 Parking lot Base 9.1 128.0 2 97
north of bldg.
S.G. = subgrade ( ) Retest no.
Shepardson Engineering Associates, Inc.
.
8 -2- 8 S.E.A. 96171-02
Elevation Dry Relative
or Depth Density Compac-
Test of test Moisture (lbs/ Soil tion
No. Date Location (ft.) (%) cu.ft.) Type (%)
16 6/6/97 Parking lot Base 7.3 127.4 2 96
north of bldg.
17 6/6/97 Parking lot Base 7.1 126.0 2 95
north of bldg.
18 6/6/97 Parking lot Base 7.1 126.9 2 96
north of bldg.
19 6/6/97 Parking lot Base 7.8 129.1 2 97
north of bldg.
20 4120/98 Access road S.G. 8.3 122.1 1 96
east of tennis court
21 4120/98 Access road S.G. 10.2 122.8 1 97
south of tennis
court
22 4120/98 Access road S.G. 10.3 123.4 1 97
west of tennis court
23 4120/98 Access road Base 7.6 128.8 4 97
west of tennis court
24 4/20/98 Access road Base 6.9 129.8 4 97
west of tennis court
25 4120/98 Access road Base 7.4 131.2 4 98
west of tennis court
26 4124/98 Access road Base 6.8 130.4 4 98
south of tennis
court
27 4124/98 Access road Base 7.7 127.2 4 97
south of tennis
court
28 4124/98 Access road Base 8.1 131.0 4 98
east of tennis court
S.G. = subgrade ( ) Retest no.
Shepardson Engineering Associates, Inc.
8
8
S.E.A.96171-O2
COMPACTION TEST SUMMARY
MAGDALENA ECKE YMCA
STORM DRAIN
Elevation Dry Relative
or Depth Density Compac-
Test of test Moisture (lbs/ Soil tion
No. Date Location (ft.) (%) cu.ft.) Type (%) .0
1 5122/97 12" RCP storm drain 160 10.3 114.8 1 90
removed in pad
2 5122/97 12" RCP storm drain 159 9.3 119.3 1 94
removed in pad
3 5122/97 12" RCP storm drain 160.5 10.9 115.3 1 91
removed in pad
4 5122/97 12" RCP storm drain 161 10.4 117.0 1 92
removed in pad
5 5122/97 12" RCP storm drain 162 10.0 116.2 1 92
removed in pad
6 5122/97 12" RCP storm drain 162 11.0 114.6 1 90
removed in pad
7 5122/97 12" RCP storm drain 163 9.7 117.7 1 93
removed in pad
8 6120/97 S.D. Box west of 150 11.1 115.4 1 91
tennis courts
9 6120/97 S.D. Box west of 152 10.4 117.8 1 93
tennis courts
10 6/30/97 12" RCP east of 158 10.3 116.2 1 92
tennis courts
11 6/30/97 12" RCP east of 161 11.4 117.5 1 93
tennis courts
12 7/9/97 Box southeast of 160.0 9.7 115.2 1 91
tennis court
13 7/9197 Box southeast of 160.0 10.3 116.5 1 92
tennis court
14 7/9/97 Box southeast of 161.0 10.8 115.3 1 91
tennis cout
F.G. = finished grade
BOE = bottom of excavation
( ) Retest no.
Shepardson Engineering Associates, Inc.
.
, 8 8
S.E.A. 96171-01
COMPACTION TEST SUMMARY
MAGDALENA ECKE YMCA
6" SEWER TRENCH BACKFILL
Elevation Dry Relative
or Depth Density Compac-
Test of test Moisture (lbs/ Soil tion
No. Date Location (ft.) (%) cu.ft.) Type (%)
1 7/9/97 6" sewer, southern 158 9.5 118.7 1 93
end of new building
2 7/9/97 6" sewer, southern 161 10.8 112.5 1 89 (6)
end of new building
3 7/9/97 6" sewer, southern 159 10.0 114.9 1 91
end of new building
4 7/9/97 6" sewer, southern 162 11.4 115.2 1 91
end of new building
5 7/9/97 6" sewer, southern 163 9.1 119.2 1 94
end of new building
6 7/9/97 Sewer line trench 161.0 10.5 115.4 1 91
new building
7 9/12/97 Sewer line trench 160.0 8.9 119.4 1 95
new building
8 9/12/97 Sewer line trench 160.0 9.3 120.9 1 95
new building
EG. = finished grade BOE = bottom of excavation ( ) Retest no.
Shepardson Engineering Associates, Inc.
.
MAXIMUM DENSITY AND OPTIMUM MOISTURE CONTENT
ASTM : D1557-91
Maximum Optimum
Soil Type Description Densitr Moisture
(pcf (%)
1 REDDISH BROWN TORREY SANDSTONE 127 . 0 10.0
2 CLASS II BASE 132.5 7.0
-"
3 CLASS II BASE 139.0 7.0
4 CLASS II BASE 133.4 6.2
SHEPARDSON
ENGINEERING ASSOCIATES INC
Date 4/24/97
Project No. 96171-02
MAGDALENA ECKE YMCA
Gtottchnical Consultants:
Engintm- Gtologists
Summary of Compaction Curves
Plate
SEA R 2'.10 Rev: '/38
8
SHEPARDSON
ENGINEERING ASSOCIATES INC
8
(,<'¡)!<',-!ll1ídl (¡'Ihlllldlll,;:
1"1:,11/""1"'-(;""/",,1,1'
IOU,,:) I'rl':'JI('¡/ ,lie,." S/IIII' 11i J
S,u:I.-,', (/\ 9207 J nc¡s
¡,J') / -f4LJ-c}!i1U
li\\ riJ~) 4-f'l-:ïSN
S.E.A.96171-03
AITENTION: Mr. Terry Peterson
SUBJECT:
Report of In-Place Density Tests
Subgrade, Base, and Sidewalk
Saxony Road
Ecke YMCA
Encinitas, CA
Gentlemen:
This report presents the results of the relative compaction tests taken on the pavement subgrade and base, as
tested by Shepardson Engineering Associates, Inc., from May 13, 1999 through May 26, 1999. The testing
was performed at the request of Terry Peterson, Project Superintendent for Good and Roberts. The plans for
the project are titled "Widening of Saxony Road, Ste. 9+29 to Sta. 13+ 18 dated May 5, 1997, and prepared
by Nolte and Associates.
The compaction of the tested area had been partially accomplished prior to our arrival onsite. Field density
tests were performed in accordance with ASTM 01556-90 and/or ASTM 2922-91. Moisture content was
determined for each density sample. The results and location of the tests are given on the attached figures.
Representative samples of the tested material were obtained for laboratory tests. Laboratory tests, to determine
maximum dry density and optimum moisture relationship, were performed in accordance with ASTM 1557-91,
Method A or C. The results of the laboratory compaction tests are shown on the attached plates.
All tests were taken on a random, post-compaction basis. The tests, as reported herein, were performed in
accordance with the above-stated procedural methods and within acceptable standards of care. No other
warranty is expressed or implied.
ECEIVED JUN 1 81999
June 17, 1999
8
-2-
8
S.E.A. 96171-03
Please do not hesitate to contact this office if you have any questions regarding this report.
Respectfully submitted,
SHEPARDSON ENGINEERING ASSOCIATES, INC.
~
Wi iam . Ellis, RCE/GE
Senior Geotechnical EngineerNice President
WEE:sj
cc: (4) Addressee
Enclosures
. 8 8
S.E.A. 96171-03
COMPACTION TEST SUMMARY
YMCA
CURB, GUTIER, AND SIDEWALK
Elevation Dry Relative
or Depth Density Compac-
Test of test Moisture (%) (lbs/ Soil tion
No. Date Location (ft.) cu.ft.) Type (%)
1 5/13/99 West side/Saxony Rd. S.G. 6.8 123.3 5 95
Sta. 9+25
2 5/13/99 West side/Saxony Rd. S.G. 7.6 124.0 5 96
Sta. 10+ 10
3 5/13/99 West side/Saxony Rd. S.G. 6.4 125.9 5 97
Sta. 10+60
4 5/14/99 West side/Saxony Rd. S.G. 5.8 125.1 5 97
Sta. 11+20
5 5/14/99 West side/Saxony Rd. S.G. 4.8 123.0 5 95
Entrance
6 5/14/99 West side/Saxony Rd. S.G. 5.3 125.6 5 97
Sta. 12+50
7 5/17/99 West side/Saxony Rd. Base 8.3 127.4 4 96
Sta. 12+70
8 5/17/99 West sidelSaxony Rd. Base 7.5 126.9 4 95
Sta. 12+05
9 5/17/99 West side/Saxony Rd. Base 7.0 129.2 4 97
Sta. 11 + 10
10 5/17/99 West side/Saxony Rd. Base 4.5 126.9 4 95
Sta. 10+40
11 5/17/99 West side/Saxony Rd. Base 6.8 124.6 4 93 (14)
Sta. 9+90
12 5/17/99 West side/Saxony Rd. Base 7.2 125.5 4 94 (13)
Sta. 9+55
13 5/17/99 West side/Saxony Rd. Base 7.5 133.2 4 99
Sta. 9+55
14 5/17/99 West side/Saxony Rd. Base 7.1 128.5 4 96
Sta. 9+90
15 5/18/99 West side/Saxony Rd. Base 5.1 127.1 4 95
Sta. 9+65
S.G. = Subgrade ( ) = Retest no.
Shepardson Engineering Associates. Inc.
. 8 8
~ -2- S.E.A. 96171-03
Elevation Dry Relative
or Depth Density Compac-
Test of test Moisture (%) (lbs/ Soil tion
No. Date Location (ft.) cu.ft.) Tvoe (%)
16 5/18/99 West side/Saxony Rd. Base 4.6 127.1 4 95
Sta. 10+35
17 5118/99 West side/Saxony Rd. Base 6.0 127.5 4 96
Sta. 10+90
18 5/18/99 West side/Saxony Rd. Base 4.4 128.7 4 97
Sta. 11 +60
19 5/18/99 West side/Saxony Rd. Base 7.3 130.0 4 97
Sta. 12+45
20 5/18/99 West side/Saxony Rd. Base 6.2 129.2 4 97
Sta. 13+00
21 5/26/99 West side/Saxony Rd. S.G. 8.0 120.8 5 93
Sidewalk
Sta. 12+40
22 5/26/99 West side/Saxony Rd. S.G. 8.6 116.9 5 90
Sidewalk
Sta. 11+32
23 5/26/99 West side/Saxony Rd. S.G. 7.3 122.4 5 95
Sidewalk
Sta. 10+20
24 5/26/99 West side/Saxony Rd. S.G. 6.8 117.5 5 91
Sidewalk
Sta. 9+40
,
,
,
S.G. = Subgrade ( ) = Retest no.
Shepardson Engineering Associates. Inc.
. 8 8
~
S.E.A. 96171-03
COMPACTION TEST SUMMARY
YMCA
SUBGRADEIBASE
Elevation Dry Relative
or Depth Density Compac-
Test of test Moisture (%) (lbsl Soil tion
No. Date Location (fU cu.ft.) Type (%)
1 5/25/99 Saxony Rd. S.G. 7.1 120.8 5 93 (5)
Sta. 12+85
2 5/25/99 Saxony Rd. S.G. 8.0 123.7 5 96
Sta. 11+75
3 5/25199 Saxony Rd. S.G. 7.3 124.4 5 96
Sta. 10+35
4 5/25/99 Saxony Rd. S.G. 7.8 124.1 5 96
Sta. 9+70
5 5/25/99 Saxony Rd. S.G. 7.2 123.9 5 96
Sta. 12+85
6 5/25/99 Saxony Rd. Base 7.8 128.9 2 97
Sta. 12+60
7 5/25/99 Saxony Rd. Base 8.0 126.3 2 95
Sta. 11+95
8 5/25199 Saxony Rd. Base 6.9 128.0 2 97
Sta. 10+90
9 5/25199 Saxony Rd. Base 6.7 130.9 2 99
Sta. 9+90
,
I
Shepardson Engineering Associates, Inc.
June 1999
8
8
S.E.A. 96171-03
MAXIMUM DENSITY AND OPTIMUM MOISTURE CONTENT
ASTM: D1557-91
MAGDALENA ECKE YMCA
Maximum Optimum
Density Moisture
Soil Tvoe Descriotion (pet) (%)
1 Reddish brown Torrey sandstone 127.0 10.0
2 Class II base 132.5 7.0
3 Class II base 139.0 7.0
4 Class II base 133.4 6.2
5 Yellow brown silty sand 129.5 7.0
SUMMARY OF COMPACTION CURVES
ClU'l'es.lSum
SheptJl'dson Engineering A$ISOCÜJtes, Inc.
~
0;
-.,.
8
8
-,
DRAINAGE STUDY FOR ECKE YMCA EXPANSION
200 SAXONY ROAD
;
.
,
I
EXISTING CONDITIONS
The YMCA site presently drains into two on-site inlets connected by a 12" storm drain.
Westerly of the existing stonn drain located near the tennis courts on site, the system
becomes an 18 .. stonn drain, which drains offsite. The westerly portion of the site
drains as overland flow into a PCC brow ditch, which discharges to an offsite drainage
system.
PROPOSED CONDITION
The proposed condition will realign the 12" stonn drain connecting the inlet in the mainb
parking lot and the inlet near the tennis courts. Drainage basins on site will remain
substantially unchanged; the westerly curb inlet will be reconstructed in place to accept
the realigned stonn drain from the east. A building expansion will be constructed, a new
service building and drivewaylservice yard will be constructed south and west of the
tennis courts, and the existing PCC ditch west of the tennis courts will be repositioned to
a location between the tennis courts and the top of a proposed crib-lock retaining wall.
The curbed parking island in the parking lot north of the existing drop-off area will be
reconstructed in place to provide for positive drainage and amended paving.
SUMMARY
The attached calculations and charts summarize runoff volumes for the drainage basins
resulting fOnD the proposed building construction and associated grading. Capacities for
the existing and realigned drainage facilities are also calculated.
The existing facilities on-site that are realigned discharge into a P.C.C. ditch that drains
offsite to drainage facilities on CAL TRANS right of way. Because neither the on-site
drainage basin nor the ultimate runoff at buildout have been changed by the new
construction, and the CAL TRANS offsite facilities are typically designed for buildout
condition, no impact on the downstream conditions will result.
r,.! ie",: i:)
i,C" ':: c,;
APR 08 1997
ENG~\!EEHjN(?¡ SERV¡CES
CITY OF ENCiNiTAS
C:j ~FS)
{/?GvroSG-O ':;>-3 (-97)
t .
8
.8
CRITERIA AND BASIS OF CALCULA nON
1. County of San Diego Design and Procedure Manual; County of San Diego
isopluvials.
2. City of San Diego charts as indicated.
3. Drainage calculations evaluated for 50-year storm.
4. Use Rational Method: Q=CIA
5. Tc (Time of Concentration) and I (Intensity): See attached calculations
6. C _factor (runoff coefficient) $'0
Use C= 0.95 for paved areas and roof areas
Use C= 0.50 for landscape areas
~)(. ~~
~arnes R. Hettinger R.C 31756
Exp.12-31-00
3"")(-97
Date
Cz- 0 ¡e 8)
(R¿V{.$€V ::?-3'I-~7)
. .~
8
DRAINAGE STUDY FOR ECKE YMCA EXPANSION
200 SAXONY ROAD
EXISTING CONDITIONS
The YMCA site presently drains into two on-site inlets connected by a 12" storm drain.
Westerly of the existing storm drain located near the tennis courts on site, the system
becomes an 18 .. storm drain, which drains offsite. The westerly portion of the site
drains as overland flow into a PCC brow dit~h, which discharges to an offsite drainage
system.
PROPOSED CONDITION
The proposed condition will realign the 12" storm drain connecting the inlet in the mainb
parking lot and the inlet near the tennis courts. Drainage basins on site will remain
substantially unchanged; the westerly curb inlet will be reconstructed in place to accept
the realigned storm drain from the east. A building expansion will be constructed, a new
service building and drivewaylservice yard will be constructed south and west of the
tennis courts, and the existing PCC ditch west of the tennis courts will be repositioned to
a location between the tennis courts and the top of a proposed crib-lock retaining wall.
The curbed parking island in the parking lot north of the existing drop-off area will be
reconstructed in place to provide for positive drainage and amended paving.
SUMMARY
The attached calculations and charts summarize runoff volumes for the drainage basins
resulting form the proposed building construction and associated grading. Capacities for
the existing and realigned drainage facilities are also calculated.
The existing facilities on-site that are realigned discharge into a P.C.C. ditch that drains
offsite to drainage facilities on CAL TRANS right of way. Because neither the on-site
drainage basin nor the ultimate runoff at buildout have been changed by the new
construction, and the CAL TRANS offsite facilities are typically designed for buildout
condition, no impact on the downstream conditions will result.
Ú ~FS)
(RèVf.$éO ;-3(-97)
~ 8.
8
CRITERIA AND BASIS OF CALCULA nON
1. County of San Diego Design and Procedure Manual; County of San Diego
isopluvials.
2. City of San Diego charts as indicated.
3. Drainage calculations evaluated for 50-year storm.
4. Use Rational Method: Q=CIA .
5. Tc (Time of Concentration) and I (Intensity): See attached calculations
6. C _factor (runoff coefficient) 5'0
Use C= 0.95 for paved areas and roof areas
Use C= 0.50 for landscape areas
Jo..-..-- ){ . ~~
¡lames R Hettinger RC 31756
Exp.12-31-00
3'-31-9 ì
Date
Cz- op e)
CR¿:V~t!šV :?-JI-~7)
8
NOLTE and ASSOCiATES,. Inc.
Engineers 1 Planners / Surveyors
UBJECT
éCJct: -r /1\ C A
¡.2v I'-ro,cF / ~ C H
,
~ 4.(5q
.8
!::. ~e S' 3" /
Z-/(-;;? / 3,) I-~?
I
JOB NO.
DATE
DESIGNED BY
CHECKED BY
;j-¡t71
t7
C A L LV c.....A~ -r e- l. I /~O f=-ej tt!.. 1< G'7I11. c..; ß^/ ;?"~/ \./'6
I
A-l.J.t:A- .-+.Jt¡;;òi u oS c fCcJ,d. Âc...c.. -rf'f,ti'ð6 """'~ I'M .s7'U~y
/
"r.:
=-
;: ß ((,1- c.) Võ
~
1- '3 (/. 1- ().9f) Vc;,o
ç;-;:;?
Tc...
( V.lC Art.-C,ð
r:. -,
c .,
54 .:5 3 1"-1/ I ^-' v r~5
(CI~[.' (0 M'I'-")
I,., ~ ':=
4.5 1"-1. If 1ft
.
I::;t ~
:]. 'ß I^í. IÍ~II¿ ,
A (2.. éA C
A, ~ -12.. A c. o.9s
A, 4. C. 1 A c, 0.65
1\3 0.52 4c. (J.8S
I:¡-a
3. 8~./J,..
~.TO
2,~ Cr5
x~o
4,.5 ;....../1". 3.1 cF.5
(('°0
¡Cf-tj CF:;
2.'cfS
All 0.057 AC. 0..$ ð 3. B;.,./L, I. I CF.;
Cl-/éc'tC- ¡IN!. er C;..PIAC rry (AT PTL i)
Q.r.:; ro 11oJc..e7' :: L-. (þ cF:::
(3)«.57", 5' riPE "8 'I 1;<.fr...e7' J'V" SUN/-"
~)
4-.5 ~ , lA.
CA~Acl-rY ::::
I.s c,r-~/ roo.,- o,c OpeAlrAl§
:;0 CA"".C-I-ry ~ (q))( !¡.s) := <;.0
CF:; -) 2. b
c.FS
/7-' if~
3. I Cr5
I. J c.r:-~
(j \ ~.
--c::::.
(3 OF 8)
8
.8
NOLTE and ASSOCIATES"Inc.
Engineers / Planners / Surveyors
JOB NO. SD 0 .33/
DATE 2 _//'-;X? I )-J>r-I)?
DESIGNED BY (,.},It}1-
-/
UBJECT é'e,cé YA1 c;IA
CHECKED BY
CI-f ê c 1=- P 11./ é..~ c..¡><. ¡';;04 C I T~ i ---Þ 2-
c?~,~ "¡'" el¡.l{;; ( r/i- t:) ~r\ A ~) -- /, /
ere:
,}o ;? Q.: ~ = /../ -+ '2-. \0 =
3. 7 C f-='
/2" J2cP e
/. 0 Ïo -) DkL~ c,,5G, (BG % FU(;¿.) <:: /. 0
c.~..
~
r -,..~
:'- c.;.. ¡;;;:-
\
c:..,:+,c. ::i-4~ ~A CIIC~)
CI-/êr-Ic.. /N'-é7' C,APIi'1C("'("-,' (Á7 ;::'7', 2)
(.2e:.--=ð^/srdVC~ IS' A-I 1iC..IL~ ON" .::L-QP'E ~/;Oro
CPs~
I'Af Gu rrCR.:, /4,'
cr.s
I
o~ oeyr~( r:>r Fc..c;)\"v /N' Gf..J r-~ = 0 - 51 <:::: o. 8) c; (.),<8
V = 3. '2. r¡:;S (~"""""L.~~)
Pe32 c, r"-I" ðF.::A1V' 0'(;(:'0 Crf.A,LT rV"ù f / -rOIf. I Z.
(A 7'~A C-.4 ~ )
C,AP'A c (r-y = c? = O.? L (A-i '-( ) 3('2.
()Qù Q ~ (6. ~(/4-){ 0..33 +0 f 40)3', (~~ ~: ;Ø~~I"?<) '1
L=:;' )
cp:: C;. / c.rs (TO ;lAre. ~ / PII;}ÇJ 2 -"3)
<:).c...
-eo
0
00
rLù\M bY::: /4.') c~ - c;..{ cPS'-= 8 - ~ Cr.:5
(':"'-0 pr:; r ,,-I -r'" .3)
Cr'icct::- ¡;¡)/P6" CAPACL"rY , 2. - 3
2" ([).1'(1 1't'J PII;}~':::- 3- ";) c.F~ .; G,! CF.7 :::: '.2> cr.s
/8'- RC-P c:
/2.,':) % =>
DId...:: O.~.s-
(3r.t.7ÚPU¿,..LJ < 1.0 O,c.
, ""'e::..
( .$ tSt!f c:. ..... t.. Co -S" I-f e. t!"?" ""'" r .,... ~ C 10-/ ~ J
(4- OF-B)
8
.8
NOLTE and ASSOCIATES,. Inc.
Engineers / Planners / Surveyors
JOB NO. S 0033/
DATE -¿-¡(-57 ( »-)(-"77
DESIGNED BY j/;t;>{....
V
UBJECT CCIt:&- YAI'fCA
CHECKED BY
C-I-ICC Ie. I A/ L e 7' C '" ,"';" C 17"'"';"
(AT pr 3)
£. Qfl ro ("'IV L er -=- 8. ~ -I- A 3 =- 8.8 -+ 2_" :::- I/. 4- cr-..:
(~~~) -
/0' A -/ /A/C- er /N .5Vr--t'I~
CAPAClrY '=
I~S c.r.: /r-?", . c)r D/:?E:'AI/^rG
~
J<J
=-A,s/Acl-r'/ -= (Í-.J) KVO)': 1.5.0 ere: ::> //4 cr:::.
o.~.
--c!!!!::.
c: (-f ¿c: Ie
P IP'€ CAPA C / 'T' r
,1
U ,eCI'?
Oð w/\.f.S'TR e A WI
or& I'JJ"-~ Ar Pðt'Afr -3 -- .
2-tþ" e
I~ 3 9-/'0
¿ Q~a TO PIP€' .: //.4- Cr5 of- ~. 8 C-rS :: 2../- 2 C-F5
(,,¡'/t.e'r@ 3) (p"e z....~
2J.L. C-Fs => D/cl:: 0,'8 (&B<.-2..s/<r--r..I,-'-) </.0
c), It ,
~
(5 OF e)
8
12"RCP @ 1.0 %, ECKE YMCA
Worksheet for Circular Channel
Project Description
Project File
Worksheet
Flow Element
Method
Solve For
n:\sd0331\calcs.fm2
12" @ 0.9%
Circular Channel
Manning's Formula
Channel Depth
Input Data
Mannings Coefficient
Channel Slope
Diameter
Discharge
0.013
0.010000 ftlft
12.00 in
3.70 cis
Results
Depth
Flow Area
Wetted Perimeter
Top Width
Critical Depth
Percent Full
Critical Slope
Velocity
Velocity Head
Specific Energy
Froude Number
Maximum Discharge
Full Flow Capacity
Full Flow Slope
Flow is subcritical.
0.86
0.72
2.37
0.70
0.82
85.93
0.010784 ftlft
5.15 ftls
0.41 ft
1.27 ft
0.89
3.83 cis
3.56 cis
0.010786 ftlft
ft
ft2
ft
ft
ft
11197
:23:54 PM
.8
Nolte and Associates, Inc,
Haestad Methods. Inc. 37 Brookside Road Waterbury, CT 06708 (203) 755-1666
FlowMaster v5,07
-
/fD ~
\..8" 01= ;r)
8
18".RCP @ 12.9%, Ecke YMCA
Worksheet for Circular Channel
Project Description
Project File
Worksheet
Flow Element
Method
Solve For
n:\sd0331 \calcs.fm2
pipe flow cales, YMCA
Circular Channel
Manning's Formula
Channel Slope
Input Data
Mannings Coefficient
Depth
Diameter
Discharge
0.013
6.25 in
18.00 in
9.80 cfs
Results
Channel Slope
Flow Area
Wetted Perimeter
Top WIdth
Critical Depth
Percent Full
Critical Slope
Velocity
Velocity Head
Specific Energy
Froude Number
Maximum Discharge
Full Flow Capacity
Full Flow Slope
Flow is supercritical.
/01/97
7:47:50 AM
0.129750 ftlft
0.55 ftz
1.89 ft
1.43 ft
1.21 ft
34.72
0.008996 ftlft
17.97 ftls
5.02 ft
5.54 ft
5.13
40.70 cfs
37.84 cis
0.008705 ftlft
.8
Nolte and Associates. Inc,
Haestad Methods. Inc. 37 Brookside Road Waterbury. CT 06708 (203) 755-1666
FlowMaster v5.07
(7 OF 8)
8
24" RCP, @ 1.34%, Ecke YMCA
Worksheet for Circular Channel
Project Description
Project File
Worksheet
Flow Element
Method
Solve For
n:\sd0331 \calcs.fm2
pipe flow cales, YMCA
Circular Channel
Manning's Formula
Channel Depth
Input Data
Mannings Coefficient
Channel Slope
Diameter
Discharge
0.013
0.013400 ftlft
24.00 in
21.20 cis
Results
Depth
Flow Area
Wetted Perimeter
Top Width
Critical Depth
Percent Full
Critical Slope
Velocity
Velocity Head
Specific Energy
Froude Number
Maximum Discharge
Full Flow Capacity
Full Flow Slope
Flow is supercritical.
3/31/97
3:11:45 PM
16.4
2.28
3.89
1.86
1.65
68.25
0.008694 ftlft
9.28 ftls
1.34 ft
2.70 ft
1.48
28.17 cis
26.19 cfs
0.008783 ftlft
in
ft2
ft
ft
ft
.8
Nolte and Associates. Inc.
Haestad Methods. Inc. 37 Brookside Road Waterbury. CT 06708 (203) 755-1666
FlowMaster v5.07
(8 of ~
i -
I
i
8
.8.
CHART 1-104.12
f ".
t- L5'-i
~ ~ ..c:m
~ I~ ,..
r
ItU I Of: III T I AI.. STIlE [T
Ole SIO£ 0IiI. T
~ I
I; ::~ 1/ ~~ ~~, ~~;:-+I
"'" ' I , =- -........./P I! ~ +
II I """"'.......11 ~~i ¡ì:
10 / I I V 0, I'" r-... 0: ~ , :/ 1'...... V I -
. '- 'f, II ~ 1 f"""......
.~ :/1" ~ I! : ~ 'I:;
f' L:? I IfT",....! I I:¡ /""""", I' ¡
I ~; I I' I ~ , ....... : - I
I_' , '/ r--...,,~ ö / ~: I I
~!V!li~'/I~/1 I~V
'" Rj j '9, I ~ .... f...,. . I 'i...... I I,
~: V! ¡ ;~1f T'~~i"~ ¡1
~ I ; I ; ,7 .' Iii r;!' -....to: . I..:']: "'.. if ~ ~ I
; z !-*l' cr ~'J""I¡ I-
. 1.1: . I I 1"" !, I' I ~~:............. ..-:-tiI 7"--..
2t w' t II ",",: I .~ ....~Õ}, ~ ,I'
~- ~.V III """'~~J ~ ..... ..!'¡, J
I I ~ ~ ~ ,- I ,-... fAl ...!
.. I '. I - .... II, .' I ,ì'"( ,~ , . '""., J ,J? .
Qt;I'~: Ii', .~. "'~ì _I".
0.1 I ' ... / fL'V "
Af ' [".....1 I I ~ '.... 1;1, ............/- "7 -¡-
AI I 1/ """-.c" t-'.... 'I l~ / I -
I! I~. ......:........
A5- , ~ """""" /: 7'~ I
04 - ",V I I ~ " ..... ;~ / " "'-l -
'-1 I IiI. I'll" I I I"
I I 4 5 I ., . . 10 -~ zo JO.O JO
OISCHAIItGE (c. F. 5)
ONE SlOE
EXAMP1..E:
G¡"III: 0-10 S 12..58,.
etao" "",: 0.,"11 I 0.4. Y8lDcity I 4.4 (ILL
"
REV.
CITY OF SAN DIEGO - DESIGN GUIDE
GUTTER AND ROADWAY
DISCHARGE - VELOCITY CHART
SHT. NO.
'.
r;J
70A
~,
..
,'"
8
URBAN AR'EAS
TIME OF FLOW
.8
OVERLAND
CURVES
--"
ICIO
Q
I
..
...
...
...
...
~
;:
100
z
400
...
u
Z
0(
..
'"
ëi
40
..
I
."
=
Ž
3
~
200
.'..'.. "1""---'"
..-,..-.- ---.--,..
L..-:-_..., .,..c....,-
""-',--, ..,..-....
~~. r:-:.:::;: l~:::--:-_:-:-.
~:._......:-"; ""'!-
..._~..'- --..,.,...
".,.-...-- _.
JOO
, .._..~'- ..-
. : . . . ~.:::... ~ ::':.:...=-- . :' ~"'--..;...::
._--,.~....._._--...._-- .---
'~..- .--...--
. .----- -...--.
~ :;:::.-- :::::::"::':=-,
,,-""----' ,..----
, .: :::-;-...- :':":':"'::::':-=
---' - ---
-'.----'- .,.-
0
Surf.c. FI- Ti- Curves
#
-- -. --------' .
EXAMPLE.. :
Gtt VEN L-E.N GTH OF FLO\N ~
S i-OPE... - I. D 0/"
COE-FfiC, E...N'T OF- Rv~o¡:ç:
OVE-K. '-AN D ?L..DW'ï\ n1 E. =
86
400
FT.
~
:: . 70
15'
K.£ A i:)
¡'V\ IN VIE.. 5
( I -E )
..'._'d._._._--.-'-- - -
eo..'
451
-"....,.,.~,....,
"'I~
-25
301 I LA!
'\ !
151
:;:0
(þ
<
....
1/1
(þ
ø.
338
(
"
5,7,
""""V"""
....
.......
00
tn'
8
451
Prep..ted b,
:a. u.s. DEPARTME~T OF COMMERCE
:g NATIONAL OCEANIC AND AT IOSPIIERIC ADMINISTRATION
.~ IPECIAL STUDIES BRANCH. OFFICE O¡':" 'DROLOGY. NATIONAL WEATHER SERVICE
CI
....
><
><
....
,
CI
30'
Jl8°
45'
301
15 '
1170
45'
3D'
Revised 1/85
IS' . 1160
APPENDIX XI-D
.--
--_.- -_.--.- ----._---
DEPARTMENT OF SANITATION ~
FLOOD CONTROL
\~,p
¡;~
~ P,.po 'd by . I~~ .
3 u.s. DEPARTMEt\ r OF COMMERCE \\ .
11 NATIONAL OCEANIC AND AT- OSPIIERIC ADMINISTRATION {;:. '>
3 ,JPECIAL STUDIES DRANCII. OFFICE OF 1\ rmOLOGV. NATIONAL WEATHER SERVICE!
~ 3D' I I
I
;')
451
301
151
}
,.
33-
¡
)
4
...
0
n
451
1180
1170
1;51
15 I
301
151 11 ÓO
APPENDIX XI-G
-8
8
~<~*U, J.~~~;.;'J)~;':-"""""" ....,~,~,. u~.l!ftJ""Pf""",,48h:,,~IG" cHì\R'r-P-------
-
.
t. ".' 0 "~ I =i.-rrr I. fi iTITT1ETrITnU'! JJ-t~'I""IIIIIII="ill"'llIlrõ-'1 . ",o::-64Su-C'--UJnHhTIi 1" Directions for Application:
I.' ~ . - _do- quatlon. - 7.44 P D
.: _.-: 0 .. 0;:".: . --I 6 l} From precipitation naps detennine 6 hr. and
1. 0 . . . - 24 hr. amounts for the sel ected frequency.
These maps are printed in the County Hydrology
Manual (10, 50 and 100 yr. maps included in th¡
Design and Procedure Manual).
2) Adjust 6 hr. precipitation (if necessary) so
that it is within the range of 45% to 65% of
the 24 hr. precipitation. (Not ùrrlicable
to Desert)
'_0 --.-. ..... ..
I of the chart.
"4} Draw a line through the point parallel tö, the
plotted lines.
15} This line is the intensity-duration curve for
the locatipn being analyzed.
Application Form:
a} Sel ected Frequency .s 0 yr.
".. :.. ". .. - 1) P 6 = 2. -¿'5 in oJ P 24 = :3 - ~c.?, * P 6 = .37 %*
:::. '.: ~_.- : .: p
~:~~:~:~~...'~:_:..., 2} Adjusted *p = Z,L~ i~. .
-- -'- . - - " 6
- .. "'" .
..... --- -~":_:. 3} t = /'0
'" --- -- c
00 - _. --"" . 0
U1.2 .. 4} I = 3. ¡;;, in/hr.
min.
;Þ
'"0
'"0
tT1
a
.....
><
~ .1
~ 10
-,
-~-
..~.._".....~......
I mil
..
*Not Applicable to Desert Region
I
-,
,- ..
.~-
...
1-1-.-
...
-
-,
.0-'
,-
Duration
2 3,
Hours
4
5
6
so y~ 12
15 20
Minutes
30
40 50 1
-
Revised 1/85 APPENDIX XI-A
-_. - ---.
----.--....- .
.
1
1
]
j
i
~
flOOD CONTROL
45'
,
30. I
.'
~
(I S(~
33-
~""'"
8
45'
prcP8i'd by
U.S. DEPARTMEN r OF COMMERCE
NATIONAL OCEANIC AND AT. OSPIIERIC ADt.IINISTRATION
SpaCIAL STUDIES BRANCH. OfFICE OF II OROLOGY. NATIONAL WEATHER SERVICE
30'
Jl8'
45'
30'
15'
11]°
1151
301
151
1160
Revised 1/85
APPENDIX XI-E
FlOO) CONTROL
451
301
151
JJ8
451
'8
-.
,"
,-'-
8
u.s. DEPARTMENtr OF COMMERCE
Plepof," br
.
,
,
1
.
j
..
<
<
..
NATIONAL OCE^:<;IC ^,fO A"nlo:iI'II£RIC AO.IINISTRATIOH
'POCI'L ITDDIES ."><"'3D::'« Df ~.'DLDGY' II.YO;.. ."T",. """CE
::
IIUO
117°
I~; I
, I (J 0
, I ~ i I
I. ~j I
1.-. 1
)01
:In.
Revised 1/85
APPENDIX XI-II
-
--... Jl,fJ :~"~~lJ!1~:- ";1~.b.U~"I'JjI~~""""""'" ",...,......~h.tA~u """~J.leh,¡S~ÎG-Ñ-CH^RT
;.".:..;.,;:~;~~ 'D'::'64Sum,mdm'l!
. 1.1-
- - .
i Blrw WillmtI .
;.<
~ ,I
~ 10
-,
~'
.~
.4.
-
15 20
Minutes
30
40 50 1
Duration
2 3
Hours
4
5 6
-
~_..-
Directions for AppHcation:
1) From prec i pita t i on na ps detenni ne 6 hr. and
24 hr. amounts for the selected frequency.
These maps are printed in the County Hydrology
Manual (la, 50 and 100 yr. maps included in th!
Design and Procedure Manual).
2) Adjust 6 hr. precipitation (if necessary) so
that it is within the range of 45% to 65% of
the 24 hr. precipitation. (Not «pp1icable
to Desert)
3) Plat 6 hr. precipitation on the right.sid~ ~
of the chart. WI'
4) Draw a line through the point parallel to, the
plotted lines.
5) This line is the intensity-duration curve for
the locati~n being analyzed.
Application Form:
0) Selected Frequency /QO yr.
1) P6 = 2.7 in., P24= 4-3 J *P6 =
P24
in.
, 2. & %*
8
2) Adjusted *P 6= 2. . ?
3) tc = /0 min.
4) I = CI.5" in/hr.
*Not Applicable to Desert Region
,
/ f!) t!)
Y t!!f" .e
Revised 1/85 APPENDIX XI-A
--- --,--".----.""",.--
'0 -
NOLTE and As~bClATES, Inc.
N~ Engineers 1 Plar,llers 1 Surveyors
~
JOB NO.
DATE
SUBJECT
DESIGNED BY
CHECKED BY
, q ') . ..;)
/5 ,.4~
A, I /. 7 ... ì.
-
- A..oo,.
¿cr-] ~ 1.
~
76. ß .-. L
~
P!},(. - 7 8. )..:- z. ::'>
6). ") 2.. At,
+ ~ ~IV , '" L 67'"
AL
r2..L,'ß~l
/ ~ro. .3 ;.-, z...
:: I?~, 6':- t
+!ì), 7"':"L+ 3b,l..~ 't.:- 33(".(:~t.::)
- 1
'2.-£\.~ ...........-'
~
2co./ - L
'3, <' Cj 1+ c,
~ 1..
I¿L-4-~
~ì.'1::-'-
". -'. ,..., .
.., I 'r (rt' " II'
U ;. i ~"" i f.e:. ¡ ::: ! ' ~.,:
If) l:'. ".., _':; I
~.., FEB 1 3 1997
ËNG¡f\/EEH-"NG', (!:;'-RVir'E('
'.. -- vC: Iv"
CITY OF ENCINITAS
(() . )..:.... L (
('a - ~..:.. 1- j
(O,.5~l.
A... ::.
s ,- C1 (0 :..., 1. + ).1-3'::-1.-+
'1, , 6 ~ l.- GJ. 'ð1 ~ 1 => ð. '5 ~
A. C,
A:3 ~ Iq."?" (, ~ 1. 7..
jAr. R;: ., J (95.1, .:...- 'L + It-13 ~ 1.. ..n...?5~'::-1. ~ !f:j', Bo~1.:: 1.53 AC,
rrv.> v ~ ... + lei-. 2.. s ;:.... ê.
I
I
I
I
I
I
I
I
I
I
I
I
I,
II
I
I
I
I
I
8
SHEPARDSON
ENGINEERING ASSOCIATES INC
8
m- ~m_m~__----"m~m -
"_m" mmmmm moW #Œ,~-ß rmn \W Z:æ prosP.IT;~':398
-,' ~'4~JO
" r: r: (1 . ~ ,FAX .. '9~5824
, . ~ ,1QQ7 '~.
SSW-A [/ CamirJ<1 Rea,
Carlsbad, CA 92008
619/931-9991
FAX 619/931-0547"
GeotechnIcal Consu1/anls:
Engineers-Gtologists
February 10, 1997
IV 0 L ';;-Cr: ": ") I'! A t'\ S
UI¡U ~ DC.
S.E.A. 96171-01
Magdalena Ecke Family YMCA
c/o Good and Roberts
1090 Joshua Way
Vista, CA 92083
r 0') ii' ';;:' ! l;, !! ',!i ."
i no(' '.
Ud
-' FEB 1 3 1997
SUDJECI':
Põveinent S~'TúI'ä1, Sectiüfi RecOmmeridations
Gymilasium and Fitness Center Additions
Magdalena Ecke YMCA
Encinitas, CA
ENGINEEíW~G SERVICES
CITY OF ENC!NITAS
Gentlemen:
This letter provides recommendations for the pavement structural sections for the proposed service
road and parking lot additions at the subject project. These recommendations have been prepared
following the request of Jim Hettinger of Nolte and Associates, project Civil Engineers,
The R-value used in preparing the recommendations herein was that tested and reported during the
previous geotechnical investigation for the site, prepared by Leighton and Associates in 1985. The
R-value test was on a sample of the native silty sand materials which are similar to those anticipated
for the subgrade of the service road and parking addition areas. This R-value result was 76. In
consideration of the traffic loading and frequency, we have selected Traffic Indices of 4.5 and 5.0 for
the parking lot addition and service road pavement respectively. Based on the above parameters,
the following pavement recommendations are provided.
Asphaltic
Concrete (inches)
Aggregate
Base (inches)
Parking lot addition
2.5
4
Service road
2.5
5
It's recommended that upper 6 inches of the subgrade and the Aggregate Base be compacted to 95%
of the maximum dry density as determined in accordance with ASTM Test Procedure D1557-91. The
Aggregate Base should conform to the specification for Oass II Aggregate Base as specified by the
Shepardson Engineering Associates, Inc.
I
I
I
I
I
I
I
I
I'
I
I
I
I
I
I
I
I
I
I
8
e
February 10, 1997
-2-
S.E.A. 96171-01
California State Department of Transportation. It is important for satisfactory pavement
performance that adequate surface drainage be provided to prevent ponding and/or infiltration of
water that can lead to saturation and weakening of the subgrade.
We trust the above information will assist you in your preparation of the plans and specifications for
the project. If there are any questions concerning these recommendations, please contact the
undersigned.
Respectfully submitted,
SHEP ARDSO EN G INEERIN G ASSOCIATES, IN e.
cc:
(2) Addressee
(1) Nolte and Associates
Attn: Mr. Jim Hettinger
¡
)
. 'am E. Ellis, G.E. 293
Senior Geotechnical EngineerNice President
WEE:sj
Shepardson Engineering Associates, Inc.
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
8
8
REPORT OF GEOTECHNICAL INVESTIGATION
TIŒ GYMNASIUM AND
FITNESS CENTER ADDmON
MAGDALENA ECKE YMCA
ENCINIT AS, CALIFORNIA
PREPARED FOR:
Magdalena Ecke Family YMCA
c/o Good and Roberts
1090 Joshua Way
Vista, CA 92083
PREPARED BY:
Shepardson Engineering Associates, Inc.
10035 Prospecti\venue
Santee, California 92071-4398
October 29, 1996
S.E.A. 96171-01
I ; 5 H E PAR 0'0 N
I .,- ~:::::,":::i:~~OClATES INC
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
8
t'"I"<'I"'-' ;"';""",
:, III.), {""",,'ct .-I;'c
'.n:tc,', L.-I ~:(i:-1.~;d"
i,,/()- ,I E: L.II""'" ¡,,'III
L.lri.,¡'¡¡¡j, L,\ ":,1118
ri~ .f~:L'J,'311
¡,1:'i'J31-~~~'1
F~,\I'I~i.f.f'L;,;:~
F,\.\ "¡,, ~;; .,J ;-i.-
October 29, 1996
S.E.A.96171-01
Magdalena Ecke Family YMCA
clo Good and Roberts
1090 Joshua Way
Vista, CA 92083
ATTENTION:
Mr. Jack Good
SUBJECT:
Report of Geotechnical Investigation
The Gymnasium and Fitness Center Addition
Magdalena Ecke YMCA
Encinitas, CA
Gentlemen:
We are please to present the attached Report of Geotechnical Investigation for the proposed
gymnasium, fitness center and maintenance building additions to the existing Magdalena Ecke Family
YMCA facilities in Encinitas, California. In general, we found excellent foundation conditions in
the areas of the proposed structures. It is our opinion that the geotechnical conditions at the site
are suitable for the proposed structures provided the recommendations contained in the body of this
report are incorporated into the design.
If there are any questions concerning this report, please do not hesitate to contact the undersigned.
The opportunity to be of service is sincerely appreciated.
Respectfully submitted,
SHEPARDSON ENGINEERING ASSOCIATES, INe.
Ke~
Vic~es~ ~ F!b ~ '
~{j/~~. G,E, 293
Senior Geotechnical EngineerNice President
-
cc:
(6) Addressee
Enclosures
Shepardson Engineering Associates, lnc.
I
I
I
I
I
I
I
I
I
II
I
I
I
I
I
I
I
I
I
8
8
TABLE OF CONTENTS
Page No.
1.0
INTRODUCTION.....................................................1
2.0
SCOPE OF WORK........................................... .........2
3.0
PREVIOUS INVESTIGATION ..........................................2
4.0
FINDINGS ..........................................................2
4.1
4.2
4.3
5.0
Site Description .................................................2
Site Geology and Subsurface Conditions ...............................3
SeismicitylFaulting ...............................................3
CONCLUSIONS ......................................................4
6.0
RECOMMENDATIONS ................................................4
6.1
6.2
6.3
6.4
6.5
7.0
Earthwork .....................................................4
Foundation.....................................................5
LateralEarthPressures............................................5
Slabs-on-Grade ..................................................6
SurfaceDrainage ................................................7
LABORATORYTESTS ................................................7
8.0
SUBSURFACE EXPLORATION .........................................7
9.0
ADOmONALSERVICES ..............................................8
APPENDICES
Plate No.
APPEND IX A
Site Plan - Gymnasium/Fitness Center Addition. . . . . . . . . . . . . . . . . . . . . ". . . . . . .. Al
Site Plan-Maintenance Building ........................................ A2
APPEND IX B - Exploration Logs
Explanation of Logs .................................................. B1
Logs of Test Borings .............................................. B2-B10
APPENDIX C
Laboratory Test Results .............................................C1-C6
APPENDIX D
Recommended Guide for Placement of Engineered Fill
I
I
I
I
I
I
I
I
I
II
I
I
I
I
I
I
I
I
I
8
8
REPORT OF GEOTECHNICAL INVESTIGATION
GYMNASIUM AND FITNESS CENTER ADDmON
MAGDALENA ECKE FAMILY YMCA
ENCINITAS, CALIFORNIA
October 29, 1996
S.E.A. 96171-01
1.0 INTRODUCTION
This report presents the results of a Geotechnical Investigation for the site of a proposed gymnasium
and fitness center contiguous to the existing offices and workout facilities at the Magdalena Ecke
Family YMCA in Encinitas. It also includes an investigation for a proposed 30 ft. x 30 ft.
maintenance building to be constructed immediately west of the existing tennis courts which will
separate the maintenance building from the gymnasium. The YMCA facility is located at 200 Saxony
Road in Encinitas.
Preliminary site plans for the addition, prepared by Architects/Larson/Carpenter, indicate that the
combined area of the proposed gymnasium and fitness center will be on the order of approximately
25,800 sq. ft. The attached Plate No.1 is a site plan, based on a recent topographic map, which
shows the approximate area of the proposed addition, as well as existing facilities. It appears that
very little grading will be required in order to construct the fitness center and gymnasium. Based
on the existing topography we would expect that a few feet of cut in the area of the fitness center
and up to four feet of fill along the southern end of the gymnasium will be required. It is our
understanding that the new construction will consist of concrete block perimeter walls and on-grade
concrete slabs. We are assuming that the gymnasium will have hardwood flooring over the concrete
slab. For the purpose of this report, we have assumed the various column loads for the proposed
structure will not exceed 75 kips per isolated column, nor 3 kips per lineal foot of continuous wall.
The preliminary plans indicate that the maintenance building will be constructed so that the first
story will be partially subterranean on the east, west, and north sides. Apparently, these three walls
of the structure will act as retaining walls in addition to their role as exterior bearing walls for the
structure. It appears that these walls will be required to retain a maximum of approximately 9 to
10 ft. of soil. An additional retaining wall is planned to retain the east side of the service yard/access
road fronting the maintenance buildings.
Shepardson Engineering AssOCUlres, Inc.
I
I
I
I
I
I
I
,
I
I
I
I
8
.
October 29, 1996
-2-
S.E.A. 96171-01
2.0 SCOPE AND PURPOSE
The purpose of this investigation was to provide an assessment of the geotechnical conditions as they
might affect the design and construction of the proposed structures. The scope of this investigation
included a number of tasks which are briefly summarized as follows:
1. Review of soil investigation report prepared by Leighton and Associates, titled
"Preliminary Geotechnical Investigation for the Proposed North County Family
YMCA Expansion", dated March 11, 1985.
2.
3.
Drilling of nine exploratory borings to investigate the subsurface conditions.
Laboratory testing of representative soil samples retrieved during the exploration
program.
Evaluation and analysis of field and laboratory data gathered.
Preparation of this report summarizing the findings, conclusions and
recommendations regarding the geotechnical parameters affecting the project design.
4.
5.
3.0 PREVIOUS INVESTIGATIONS
II
II
I
I
I
I
I
I
As part of our current investigation we reviewed the data contained in a report by Leighton and
Associates prepared for the existing YMCA facilities. The investigation contained several borings
and test trenches, two of which were near or within the area of the proposed building expansion.
The conditions encountered by Leighton and Associates generally conformed to the conditions we
encountered in our investigation.
4.0 FINDINGS
4.1 Site Description
The site of the proposed addition is relatively flat and has been previously graded. The area of the
proposed gymnasium and fitness center is essentially in an area that was previously cut in order to
achieve the existing grades. There is existing fill in the area of the proposed maintenance building,
however, the proposed floor elevation of the building will result in the removal of all of the existing
fill from beneath the new structure.
S~pardson Engineering AsSOCÜltes, Inc.
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
,I
I
,I
8
8
October 29, 1996
-3-
S.E.A. 96171-01
The area of the proposed gymnasium and fitness center structure is currently occupied by lawn areas,
driveways, parking areas and open ground. There are two portable office structures in the area of
the proposed gymnasium that will have to be moved.
4.2 Site Geology and Subsurface Conditions
Our investigation indicates that the site of the proposed additions is underlain primarily by dense,
sandy soils thought to be part of Pleistocene age Terrace Deposits possibly associated with ancient
coastal dunes. These deposits were found to be only slightly clayey. However, we encountered a
zone in Test Boring No.5 that was classified as clayey sand-type material at a depth of between two
and four feet below the existing ground surface. Also in Boring No.5 we encountered approximately
two feet of existing fill soils. These are the only fill soils of significant thickness encountered in the
area of the proposed gymnasium/fitness center.
In the area of the proposed maintenance building, we estimate that a maximum thickness of fill, on
the order of five feet deep may exist at the hinge point of the slope. According to the preliminary
plans for this building, the elevation of the first floor should be such that it will be below any existing
fill and, therefore, the footings will be in undisturbed terrace deposits.
4.3 SeismicitylFaulting
There are no known faults that pass through, or near, the project site. In our opinion, the nearest
active fault which could possibly affect the project site would be the Rose Canyon Fault, which is
thought to parallel the coastline approximately 3 miles offshore. This fault is considered active,
however, the recurrence interval for a major earthquake is thought to be on the order of, possibly,
300 years. We estimate that a maximum probable earthquake on the Rose Canyon Fault would be
on the order of 6.0 magnitude.
In our opinion, the most likely source for a major earthquake which could affect the project site,
would be the Coronado Banks Fault Zone, which lies approximately 18 miles to the west. This fault
zone is considered very active and capable of producing a maximum probable earthquake on the
order of 6.75 magnitude. If a maximum probable earthquake should occur on the Rose Canyon or
the Coronado Banks fault, maximum peak ground accelerations at the site would probably be on the
Shepardson Enginuring Associates, IlU:.
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
8
.
October 29, 1996
-4-
S.E.A. 96171..01
order of .3g and .1g for the Rose Canyon and Coronado Banks Faults respectively. These calculated
accelerations are based on Campbell's "Attenuation Relationships for Soil-like Materials" (1993).
5.0 CONCLUSIONS /
From a Geotechnical Engineering standpoint, it is our opinion that the site is suitable for the
proposed structures. Relatively shallow spread or continuous wall footings designed for moderate
loads are an appropriate foundation system for the site. Recommendations for foundation design,
earthwork and site preparation are contained in the following sections.
6.0 RECOMMENDATIONS
6.1 Earthwork
The minor amount of fill which is thought to be present within the areas of the proposed structures
is not considered to be significant enough to affect the structures provided the recommendations in
this report are followed. Any soft or unstable fill, or natural materials encountered during
construction should be removed and replaced with compacted fill.
Fill will be required to raise a portion of the site to the desired grade. Fill may consist of the onsite
materials if they are free of organics and any debris. The guideline specifications for fill placement
and compaction are contained in the attached "Recommended Guide for Placement of Engineered
Fill" included in the Appendix of this report. All fill should be placed at, or slightly greater than,
optimum moisture content, and then compacted to at least 90% of the maximum dry density, as
referenced to ASTM Test Method D1557. This compaction should also be applied to all utility
trench backfill and subgrade beneath pavement areas as well. In addition, the upper six inches of
subgrade beneath pavement areas, as well as any overlying aggregate base, should be compacted to
95% of its maximum dry density.
SMpardson Enginaring AssocŽiJtes, Inc.
I
I
I
I
I
I
I
I
I
I
I
I
:1
I
I
I
I
I
I
8
8
October 29, 1996
-5-
S.E.A. 96171-01
6.2 Foundations
Due to the tendency for fill soils and natural formational soils to settle differentially under applied
loads, we recommend that all foundations for the proposed structures be constructed in the natural
soils onsite. In order to achieve this, based on our interpretation of the proposed finished floor
elevations, deepened footings on the order of four feet will be required in the southern area of the
proposed gymnasium, where fill is to be placed. We recommend that footings extend a minimum
of one foot into undisturbed, competent formational soils, or a minimum depth of 18 inches below
the adjacent finish grade whichever is deeper. The recommended minimum footing width is 12
inches for continuous footings, and 18 inches minimum width for column footings. The
recommended maximum allowable soil bearing pressure is 3,000 lbs./sq. ft. for dead plus live load.
This pressure may be increased 33% for wind or seismic loading. We estimate that differential
settlement for similarly loaded foundations designed to the maximum allowable soil bearing pressure
will not exceed 0.5 inches. We further anticipate that the settlement will occur relatively rapidly
following imposition of a load upon these relatively granular subgrade materials.
Final footing reinforcement should be selected by a structural engineer. As a minimum, we
recommend one No.4 reinforcing bar in both the top and bottom of the footing.
The onsite native soils are predominantly silty sands with small amounts of clay fines. In our
opinion, these soils provide very low expansive characteristics and should not promote excessive
expansive pressures upon foundations or slabs. However, we do recommend that the subgrade soils
be maintained in a moist condition prior to placement of concrete for footings andlor slabs.
6.3 Lateral Earth Pressures
The active state lateral earth pressures may be assumed equivalent to a pressure of fluid weighing
36 lbs./cu. ft. and 56 Ibs./cu. ft. for unrestrained and restrained walls, respectively. Passive earth
pressures may be taken as equivalent to a fluid weighing 350 lbs./cu.ft. These above lateral earth
pressures do not include any reduction factors for factor of safety. In addition, these pressures are
applicable for conditions of level backfill, no surcharge loads within the backfill, and where the
backfill is drained. A friction coefficient of 0.35 may be used to determine the resistance of sliding
between the base of the foundations and firmly compacted soil.
Shepan:lson EngiMering Associaæs, Inc.
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
8
8
October 29, 1996
-6-
S.E.A. 96171-01
6.4 Slabs-on-Grade
Concrete slab-on-grade floors may be supported directly upon the native soils and/or compacted fills.
The final slab reinforcement should be incorporated as determined by the structural engineer. As
a minimum, we recommend No.3 reinforcing bars spaced at 24 inches maximum in each direction.
Supports for the reinforcement should be provided as needed to maintain the position of the
reinforcement at mid-slab during concrete placement.
Due to the sandy nature of onsite soils, we expect that subsurface transmission of infiltrating water,
from irrigation and rainfall will be extensive. It should be anticipated that slabs near irrigated areas
could eventually be subjected to high soil moistures within the native or fill soils. Since we expect
hardwood flooring will be placed on the concrete slab in the gymnasium, we recommend that careful
planning be incorporated in the design and construction to prevent soil moisture vapors from
penetrating the slab. As a minimum, an impermeable membrane placed beneath the slab is
recommended where moisture sensitive floor coverings are to be used or where potential floor
dampness from moisture vapor is undesirable. The membrane should be 6 mils or thicker and
should be covered, and underlain, with 2 inches or more of coarse sand to protect the membrane.
The sand overlying the membrane should be moist to promote more uniform curing of the concrete
slab.
Our experience also suggests that considerable moisture may enter the concrete slab by "wicking" of
the moisture from adjacent landscaped areas, through the footingtstemwall. We recommend
consideration be given to isolating the slabs from the footinglstemwall with the use of a cold joint
and a moisture proof barrier.
Plastic shrinkage cracking of concrete is common in large, flat slab areas which are not designed or
constructed to account for this characteristic. We recommend the designer incorporate appropriate
details and specifications for material, workmanship and quality control to reduce the adverse effects
of concrete shrinkage cracks.
SMpardson Engi1ll!ering AsSOCÚltes, /111:.
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
8
8
October 29, 1996
-7-
S.E.A.96171-01
6.5 Surface Drainage
It is important to provide positive surface drainage away from buildings and pavements. Ponding
of water near pavements and/or footing areas could lead to disruptive, differential settlement and
elevated interior moisture. Irrigation of landscaping near these structures should be carefully
monitored and controlled.
7.0 LABORATORY TESTS
Laboratory tests were performed in accordance with generally accepted American Society for Testing
Materials (ASTM) test methods or suggested procedures. Representative samples were tested for
natural density and in-place moisture content, maximum dry density determinations, expansion index,
consolidation characteristics and direct shear properties. The results of these tests are presented in
Appendix C or on the Boring Logs, Appendix B.
8.0 SUBSURFACE EXPLORATION
The subsurface exploration performed as part of this investigation included the drilling of nine
exploratory borings via continuous flight, hollow stem auger advanced by a drill rig. The conditions
encountered in the exploratory borings were visually examined and logged by a geologist from our
office. The soils were described in accordance with the Unified Soil Oassification System as
illustrated on the Explanation of Logs attached in Appendix B. In addition, a visual textural
description of the wet color, apparent moisture content, and the density or consistency of the soils
are illustrated on the boring logs. Soil densities for granular soils are given as either loose, medium
dense, or very dense. The boring logs are presented as Plate Nos. B2-BlO. Bulk samples and
relatively undisturbed drive samples were obtained from the borings and transported to our office
for testing and/or further classification.
SMpardson Enginuring Associates, Inc.
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
8
8
October 29, 1996
-8-
S.E.A. 96171-01
9.0
ADDmONAL SERVICES
This report completes our scope of services for this project. During the construction phase, the
Geotechnical Engineer should be contacted to observe and test compacted fill placement, inspect
placement of slope drains and to verify that the exposed soil conditions are as anticipated. These
services are intended to permit the Geotechnical Engineer to express the opinion that the
geotechnically related work is in conformance with the project specifications and plans, and to
document changes encountered or made during construction.
Shepardson Enginuring AsSOCÚltu, Inc.
iL
.1
. ¡
J
---
.,..:.....¡-
I
!
~
i
i
!
¡
i
I
i
I
I
i
tl
". .
j
~
i.l
¡j
!
}
¡j
~
~
..
,
t
...
~
L
Ii
~
.i
jllO
J
--
+'v
----------------------- r- ---r---:t...-- ---------
:)/), l"'lul........... l.h.._ù'O I\~ ¡, I
I
I
~----------------_____---I
------
--------
2
Fitness ICenter
~
~r~
~~
-,
:;:-,~ -ouu-
----""'_-_n-
-
_.
I
.. I
l I
I ¡
! !
I
I
I
I
I
I
I
I
--.- -1----/ "--"'"
---~-
: I
. I
:"--...1
Existing
-$- = Test Boring
.-r~--r'--~-'
........
-... ~.~--..---
.~;,:::
:1 ---~-_..--.-.-.--
--' -- '--.,.
ó------..-... ¡ ,.........
I
I
I
I
I
I
I
J
J
1
j
.aà
..
~
SEA R.171 Rev: 4/88
Scale: 1" = 16'
-I~.j-
.
%
-.-mo --'" .........
I --- ,
,... - .,....,.,.,. ........
-.-
Job NLmber: 98171-01
Date:
October 1996
'.'-~' --,
~ SHEPARDSON
;~ ENGINfERING AssocIATES INC
, '.
. ":'..-.
SITE PLAN
Gy.....8I.. 8IId FIlM.. Cent.r Addition
Magd.18na Eok. YMCA Enolnl.... CA
GtØlrc/lllü:.1 Gnuu/t."",
E"lirwm-Gmøtw$
N
~
Plat.
A1
I
1
1
., ',,",'
1:;1'
", ,,<'
.."":""
.,..;;,:
,~;:::;
I,,'~
, ,',."
". "
,",;.;t:l.
"""'/"" ,
rl!:.:t;{;-- '
" '
. ,
1',.-
"',
, ",~
,~.
";,,, , :", '.
I .,'
I'
I
I
I
I
I
I
I
I
I
I
I
, --,'
",
',J
-,. ',-'
"
, '
- ' .
,,'
""",,~,.
,'"..-,
..:-
,,'.- ....'.' '".f-
" " '
.,',
"
, '
APPENDIX -A-
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
8
0
I-
U1
. S
EXISTA" P.V.C.
SEWER
163.62
TENNIS
COURT
x
1 63.23
= Test Boring
~
Scale: 1 = 20'
-~ SHEPARDSON
~ ENGINEERING ASSOCI,A,TES INC
Gtoltch"ic/JI CO"swlt/J"ls:
E"gi"ttTS-GtOlogisls
Date Cctober 1996
Project No. 98171..01
SITE PLAN
M.lnt.n."oe Building
A2
Plate
SEA A.17Q Aev: 4/88
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
. . . .
"
APPENDIX S'
SHEPARDSON ENGINEERING
SOIL CLASSIFICATION PROCEDURE
The Tables Included Below are Used By Shepardson Engineering
Associates. Inc. to Determine the Group Symbol for a Soil in
Accordance with ASTM Test Standards. The Name Used in Conjunction
with the Group Symbol is Determined By Using ASTM Test Method
02487-85
COARSE MATERIAL (ASTM D2487)
Ualor Dlvlalon.
Group
Symbol.
Typical N.m..
Î'i
.
CD
>
..
¡¡;
0
0
CII
"0
~2:
Cl)c
'00
"'0
c..
-c
"-
~..
CJ-
,..
..a:
~~ ~ =..
00 °....>
u'" II)~::.!
c 'Oc..D..CI)
:IS c .. 0
== :::u~-;¡
~ ~ÕÕ2:
0 0:lS
~ E ù:
SP
Poorly Graded Sand. and Gravelly
Sand, lillie or no Fines
ãi
>
'"
ð
GW
Well-Graded Gravel and
Gravel-Sand Mixtures, Ut~1e or
no Rnes
..
"c
;;;0
0",
~-š~
0",..
j!!o;¡¡;
"'oa:.
èiEco
~.2z
°õ
~..
où:
II)
c
'"
.!!
u
GP
Poorly Graded Gravel and Gravel-
Sand Mixtures, Uttle or no Fines
GM
Silty Gravel. Gravel-Sand-Clay
Mixtures
~
ãi"" ..
>- ..
!J"i~
GC
Clayey Gravels. Gravel-Sand-Clay
Mixtures
SW
Well-Graded Sand and Gravelly
Sands, Lillie or no Fines
'0
C
'"
CI)
c
'"
.!!
u
...
FI NER MATERI ALS
(More Than 50 Percent Passing a No.4 Sieve)
0
5
f 12
t
w
>
I ~
I CI)
0
... 0
C'õ
..
CJ
L f ~
CI)
CI)
< 50
"-
I-
2:
w
L I u
a:
w
D.. 70
L I 85
I
100
~
~
-..
SW or SP
(5.. Tabl. No,11
SW-SM or SP-SM SW-SM/SC or SW-SC or SP-SC
SP-SM/SC
I
(SM) (SM-SC) eSC)
(MU (ML-CU (CL or CHI
(MU (ML-CU eCL or CHI
(MU (ML-CU eCL or CHI
-""II( Fines Below 'A" Line Rnes Above 'A' Line
Fines - PI < 4 Fines 4 < PI < 7 F;n..~ PI ~ '7
~
Notes: 1. 00<"" not Dlstlnqulsh between Sill-Elastic Silt -Organic Silt
2, Classification 01 CH (Fat Clayl is uMd when LL ~ sa. Classily
as lean Clay (CLI when LL<Sa
3. Assumes less than 15% Gravel
SEA: R'300 2/88
..
--- -- -- -' - - .-
SAND GRAVEL
SILTS AND CLAYS I Medium I Coarse Fine I Coarse COBBLES BOULDERS
Fine
GRAIN SIZES
Classlllcatlon Crlt.rla
u
CI)
::i
CI)
Ù
CJ
~"
CJ
~ I c." 0'0/0", Go..,., '.aft .
~-õ '0,0,2
ern c.' 1I1'_ft 1 a"" 3
:. [ °'0 . °.0
CCl)
.. .g ~ I Not Meeting both Criteria for GW
c "0
_u
~~~
"E .. ..
oo!!..
a3U~
.. D..
~ CI)
iLi
gõ ::
.. CJ
co"
.2~ ~
0; c 0
u..
-u
- ~
-¡¡; .. .. ..
"D.. > >
.. .. 0>..
Ü õ OItéñ ~ éñ :..
~ ",g -g D.. ¡;
.. c,,! :;i"! ~¡¡;
a3~o.co-o
-2: - 2: 00
.." ""-CII
..: o;~o
2/e.. ~ D.. '" 2:
Atterberg Limits Plot Below
. A" Line or Plasticity Index
lass than 4
Atterberg Limits Plot Above
. A' Une and Plasticity Index
Greater than 7
c. - °.0 I °'0 c..a... "'aft .
c. .
'~O,2
-IIo'_ft Ie"" 3
°ta . O..
No: Meeting Criteria for SW
U.S. STANDARD SERIES SIEVE
zoo
40
10
MOISTURE CONTENT
Description Criteria
"Dry' Absence of Moisture; Dusty;
Dry to the Touch
'Damp. Some Moisture But less Than
Optimum for the Soil
'Moist' Near Optimum for the Soil
'Wet" Above Optimum lor the Soil
"Saturated" Containing Visible Free
Moisture
These fina I logs represènt Shepardson Engineering Associate¡¡',
interpretation of subsurface conditions bused on . field logs In
combination with the results of labaratory examination and tests of
representative field samples. Therefore, these logs contain both
factual and interpretative information, The logs represent subsurface
'conditlons at the dates and locatians indicated and are not necessarily
representative of subsurface conditions at other locatior.s and times.
The horizon tal lines represent the approxi mate generic and/or lithologic
boundary between types of soil and/or rock material and the transition
may be gradual.
Please note that the logs summarize only a portian of the
geotechnical report. They should not be reproduced for distribution
separated from the bady of the report and the data contained on the
lag should be used only in conjunction with the report .
"Refusal': indicates inability to extend excavation practically/
econamically with exploration equipment used.
KEY TO LOG
SalT'()le
Interval
00
c- ~. * ~
,,- - -
""= .!. og ~= :;¡ :;~ ... ~
~: ~ ~ u... ~ ~ ~ ë =: ~ i
a~ ';:1- ~i... - ~~ 01- ::) ~
ã- 0 0
,
7
~ f 5 103 11
"-'
~ 0 6 :g~ '.
t
- . ~
-
I-
Atterberg Umits Plotting
in Hatched Area are
Borderline Classifications
Requiring use at Dual
S~bols
I
CLEAR SQUARE SIEVE OPENINGS
* Unified Soil Classification System
"
3/4'
3"
IZ'
NOTES:
COMPACTNESS
CON SISTENCY
SANDS GRAVELS
AND
NON-PLASTIC SlL15
CLAYS AND
PLASTIC SILTS
Very Loose
Loose
Medium Dense
Dense
Very Soft
Soft
Firm
Still
Very SUfI
Hard
Very Dense
_.~ SHE PAR D SON
~ ENGINEERING ASSOCIATES INC
GtOltChniclIl CoFlSullllnls:
Enginllrs,Glologisls
Job Number:
95171-01
r-- Level of Free Water & Date Measured
rJ Seepagp. at Time 01 Boring
TYP".. OF SAMPL E OA SAMPLER
SS . Siandard Penetralion Test Sample (ASTM)
0 . Evans Sampler (3.ZS' 0.0., 2.6' I.DJ
H . Californ'a Sampler ¡3"0.0.. Z.37S' I,D.)
SI . S!>elby Tube 13"0.0./
5Z. Shelby TuDe (Z.S'O.D.I
PB . Pitcher Barrel (3'0.0.1
. - UnaDle to Aetrieve Sample
B . Bulk Sample
C . Chunk Sample
NUMBEA OF BLOWS FOR LOWER IZ' OF DAIVE SAMPLE
When SS Sampler Used, Blows are Taken Using
14alb Hammer-30' Drop
Energy Criteria on Log for Other Samplers
P - Push Under Hammer Weight
MOISTUAE CONTENT (Percent Dry Weiqhtl
DAY DENSITY (Pounds Per Cubic Footl
(AI - Relative Compaction
OTHER TESTS PERFORMED
SG - Specific Gravity
OS - Direct Shear
UC - Unconfined Comoression
TC - Triaxial COm¡¡ression
R S - Residual Shear
CN . Consolidalior.
EX - Expansion
EI - Expansion Index
1.40 . Maximum Density-Optimum
SE . Sand Equivalent
GS - Grain Size Determination
PM - Permeability.
AL - Atterburg Li mits
R - R -Value
CBA - Ca610rnia Bearing Ratio
CH - Chemical Tests
MoiSlure
Date: 10/29/96
Plate
YMCA GYMNASIUM AND FITNESS CENTER
ENCINITAS CA
EXPLANATION OF LOGS
81
I
I
I
I
Drilling Date(s):
Logged By:
...c-
ë.~
QQ
CI:t:.
Q
-Q
0.0.
E>
<01-
en
I
I
- 2 )c B
H
I- 4
I
I
- - --
f-6ZH
f- 8
I
I
I
10
ZH
12
14
I
I
16
18
I
I
20 Ix: H
-22
-24
I
I
8
8
LOG OF TEST BORING NO. B-1
09/17/96
KLS
Drilling Equipment:
Method/Hole Size:
Q -""
....- ~ ... ë ~'#. ~
~C:Õ~ïñC'::JQ- 5- I-
.2 g 0 è5 c: g, ; ë'#. .... c:
aJu5 ~-~8- ~.g ~
55
8.2
46.2 DS
, '2
------
------
39
76
37/6'
Drive Energy Data: Hammer Type CAT HEAD
Weight 140 Ibs.
Drop 30 ins.
en
u
en
~
U
:201
0.0
~...J
(:1
Surface Elevation:
Bottom Elevation:
SM
I
- - ŠM-ŠC vV'. /.
[(:I
l/ft /
.V .
/
l/Y
v'.¡//.
i///
VY'/
v'.¡//.
i///
VY'/
v'.//.
. //
VY'/
.;/.
//
y¡
.f.
;//
y¡
.f/
;//
Y'¡-
.i')/.
(/
y¡-
. ://.
;//
ÿv
./11-
. /V
Yll
./11-
/v
ill
-164'
-142'
FLIGHT AUGER/6"
MATERIAL DESCRIPTION
TFRRACF nFPOSITS (Ot). Sandstone, silty sand, dense,
moist, yellow-red brown.
"
- - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - --
LQt¡;. Sandstone, slightly clayey sand, medium dense to
dense, moist to wet, orange brown.
:Less clay, becomes silty sand.
:Becomes slightly clayey.
:4" thick gravel zone.
END OF BORING AT -20.5 FT.
Hole left open for 6 hrs., no free water.
Please refer to symbols and note limitations shown on "Explanation of Lo s"
I
::;::!;¡:S H E PAR D SON
¿:::: - ENGINEERING ASSOCIA rES INC.
Geotechnical Consultants:
Engineers-Geologists
II
Project No.: 96171-01
Plate
Log of Test Boring No. B-1
Encinitas YMCA
B2
<0
0)
CI)
(/)
M
-I
CI)
1 of 1
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
II
I
I
8
8
LOG OF TEST BORING NO. B-2
Drilling Date(s):
Logged By:
09/17/96
KLS
Drilling Equipment:
Method/Hole Size:
Surface Elevation:
Bottom Elevation:
-164'
-154'
FLIGHT AUGER/6 "
aJ > aJ- ~~ <c¡; .~
..e- ~ëZ "'c U)
-aJ ð'~~ ~aJ- aJ ..em
ë.~ 0.0. o~o ;ë~ ~- I- U 0.0 MATERIAL DESCRIPTION
aJaJ E> -00 -c ~ U) ~-i
o:t:. 101- ccU:S aJ- 00- 100 :::J
U) 0 ~U U).;:; 10 c.=J
-i
SM TFRRAC'.F nFPO~IT~ (Ot). Sandstone, silty sand, medium
dense, wet, orange brown mottled gray.
2 2 H 21 121 11.8 85.8
- 4
r- 6
r- 8
X H 58
END OF BORING AT .9 FT.
10
12
14
16
18
1-20
r-22
r-24
Drive Energy Data: Hammer Type CAT HEAD
Weight 140 Ibs.
Drop 30 ins.
Project No.: 96171-01
.:;¡¡¡;¡:S H E PAR D SON
.::HH>"'- ENGINEERING ASSOCIA TES INc.
.",
Plate
Log of Test Boring No. B-2
Encinitas YMCA
83
(C
en
aJ
en
M
-'
aJ
Geotechnical Consultants:
Enginee rs-Geol ogists
1 of 1
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
1,1
I
I
8
8
LOG OF TEST BORING NO. B-3
Drilling Date(s):
Logged By:
Drilling Equipment:
Method/Hole Size:
09/17/96
KLS
Surface Elevation:
Bottom Elevation:
-164'
-154'
FLIGHT AUGER/6"
<I) -~ >- <1)- ~~ 'õ; .!:!
.c~ ""C: en
-<I) ~~¥~]: ;;¡<I)~ cu .cO!
-- c.c. I- U
c.<I) ;ë~ ::1- c.o MATERIAL DESCRIPTION
<l)CU E>- -C: .a en ~...J
C)~ «II- cou-- ~- oo~ «10 ~
en ~u en.;:; ca <.::)
...J
U
SM-SC, -:¡'-V Fill (7)' slightly clayey silty sand, medium dense, moist,
- - - - - - - - - - - - - - - - - -ŠM' brown. '
B TFI:fRÃëF-nFPosiT~ (Ot):- Sãndstõnë, siÌi:ÿ sãñd~ dëñsë, - - - ~
2 ~ H 36 121 11.7 86.0 moist, yellow brown and gray brown, mottled.
4
6
8
X' H 35
END OF BORING AT .9 FT.
10
12
14
16
18
20
22
f--24
Drive Energy Data: Hammer Type CAT HEAD
Weight 140 Ibs.
Drop 30 ins.
Project No.: 96171-01
.::;¡¡~¡~: SHE PAR D SON
:¡H¡¡¡¡¡¡:o - ENGINEERING ASSOCIA rES INC.
.",
Plate
Log of Test Boring No. B-3
Encinitas YMCA
84
<C
O'J
co
(/)
("')
~
co
Ceotec:hnic:al Consultants:
Engineer s- Ceol ogists
1 of 1
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
II
8
8
LOG OF TEST BORING NO. B-4
Drilling Date(s):
Logged By:
09/17/96
KLS
Drilling Equipment:
Method/Hole Size:
Surface Elevation:
Bottom Elevation:
-163 '
-147'
FLIGHT AUGER/6"
>- <1)- ~i - ,~
.c- c ~ë;:; ""c CI en
-c ~'~]. ::1<1)- c .cO)
-- c.c. ~ U
c.c 0::10 ~-~ ::I- c.o MATERIAL DESCRIPTION
CC E>- -00 - co -c .Q en ~...J
a::=. <V~ ccu5 c- 00- <Vo :::::>
en 0 ~u en..;:; <V <.:)
...J
SM TFRRAC'.F OFPOSITS lOt), Sandstone, silty sand, dense.
moist, red brown,
2
I-- 4
I-- 6 :g H 40 121 9,7 70.2 CN "
8
:Becomes orange brown.
10
~ H 82
12
14
t>< H 42/6'
16 END OF BORING AT -15,5 FT.
1--18
1--20
~22
24
Drive Energy Data: Hammer Type CAT HEAD
Weight 140 Ibs,
Drop 30 ins.
Please refer to symbols and note limitations shown on "Explanation of Lo s"
.,:::::~:;: SHE PAR D SON
,:,H¡¡n,::: - ENGINEERING ASSOCIA rES /NC.
."
Plate
Project No.: 96171-01
Log of Test Boring No. B-4
Encinitas YMCA
B5
CD
(j)
co
en
M
...J
co
Geotechnical Consultants:
En g ¡nee r s - Ceolo gis is
1 of 1
I
8
I
I
I
8
LOG OF TEST BORING NO. B-5
Drilling Date(s):
Logged By:
09/17/96
KLS
Drilling Equipment:
Method/Hole Size:
Q ~ëz >- Q- .¡,~ ûí .~
..c- ~c: (IJ
-Q ~O~g ~Q- Q ..cO)
ë.Q; 0..0.. ~Q f- U
o:::¡o ûí-~ :::¡- 0..0 MATERIAL DESCRIPTION
QQ E> -00 - C:Q -C: .Q (IJ ~~
a~ tIIf- CDU:::: Q- 00- tIIo :::::>
(IJ a ~u (lJo;:; tII ~
~
SM ÐLL silty sand. medium dense, moist, dark yellow-gray
brown.
2 => .J.i-- 44. -
- - - - - - - - - - - - -šë ~ - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - --
MD TFRRAC:F nFPOSITS (Ot). Sandstone, clayey sand, medium
~ dense to dense, moist to wet, red brown.
f-4 - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - --
SM '~ ~ Sandstone, silty sand, dense, moist. red brown-orange
B brown
f- 6
f- 8
R H 54
END OF BORING AT .9 FT.
10
12
14
16
18
20
22
24
°1
I
I
I
I
I
I
I
I
I
I
I
I
I
I
Drive Energy Data: Hammer Type CAT HEAD
Weight 140 Ibs.
Drop 30 ins.
Surface Elevation:
Bottom Elevation:
-164'
-154'
FLIGHT AUGER/6O1
::;;i!¡¡: SHE PAR D SON
'" ENGINEERING ASSOCIA rES INC.
Geotechnical Consultants:
En g inee r s - Geolo g is ts
Project No.: 96171-01
Log of Test Boring No. B-5
Encinitas YMCA
Plate
B6
(0
a>
CD
(/
M
-J
CD
1 of 1
I
I
I
I
I
I
I
I
I
I
,
I
I
I
I
II
¡I
I
I
8
8
LOG OF TEST BORING NO. B-6
Drilling Date(s):
Logged By:
09/17/96
KLS
Drilling Equipment:
Method/Hole Size:
Surface Elevation:
Bottom Elevation:
-164'
-149'
FLIGHT AUGER/6"
>- IU- ~~ - .~
.I:~ IU ~ëz "'C en (J'
-IU ~.~C" ::IIU~ IU .I:C)
ë.Q; 0..0.. 0::10 ;ë~ ::I- ~ u 0..0 MATERIAL DESCRIPTION
lUlU E>- -00 o~g -c ~ (J' ~....
c~ IC~ aJu:S 00- reo ~
(J' C ~u (J'.;:; IC l:)
....
SM TFRRAC'.F nFPOSITS' Sandstone, silty sand, medium dense to
dense, moist, red brown.
2
~ H 25 116 6.6 40.8 CN
4
- - - - - - - - - - - - - - - - 1--- -SM ----------------------------------
!Q.1l.:. sandstone, silty sand, dense, moist, dark gray brown.
6
- - - - - - - - - - - - - - - - 1--- SM-SC :71..:.- ----------------------------------
I- 8 ';/r; !Q.1l.:. Sandstone, slightly clayey-silty sand, dense, moist to
X H 47 yl.J wet, orange brown mottled gray.
~ .'/1.,.<'
/v
1-10 'Yv
.j/I.,<
;/v
;"V
I/./'I.,<
1-12 I//v
v;"v
I/./'
X H ap/10.5 I/;/v
1-14 "-' v"'<v
END OF BORING AT -14 FT.
1-16
18
20
22
24
Drive Energy Data: Hammer Type CAT HEAD
Weight 140 Ibs.
Drop 30 ins.
Please refer to symbols and note limitations shown on "Explanation of Lo s'
..::¡¡:!¡¡:S H E PAR D SON
.::i!W¡¡¡::- ENGINEERING ASSOCIA rES INC.
.",
Geotechnical Consultants:
Engineers-Geologists
Project No.: 96171-01
Plate
Log of Test Boring No. B-6
Encinitas YMCA
B7
CD
en
CD
(J)
M
..J
CD
1 of 1
I
8
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
8
LOG OF TEST BORING NO. B-7
Drilling Date(s):
Logged By:
09/17/96
KLS
Drilling Equipment:
Method/Hole Size:
Surface Elevation:
Bottom Elevation:
- 160'
-139'
FLIGHT AUGER/6"
QJ >- QJ- ~~ tí .~
..e~ ~¡:;:; -c en
-QJ >-.~C' ::JQJ- QJ ..eC)
-" 0.0. I- U
c.QJ 0::J° ;¡:<¡e ::J- 0.0 MATERIAL DESCRIPTION
QJQJ E>- -00 pcg, -I: .Q en ~~
Q::::' All- ccu:$ QJ- 00- Alo :;)
en Q ~u en.;:: AI <.:)
~
B
2
4 H
6
113
7.9
45.6 EI
30
112
10.3
57.8
8
H 63
10
------ ------
12
14
16
18
20 H 71
22
24
Drive Energy Data: Hammer Type CAT HEAD
Weight 140 Ibs.
Drop 30 ins.
I
, I
I
SC
TE=RRACF OFPOSITS (at). sandstone, clayey sand, medium
dense, wet to moist, red-orange brown.
:Becomes gray brown.
- - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - --
!Q1l.:. Sandstone, clayey silty sand, dense, wet, orange brown
mottled gray.
:Becomes silty sand.
END OF BOR91NG AT -20 FT.
.::;¡¡~¡¡: SHE PAR D SON
~ ENGINEERING ASSOCIA rES INC.
Geotechnical Consultants:
Engineers-Geologists
Project No.: 96171-01
Log of Test Boring No. B- 7
Encinitas YMCA
Plate
B8
<0
a>
CD
en
M
-J
CD
1 of 1
I
I
I
I
I
8
8
LOG OF TEST BORING NO. B-8
QJ ~¡:;:; >- QJ- "'~ 'ü; .!:a
.c- "'c en
-QJ ~.~ç :J QJ- QJ .cO)
ã.4í 0.0. ...a f- U
O:J° ;¡:¡¡!! :J- 0.0 MATERIAL DESCRIPTION
QJQJ E>- -00 è5~Ë: -c ~ en ~-I
a:= C'CIf- aJu:S 00- C'CIo ::J
en a ~u en..;:: C'CI <.::J
-I
- - - - - ~Sl'tiT~ ~ . ASPHAI T r.ONr.RFTF ANn RASF.
- - - - - - - - - - - - -
t- SM TFR-RÃë.F-n-FPo~c;iT~ (Ot):- -S~nd;t~n~:~I~y~ÿ s-a~d~ ~e-di~~ - -
B dense to dense, wet, red brown.
2 Z H 30 123 10.2 79.0
~
-
4
:Becomes silty sand, dense, moist.
I- 6 :2 H 67 115 9.7 58.6 DS j.
I
- 8
10
12 :Becomes orange brown, moist to wet.
'..
14
16 H
END OF BORING AT -16 FT.
H8
1-20
22
24
Drilling Date(s):
logged By:
09/17/96
KlS
I
I
I
I
I
I
I
I
I
I
I
Drive Energy Data: Hammer Type CAT HEAD
Weight 140 Ibs.
Drop 30 ins.
I
I
I
Drilling Equipment:
MethodlHole Size:
Surface Elevation:
Bottom Elevation:
-162'
-145'
FLIGHT AUGER/6°O
::,¡¡m: SHE PAR 0 SON
:¡!!i¡¡¡::':- ENGINEERING ASSOCIATES INC.
.",
Geotechnical Consultants:
Engineers-Geologists
Project No.: 96171-01
Log of Test Boring No. B-8
Encinitas YMCA
Plate
89
<D
en
CD
(f)
C")
...J
CD
1 of 1
I
I
I
I
I
I
I
I
I
I
I
I
I
I
II
I
I
I
I
I
8
8
lOG OF TEST BORING NO. 8-9
Drilling Date(s):
Logged By:
Drillin~ Equipment:
Method/Hole Size:
10/02/96
KLS
CME 55
HOLLOW STEM/S Of
Surface Elevation:
Bottom Elevation:
Q ~ê:z >- Q- ,!:
..c- -Q - -c III (/)
-" 0.0. 5'~], :;'Q- .c- U ..cO)
o.Q E>- 0:;,0 ;ê:~ ralll 0.0 MATERIAL DESCRIPTION
QQ -00 ...J~ (/) ~...J
0::::" tal- aJu:$ Q- 00- ::J
(/) 0 ~u ~
SM ElLL:. silty sand, medium dense, damp, light brown-red brown.
8-- - - - - - - - - - - - - ŠM - ------------------------------------ -
- 2 TFRRAC'.F nFPOSITS. Sandstone, fine to medium grained silty
)< H 85 130 6.4 sand. dense to very dense, moist to wet, red brown to brown,
- 4
"
6
.'
8 :8: H 32 113 6,2
10
,..12
~ H 87
-14
-16
'-18
.'
1-20
End of boring at -20 ft.
1-22
1-24
Drive Energy Data: Hammer Type Automatic
Weight 140 Ibs.
Drop 30 in.
Project No.: 96171-01
::;¡:m: SHE PAR D SON
,::U¡¡¡¡¡::- ENGINEERING ASSOCIA rES INC.
.",
Plate
Log of Test Boring No. B-9
Encinitas YMCA
810
<0
m
cry
....J
CI)
Geotechnical Consultants:
Engineers-Geologists
1 of 1
I
I
I
I
I
I
I
I
I
I
I -
I
I
I .
I
I
I
I
I
8
8
.. .
"
. .
, APPENDIX C-
I
I
I
I
I
I
I
I
I
I
I
I
I
II
I
I
I
I
I
Sample
Location
8- 7 @ 1,0
EXPANSION INDEX TEST RESULTS
Initial
Moisture
(%)
7.9
Compacted
Dry Density
(pcf)
113
Final
Moisture
(%)
16.4
Classification of Expansive Soil (ASTM D 4829-88, EI @ 50% sat. estimated)
Expansion Index
0 - 20
21 - 50
51 - 90
91 -130
130+
Date:
,:¡:¡¡¡¡'S H E PAR D SON
,¡¡¡ny:::':- ENGINEERING ASSOCIA rES INC.
."",
Geotechnical Consultants:
Enginee rs-Geol ogists
Potential Expansion
very low
low
medium
high
very high
Expansion
Index
10
October, 1996
I Project No.:
Expansion Index Test
Encinitas YMCA
Expansive
Classification
very low
96171-01
Plate
C1
co
m
t::
UJ
I
I
-1
I
0
I
I
-
I c 2
4J
~
4J
Co
z
I Q 3
f-
<:
0
..J
0
I (J)
z 4
0
u
I 5
I 6
I 7
I
I
I
I
I
I
I
I
8
-2
8
100
10000
1000
NORMAL LOAD (pst)
SAMPLE DATA
Sample Location and Depth (teet): B-4 @ 5.5
Soil Type and Visual Description: clayey sand. yellowish brown
Sampling Method/Sample Type: H / insitu
TEST RESULTS
USCS Moisture Content (%) Dry Density (pet)
Group Symbol Initial Final Initial Final
9.7 12.0 121 124
Water Added @ (pst): 5749 Expansion/Hydrocompression (%): -0.78
Date:
Project No.:
96171-01
October, 1996
oo¡¡¡¡:j:oS H E PAR D SON
¿:::oo- ENGINEERING ASSOCIA TES INC.
Geotechnical Consultants:
Enginee rs-Geol ogists
Plate
Consolidation Test
Encinitas YMCA
C2
co
en
~
z
u
I -2
I -1
I
0
I
I
I
I
I
I
I 6
I 7
I
I
I
I
I.
I
I
I
ë
Q)
u
...
Q)
Q,
z
0
I-
~
0
....J
0
(/)
z
0
u
2
3
4
5.
8
100
1000
NORMAL LOAD (pst)
SAMPLE DATA
Sample Location and Depth (teet): B-6 @ 2.5
Soil Type and Visual Description: silty sand, yellowish brown
Sampling Method/Sample Type: H / ¡nsitu
TEST RESULTS
USCS Moisture Content (%) Dry Density (pet)
Group Symbol Initial Final Initial Final
6.6 12.8 116 120
Water Added @ (pst): 5726 Expansion/Hydrocompression (%): -1.50
Date:
October, 1996
Project No.:
96171-01
.:::,;¡;.S H E PAR D SON
.:nnm::::':- ENGINEERING ASSOCIA TES INC.
.,
Geotechnical Consultants:
Engineers - G eol 0 gists
Consolidation Test
Encinitas YMCA
Plate
C3
to
01
~
z
u
I
I
3000
I
I
I
I
I
I
I
I
I
I
I
I
II
I
I
I
I
2500
íî" 2000
(/')
a..
(/')
(/')
UJ
~ 1 500
(/')
c::
«
UJ
::I:
(/') 1000
500
0
0
500
1000
1500
2000
2500
NORMAL STRESS (PSF)
Sample Location and Depth (feet):
Soil Type and Visual Description:
Sample Type/Sampling Method*:
USCS Group Symbol and Name:
B-1 @ 2.0
silty sand yellow brown
insitu / H
Test Data
MOISTURE CONTENT (%)* *
Initial Test: 8.2
Final Test: 15.0
DRY DENSITY (pcf)**
Initial Test:
113
TEST CONDITIONS:
NORMAL LOADS (pst):
STRAIN RATE (in/min):
(C,D,S)
1000,2000,3000
0.0020
Results
INTERNAL FRICTION ANGLE (degrees)
Peak: 36
Ultimate: 35
APPARENT COHESION (psf)
Peak: 151
Ultimate: 0
* See Explanation of Logs for sampler symbol definitions. ** Average of three test points.
Date:
October. 1996
Project No.:
.:;;";,,S H E PAR D SON
.:::H!!'::::':- ENGINEERING ASSOCIA rES INc.
."
Geotechnical Consultants:
Engineers-Geologists
Direct Shear Test
Encinitas YMCA
3000
3500
96171 -01
Plate
C4
(()
en
(f)
0
I
I
I
I
I
I
I
3000
500
2500
u:- 2000
en
a..
en
en
UJ
~ 1 500
en
a:
~
UJ
:J:
en 1000
I
I
I
I
I
I
I
!I
I
I
I
I
1500
2000
2500
3000
3500
NORMAL STRESS (PSF)
Sample Location and Depth (feet):
Soil Type and Visual Description:
Sample Type/Sampling Method*:
USCS Group Symbol and Name:
B-8 @ 5.5
clayey sand drk. yellow brown
¡nsitu / H
Test Data
MOISTURE CONTENT (%)**
Initial Test:
Final Test:
9.7
14.2
DRY DENSITY (pcf)**
Initial Test:
115
TEST CONDITIONS:
NORMAL LOADS (pst):
STRAIN RATE (in/min):
(C,D,S)
1000,2000,3000
0.0020
Results
INTERNAL FRICTION ANGLE (degrees)
Peak: 40
Ultimate: 33
APPARENT COHESION (pst)
Peak: 44
Ultimate: 0
* See Explanation of Logs for sampler symbol definitions. ** Average of three test points.
.:,:,,;,'S H E PAR D SON
¿"':::':- ENGINEERING ASSOCIA TES INC.
Geotechnical Consultants:
En ginee r s- G e 010 gists
Date:
October, 1996
Project No.:
96171-01
Direct Shear Test
Encinitas YMCA
Plate
C5
<0
('
(/)
0
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
125
-
u
E:
I--
::I:
Q
L.U 120
~
t::
z
::¡
>-
a::
a
115
100
0
Sample Location and Depth (feet):
Soil Type and Visual Description:
8-5 @ 2.5
clayey sand, drk. yellow brown
140
Results
ASTM D 1557-91 Method:
Maximum Dry Density (pcf):
Optimum Moisture Content (%):
In-Place Moisture Content (%):
135
USCS Group Symbol:
Liquid Limit (%):
Plastic Limit (%):
,;¡¡¡¡¡~¡, SHE PAR D SON
.¡¡¡¡¡H:¡::"- ENGINEERING ASSOCIA rES INC.
.,
Geotechnical Consultants:
En ginee r s - G eol 0 gists
130
Percent Finer 3/4-ìnch:
Percent Finer 1/4-inch:
Specific Gravity:
110
105
10
WATER CONTENT - PERCENT OF DRY WEIGHT
Date:
October, 1 996
Project No.:
A
127
10.0
Zero Air Void Curves
Gs=2.75
Gs = 2.70
Gs = 2.65
20
96171-01
Compaction Curve
Encinitas YMCA
Plate
C6
to
en
Cl..
U
I
8
I
I
'."'~:'
'. .
I
. ~ .'
I'
,;,.;.., ..
'4. ,';
I
,'-' '., "
^ ~,
I
I
I
I
I
I
I
..
I
I
I
I
I
I
0,
, '
, , .' ~~~:~...
8
,'0, '". ,
"
'.
- "
" .' ,~'.;;~~""
. " ,', ",n',"..'
APPENDIX
.'
D
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
1.0
8
8
RECOMMENDED GUIDE FOR PLACEMENT
OF ENGINEERED FILL
GENERAL
1.1 Purpose
The intent of this guide is to outline procedures for placing engineered fill soil to the lines and
grades shown on the approved plans. The recommendations contained in the preliminary
geotechnical investigation report prepared by Shepardson Engineering Associates, Inc. are a part of
this guide and would supersede the provisions contained in the guide in the case of conflict.
1.2
Jùv. 1192
Definition of Terms
0
Fill: All soil or rock material placed by man to raise the natural grade of the site or to
backfill an excavation.
0
Onsite Material: Soil and/or rock obtained from excavations within the boundaries of the
project.
0
Import Material: Soil andlor rock hauled in from offsite.
0
Engineered Fill: Fill which has been placed under the properly documented observation
and testing of a Geotechnical Engineer.
0
ASTM Specifications: Specifications contained. in the latest edition of the Standard.
Specifications of the American Society for Testing and Materials.
0
Relative Compaction: The ratio, expressed as a percentage, of the in-place dry density
of a soil, to the maximum dry density of the same material based on specific test
procedures referenced in the preliminary geotechnical investigation report.
0
Geotechnical Report: The soil and geologic reports (including addendwns) were
prepared specifically for the development of the project. The owner should confirm that
this report is current and valid for the project as presently planned.
0
Geotechnical Engineer: A registered professional Civil Engineer authorized by the State
of California to use the title Geotechnical Engineer (G.E.).
0
Engineering Geologist: An Engineering Geologist certified by the State of California.
SJIEP ARDSON ENGINEERING ASSOCIA TBS, INe.
I
I
I
I
I
I
I
I
I
I
I
I
I
I
:1
I
I
I
I
8
8
- 2-
0
Design Civil Engineer: A California Registered Professional Civil Engineer responsible
for the preparation of the grading plans and as-built topographical surveys.
1.3 Testing and Observations
The person responsible for the quality of the fill placement should employ a qualified Geotechnical
Engineer to provide observation and testing of the fill construction.
The Geotechnical Engineer should, when under contract, observe the grading operations during both
preparation of the site and construction of any engineered fill. He should perform a sufficient
number of field observations and tests to form an opinion regarding the conformance of the site
preparation, the suitability of the fill material, and the extent to which the results of the testing
indicate that the degree of compaction of the constructed fill meets the project specification. The
Geotechnical Engineer will inform the owner if the fill does not meet the specifications and can
assist in determining the limits of fill not meeting specified requirements. It is the responsibility of
the contractor and owner to keep the Geotechnical Engineer notified regarding work schedules and
changes in the project, or plans.
It is the sole responsibility of the contractor to determine the nature of the work and the
equipment/method required to adequately perform all work.
1.4 Existing Soil Conditions
A geotechnical investigation has been performed for this site. The contractor should familiarize
himself with geotechnical conditions at the site, whether covered in the report or not, and
acknowledge his understanding of all findings, conclusions, and recommendations associated with the
grading, or make a written request to the owner for appropriate clarification.
2.0
SITE PREPARATION
2.1 Clearing
Prior to excavating or filling all brush, vegetation, rubbish, debris and topsoil should be removed or
otherwise disposed of so as to leave the areas to be ftlled free of vegetation and debris. Any soft
and/or wet spots should be corrected by draining and/or removal of the unsuitable material. The
limits to which removal will be extended should be determined by the Geotechnical Engineer.
Grubbing consists of the removal of all tree stumps, roots or other projections larger than 2 inches
RII'. 1/92
SHEPARDSON BNGINBBRlNG ASSOCIATES, INe.
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
8
8
- 3 .
to a depth at least 3 feet below finished grade. Topsoil may be stockpiled for reuse subject to
evaluation by the Geotechnical Engineer.
2.2 Site Preparation
The ground to receive fill or improvements should be excavated of all loose and porous soil to the
depth recommended by the Geotechnical report. The natural ground exposed at the level which is
determined to be satisfactory for the support of the fill should then be plowed or scarified to a depth
of at least six inches and until the surface is free from ruts, hummocks.or other uneven features
which inhibit uniform compaction by the equipment to be used. The scarified ground should be
brought to the recommended moisture content and compacted to the minimum relative compaction
specified in the investigation report. Where undisturbed dense bedrock is exposed at the surface,
scarification and recompaction may be omitted if acceptable to the Geotechnical Engineer.
2.3 Benching
Where fill is placed on hillsides or exposed slope areas, the e?Ósting surface soil should be removed.
The depth of removal will vary based on site-specific conditions. If existing slopes are steeper than
five horizontal to one vertical (i.e.. 20%). horizontal benches should be cut into firm and competent
undisturbed soil or bedrock in accordance with illustration on the attached "Standard Grading
Guidelines." The width and frequency of the subsequent. higher benches may be varied by the
Geotechnical Engineer based on ground conditions and steepness of slope. The new horizontal
portion of each bench should be compacted prior to receiving fill. Ground slopes flatter than 20%
should be benched when recommended by the Geotechnical Engineer. The benches should be
constructed with the suñace inclined at not less than 2% gradient into the slope.
2.4
Subdrains
Canyon sub drains should be installed where recommended by the Geotechnical Engineer. Details
for subdrain construction are provided in the investigation report.
3.0
FILL MATERIAL AND SPECIAL REQUIREMENTS
3.1 The fill should consist of soil material approved for use by the Geotechnical Engineer or his
representative. This material may be obtained from the onsite excavation areas and any other
approved sources, or by blending soil from one or more sources. Samples of proposed import fill
should be submitted to the Geotechnical Engineer for review and testing at least five working days
/In. 1/'2
SHEPARDSON ENGINEERING ASSOCIATES, me.
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
8
8
- 4 -
prior to its importation.
3.2 Fill material should consist of soil so graded that at least 40% by dry weight of the material
passes a standard No.4 sieve. Soil with greater than low expansion potential should not be placed
within the upper four feet of the fill unless and placement is provided for in the preliminary
geotechnical investigation, or specific acceptance by the Geotechnical Engineer is obtained. A
definition of the expansion potential is presented in the investigation report. The material used
should be free of organic matter and other deleterious substances, and should not contain rocks or
lumps greater than twelve inches in least dimension except as provided for in the investigation
report. Soil with objectionable characteristics should be disposed of offsite or in nonstructural fill
areas, as defined by the project Design Civil and/or Geotechnical Engineer. The Geotechnical
Investigation Report may also specify additional soil suitability parameters for the fill.
3.3 During grading operations, testing may be performed to further determine the physical
characteristics of the fill. Any special treatment recommended as a result of this testing should
become an addendum to this guide. Boulders greater than twelve inches in least dimension, or the
thickness of the compacted lift, whichever is least, should be placed in accordance with the "Rock
Disposal Detail" presented in the investigation report. Continuous observation and testing by the
Geotechnical Engineer is a necessity during rock disposal operations.
3.4 All fill material shall be free of hazardous materials as defined by the California Code of
Regulations, Title 22, Division 4, Chapter 30, Article 9 and 10: 40CFR and any other applicable
local, state, or Federal regulations. The Geotechnical Engineer is not responsible for the
identification of possible hazardous material. The Geotechnical.Engineer may however observe soil
discoloration, odor or other indicators that may prompt him to recommend that the owner terminate
grading operations in the suspect area, and assess there condition prior to proceeding.
4.0
PLACING, SPREADING AND COMPACfING F1LL MATERIAL
The engineered fill material should be placed in approximately level layers which, when compacted,
do not exceed approximately eight inches in thickness, or less if necessary to obtain uniform,
minimum specified relative compaction. Each loose layer should be spread evenly and thoroughly
mixed during the spreading to promote both uniformity of material and moisture content.
Rn. 1/92
SHEPARDSON ENGINEERING ASSOCIATES, INC.
I
I
I
I
I
I
I
I
I
I
I
I
:1
I
I
I
I
I
I
8
8
- 5 -
When the moisture content of the fiU material is below that recommended by the Geotechnical
Engineer, Water should be uniformly added and blended until the moisture content is satisfactory.
When the moisture content of the fill material is above that recommended by the Geotechnical
Engineer, the fill material should be aerated by blending, scarifying, or other satisfactory means until
the moisture content is satisfactory. Fill, with a moisture content outside the recommended limits,
is normally considered unsuitable.
After each layer has been placed, mixed and spread evenly, it should be thoroughly compacted to
not less than 90% or the minimum relative compaction as referenced to AS1M D1557-78.
Compaction equipment should be of such design so as to compact the fill material to at least the
recommended density in a continuous and uniform manner over the entire area.
Fill slopes should be compacted by a means of sheepsfoot and grid rollers. Compacting of the slope
face should be accomplished by uniformly backrolling the slopes in maximum 4 feet fill height
intervals of elevation gain, or other methods producing satisfactory results to a relative compaction
of at least 90% followed by grid-rolling. Overbuilding and compacting the fill slope beyond the
finished slope line with subsequent trimming of all excess material is an acceptable alternate method.
5.0
TRENCH BACK.F1LL
Trench excavations for utility lines and pipes should be accomplished to the line and grade shown
on the project plans. The utility line or pipe should be properly bedded by backfilling the space
under and around the pipe with clean sand or approved granular soil to a depth of at least one foot
over the top of the pipe. The sand backfill should be uniformly compacted in place before the
engineered backfill is placed on the sand bedding.
The soil material accepted by the Geotechnical Engineer for use as backfill over the pipe, should be
watered and mixed as necessary prior to placement. The backfill should be compacted to a density
equivalent to at least 90% of the maximum laboratory dry density determined by the Geotechnical
Engineer.
In-place density tests and observations of the backfill procedures should be made by the
Geotechnical Engineer during backfilling. The contractor should provide test holes and exploratory
pits required by the Geotechnical Engineer during backfilling. The contractor should provide test
/In. 1192
SHEPARDSON ENGINEERING ASSOCIATES, INC.
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
8
8
- 6 -
holes and exploratory pits required by the Geotechnical Engineer to permit sampling and testing.
Shoring and/or sloping of the test holes should be provided by the contractor when the trench depth
exceeds five (5) feet.
6.0
TREATMENT AFTER COMPLETION OF GRADING
After grading is completed and the Geotechnical Engineer has finished his observations of the work,
no further excavation of filling should be done, except with the advanced notification of, and under
the observation of, the Geotechnical Engineer.
It is the responsibility of the contractor to prevent erosion of the freshly graded area during
construction and until such time as permanent drainage and erosion control measures have been
installed and established. Surface drainage should be maintained during and following construction
to avoid damage to the site or adjoining properties.
7.0
SEASONAL LIMITS
No fill material should be placed, spread or rolled while it is at an unsuitable high moisture content,
or during unfavorable weather conditions. When the work is interrupted by rain, fill operations
should not be resumed until tests by the Geotechnical Engineer indicate that the moisture content
and density of fill already placed are still within recommended limits. The contractor must control
surface water to avoid damage to finished work on the site or adjacent property.
8.0
UNFORESEEN CONDITIONS
In the event that site or soil conditions are encountered during site preparation and construction that
were not encountered during the preliminary geotechnical investigation, the Geotechnical .Engineer
should be notified immediately to permit evaluation and submittal of alternative recommendations
as needed. The Geotechnical Engineer should be notified of any significant changes in the proposed
site grading.
Røv. 1192
SHBP¡(JlJ)SON ENGINBElUNG ASSOCIATES, INC.
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
8
8
- 7 -
9.0
REPORTING
Upon completion of the work, Contractor should furnish Owner a certification by the Design Civil
Engineer stating that the lots andlor building pads are graded to within proper tolerance of
elevations shown on the grading plans and that all tops and toes of slopes are also within tolerance
of the positions shown on the grading plans. After installation of a section of subdrain, the project
Design Civil Engineer should survey its location and prepare an as-built plan of the subdrain
location. The project Design Civil Engineer should verify the proper outlet for the sub drains and
the Contractor should ensure that the drain system is free of obstructions.
The Owner is responsible for furnishing a final as-graded geotechnical report to the appropriate
governing or accepting agencies. The as-graded report should be prepared and signed by a
Geotechnical Engineer and, and if necessary by a California Certified Engineering Geologist,
indicating that the geotechnical aspects of the grading were performed in substantial conformance
with the Specifications or approved changes to the Specifications.
Rw. 1/92
SHEPARDSON ENGlNEERING ASSOCIATES, INe.
~.
a)
CUT LOT
It..
Variable FIll
Slope Height
Ì'..,
backcut--varle. ð.""
---
-: :. .i-1
Downslope
Key Depth
Comp
acted FIll
---- -
--- --
~~
---- -- -- ----
~ .......... ~~O"~""""" ..........
~ ~,-~
/' øCO\~~
'{ 9"\\" ~
...---þ ~
~---
Toe 01 Slope Shown
On GradIng Plan
---
~
iro..;
Benche. to be designed to proVIde gradual
change to sldehlJl fill. MInImum height of
benches I. 4 feet; wider benches when
specified In Investigation report or when
recommended by con8Ultant.
- ¿II.' 118'0"01
Suitable to Consuttant
3° mIn.
. f
l.0V8rexcaV8t8d and Recompact
(
Bedrock or approved foundation materIal.
DEEPER OVER-EXCAVATION MAY BE
REQUIRED BY THE GEOTECHNICAL
ENGINEER IN STEEP TRANSITIONS.
L
Keyway In firm earth material.
Minimum width of 15 f..t or a.
8p8clfled In InvestIgatIon report
[L1'tllt
I' back (mIn.)
NOTE: Where natural slope gradIent I. Ie...
than 5:1, the nece88lty for benchIng
..all be determined by the con8Ultant.
b) CUT-FILL LOT (TRANSmON )
Figure No.1
1
i
...
Keyway In firm earth material.
MInimum width of 15-f..t or
a. specified In In_.tlgatlon report.
..---
Cut elope to be conatncted prior
to placement of fill
CutlflJl contact shown
on gradIng Plan
Compacted All
-........""
--
-_....-
--
---""
.....- ..A<J~'
CO\\\'r-A(oG~ -- ""
.-ft\\' fð"" ....
~09"'- e(.I> ,"
~e.";:~
.
to#'Ò '1'--
\',\~.\ 9 ------
ot ::: ---- ..;:
....",,'
L
TYPICAL SIDEHILL FILL MASS
ABOVE NATURAL SLOPE
i...
L
Remo- all top80lI, colluvium
and creep Material from
transition
3' min.
!b'-,
Setback betw8en cut and
fill stope when 8p8c1f1ed
In In_.tlgatlon report.
\ (
\
-r-
Soli or MaterIal
Suitable to Con8Ultant
loti
¡
IIIi
Natural S]ope ----
-- ,...¿
-- ---
-- ---
--
Cut 8Iope
T
~ Sod,... ., S""."
foundation material.
Benche. to be de8lgned to
proVIde gradual change to
sldehlll fill. Minimum
heIght of benches I. 4 f..t;
wider benches when specifIed
In Investigation report or when
recommended by con.ultant.
Figure No.3
-
STRIPPING DETAIL-REMOVAL OF
DA YUGHT UNE
b
-¡.¡
Figure No.2
TYPICAL SIDEHILL FILL MASS ABOVE
EXISTING CUT SLOPE
NOTE: As an alternatl_, the cut po,rtlon of
the 8Iope can be o_rexcaV8t8d and the 8Iope
rebuilt using a keyway a. shown on FIgure No.1
NOTE: For additIonal details refer to the text of the Geotechnical
Investigation Report and the Recommended Guide for Placement
of Engineered Fill. BackdraJns may be required ba8ed on
consultant's observations.
c....
~ SHEPARDSON
~. ENC1NEERING AssoaA75 INC.
Gcøt«lutial ÚtuMlt.tds:
£"fÌrurn- GcoleriW
Job Number:
. Date:
Plate
STANDARD GRADING GUIDEUNES
k.
SEA R
!leY: 41811
.
.~ NOLTE and Asso8TES, Inc.
. .. Engineers / Planners / Surveyors
JOB NO. ~DO? ",,-2.
DATE / / //9/ 9 {¡;
DESIGNED BY æ
CHECKED BY Ij J2f1
8
SUBJECT
~OD I?d. ,JC(I'1'ßj
(-
V)
~
I'~,'D-~ ¡-e f,ILÌ Il.~, !! I,v' ! '
! C,,' ,,_IF, 1 '.', '1': \, j:"
--' - - \ ¡ ¡ !
ru L~)
.,J JAN 1 4 1997
ENGINEERING SERVICES
CITY OF ENC¡NITj\:~
~ -C.do/'LO)O
\ "
~\
~\ -
~ ~
~) \ ~ .....
X
<..J ........ Q.)
11 (7=1 /6 'ð}ð')/ ) ' à
(:;;1. g.£. l dJ ~ 1:\.\
t ~
'"
\
\
77 flt'if "'
~ ~ ..
h-.' II ~
\,)-- - I
~\ ~ ...\
;.: "-
,~ ,I\}--~~,
~~~
.N~ NOLTE and Asso8TES, Inc.
~ Engineers / Planners / Surveyors
SUBJECT
~x~ "Rd IIJldill//'.t1
0'
~-
~'L'll
^
~¡
::s:
()
77 1/,."
~
~
Cz/'gðJ/)
"
( 7.::ÏdJ!; 'Lð) i)
(. 'Z2L @6 'LftJ /)
7:J z,9:L.<7J/
"JJ.. ?,o'g~ /
( f./'dJdJ /)
8
~1""Y"'. (;2tl,.e
JOB NO. ~--- ~
DATE II /Jq Ie¡ Ú)
DESIGNED BY ¿13
CHECKED BY ¡j J2H
~ "
~~
~
~
,
«>
~
({)
~
... . .~--~- .
..
~ ~ ..
..'\ ~
~"
~~
~~ ~
.......~ NOLTE and ASSO.ES, Inc.
~- ~ Engineers / Planners / Surveyors
SUBJECT
'Sqxo~ ¡q;¡ I/Jdenl '()
~
-. -p-- -- ---~-~
~
-..-::
(-J.//;ð)!)
8
JOB NO. SP:>~~~
DATE IIIJ919~
DESIGNED BY /.,/3
CHECKED BY i/ lZII
~~
- (C:/£t7J,gtT)/)
Iù ~ CJB'EJdJ l
-:>::i c:7)g.' 8ðJ / ~
P.l. o;Q '6ð'J1 ' ~
~ ~
'-
771/f'1
(Lr7J '~dJ/)
.",'___n...
...
8- -Q ~
"h- ~\\ \\
D'~
" N
~ :--...'-\...\
-- ~- ~
~-~
NOLTE and ASSO~ES, Inc.
Engineers 1 Planners / Surveyors
SUBJECT
~~ Rq w4el?/~
f'-
~
\'::V
(Z<J'oL~
C'16 . 'J'J.?
ï7f1(YJ
8
JOB NO. "EEo B ~ .z.
DATE 11/ /9 ¡'J(p
DESIGNED BY LJ3
CHECKED BY V ¡¿../-I
~b
~
'"
..
~
\.f)
...
~
,
't'
.Q ~ ~
~ ~I ;:1\
û"'"
"" r-J
~~í
\j) ~ ::s.
N. . NOLTE and ASSO~ES, Inc.
~ Engineers 1 Planners / Surveyors
SUBJECT
<::::v,V,' "', I '~;j" //) ,Ie, .
~^'--I;~' c-- \ ,/\ 111"/
~, (::
0
"
~
I
\
\
\~
\
g
( ~.9 'OtJ )
n,__- --------
ðJL 'OLI
7::1 þ/'oL/
'DlV') 'OLI
( '1 $' C'L/)
.ì
>-
't()
~
\<)
~
N
l[>
~
8
JOB NO. ÇCO~S~
DATE ////'1/q~
DESIGNED BY ;.;-ß
CHECKED BY iJ/?ft
-------,
~~ Ò'
~ '....... ~
Ç) 0 ,I' II
~~,,~
~.. '~ t>J ~
~~l~
"N~ NOLTE and ASSO.TES, Inc.
~ Engineers / Planners / Surveyors
SUBJECT
~~ Rei (AJ¡c!f"/7ìtl1
c/
~
~
~
~
Ç)
~
~
i\~
~~
" \~
\
8
~
........
(~¡"'I I)
77{,p;
('7:2' 'oLD
(ï).L 0'21L I)
7=i ~'Ot.,
?L $';'; LI
JOB NO. SDa~~-Z
DATE ////Cf/o/CR
DESIGNED BY ¿'ß
CHECKED BY I/Rfl
,----,,-~-
~~
'~
. '4)
t
~
-
~
(91J~/)
-~----- .... _-n- "-nn,,
-
°.Q~
- ..~--~"--:.w- n
..... ....... ,
~ .......
-, N
~~
_n~ ~~
. ~ NOLTE and Asso8TES Ine
- Engineers / Planners / Surv~yor;
8
SUBJECT
S::ix~ ¡:?q w,d€-nIlJQ
CY
JOB NO. ~CO 'Z ~ '2.
DATE III /9/9tP
DESIGNED BY t..l3
~
........
CHECKED BY :}.elf
~
( n;' Z/.. !)
,
- ._-~
~
~\
~\
.J.SlX;; .:;:::;\
~ßII
~ £~ 'ILl Q
~~ ~
s -.::.
-~--+----
..
~~
- '-5<
"tti
c.. 7:::1 'U- '! LI ?
DJ. bb ïLI)
7=1 Ls, 'IL I
:lL Lo' LI
t
Iò
~
\\-.
\0
'to-
...
~ 0...
3f~
... ~"
~ "
'1\&
-t
~~§
( -þb'dJl}/)
Î'flf"1
.N~ NOLTE and ASSO&ES, Inc.
~ Engineers / Planners / Surveyors
SUBJECT
S;{~ f?cI t<,.)¡clélJ~
~
\
~,
~
\
.Ls./ X a
EEl.!
776<11
8
R
-..
JOB NO. ~.[;c'3Bt.
DATE 1111'1/9ú;
DESIGNED BY ¿ B
CHECKED BY ;) t:H
- (:2'8' 'J,Lt)
~
'tù
0
~
-S
,
~
\J1
*
7.::¡;1' Z L. 1
-;.L bL 'JL I
~'J'~~J/)
0 Ò...
~, ":- \J
i-.. _'I II
~... ~
"""
....~
~!~
NOLTE and ASSO8rES, Inc.
Engineers 1 Planners / Surveyors
SUBJECT
Sà.xù1; 'Kt" ¿1)¡[/(/It1(j
0'
~
\
\
J
1::.\
~
\
.../.SIX;)
...Lß.!it.{
7 i -1:1 (VJ
8
Q
----..
JOB NO. SDð~~~
DATE / II/919ft;
DESIGNED BY :...8
CHECKED BY iI~)f
l'
ì
(LdJ "2Lr)
.--- -. --. _.-
....
~~
~)<
LQ
(7.dti2'~¡)
;:J.L9Þ'$LI)
~ '
~ ~
-. .~
'd otJ '~L I
7)L~~ ';'L (
() ..
Q-~
~ ,'I ,\\
~""'"
......Nt
~ju§
0 r.....~ NOLTE and ASSO8rES, Inc.
A. ~ Engineers / Planners / Surveyors
SUBJECT
~XCJl(3 I?d rÌ:Jldl'n/(J
g
"
~
\
'\
( Co ÞL.I)
\
~\
~
~\
\
J
~,,~
~
'-......
...........
(7.=1 S-~ '~LI j
72L6JL.'9L.1)
77f1fYJ
8
JOB NO. $'DOß'3~
DATE ////9/9f.#
DESIGNED BY ¿13
CHECKED BY I/¡::'¡¡
h
ti~
,
0.-
~
~
( dJt.'~ f)
---t-r~ -- ----1
--t--- . -
f',-
-.. () -
- ""'-
~~" ~
J)-~
" ~
----- ~ ~..~
8
8
rrr" ~
DRAINAGE STUDY FOR PUBLIC IMPROVEMENTS IN
SAXONY ROAD, STA. 9+29 TO 13+18, WEST SIDE
EXISTING CONDITIONS
The present drainage condition is that runoff in Saxony Road breaks north and south at a
high point at approximately station 21 +50. Runoff is collected against the existing west
side curb and gutter, and conveyed southerly to the existing type "c" inlet and the 16'
type "B-1" inlet at station 9+25 (as shown on TM 4281-1). These existing stonn drain
inlets are located at the southerly tenninus of the proposed improvements. Existing City
of Encinitas topo (attached) and a field check of the area shows that streets are crowned,
therefore the drainage basin will consist only of the area west of the Saxony Road
centerline and north of the inlets to station 21 +50. See cales for this area and the resultant
runoff.
PROPOSED CONDITION
This project proposes only to remove the existing berm on the west side of Saxony Road,
and replace with a curb, gutter and sidewalk at the ultimate width. The adjacent on-site
work for the expansion of the YMCA facility consists strictly of on-site work, downslope
from the street; therefore, no additional runoff will be created in the street as a result of
this project. Drainage calculations for on-site work will be covered by a separate grading
plan submittal. Therefore, the existing drainage facilities will remain in place and will be
adequate to collect the runoff.
SUMMARY
The attached calculations and charts show the runoff calculations and capacities for the
curb and inlet on Saxony Road described above. It is assumed that the installation ofthe
existing inlets and stonn drain was perfonned for ultimate runoff capacity. Because the
subject project does not increase runoff, there is no need to improve the existing stonn
drain system.
tL _-/L~
Jimes R Hettinger RC.E 56
Exp. 12-31-96
/1-2. 7-'"
Date
~
.,( JLTf and ASSOCIATfS.lnc
"'"~" "',"om, '"~~
8
8
N~ NOLTE and ASSOCIATES, Inc.
~ Engineers / Planners / Surveyors
SUBIECT_~("....,.,.....rÂG ¡;; ;;¡;,?'t.I¡;)Yj ~V"rJ....r"r /-tL()øI1-~
./
JOB NO. 5. D 0 3':3 L-
DATE / / - Z ?-;Jc.
DESIGNED BY 9 ¡¿')Î-
CHECKED BY
c;.,(2 ( -r€7¿ I A , 1:1 ~ r J 0 F C/I '- c- V'-;4. 71' 0 ;oJ
I
f) C:9 VMr-( ö¡:: ..s.,A~ Df £GO oe.~/6v t p~f!) CßOc/A!!J!!!1- ¡t/'IA-NI/Æ-L.
COv'NrY cS>F $..4V" DIeGO t:'.50Pc..VV/AL$ (CJ-fA;"I27S ~~
2-) oe.7e/£"~'1l'f..Je r¿VtVùf7C" ~,L /OO.Yc...1...L f5Ve;".....fr
~) V:: e. /~ ~~/' ON A l- HI e:?'~é) ~ ;
9,..;),J .::- C-.I; ~ A
4) I~ C 7"'#1 e ~ c.:JAft:e,.Jr~,A"""cj;o../) ]
::e:e- A7rA c"" er:;;;
1; 0 () (/N 7'"'&J':: fry)
s) c - FA Co- ..,.... ð r¿ ( 12 C) N' ()F7C c-o ~ I'" ~ I (!7...1"'" )
t./ $ ~ c.. =- c. 9f .... Vla~C/'A\ c. L Y """'"" '-~ -+-tltc:"A-- /..$
/M~YIO liS
~) /t¡¡~ OF P¡ti!Ar"'/Â.Gf!f- 81+.$.'rV: ,LIA'-r-W,~rH d-F
,
~ T~~ ; .sHðVL..o~ 9- + '2..S" ?""~ 2.1 +..s-o II
A =
ð.':; A c.
¡¿ v^rð F F
Q'<J,j .:= C. I,o( A
Ie- .:
/.5 (f.J-C)Vo
~
9,~v := (p.ø;~4-.S)(O~ ~3)
Ie. ~
8.; M 'A/c) 7~.s
({/J~ ,It) ~4r"..,.)
(?~ù ~ 3.~' ~ tI-. t) C¡:',£
I,orJ-= 4.5" /.N./HOiI~
POtJOING oe-p~ /AI ~u.".r~
.5T4Z6:E?r S~oð'~ 3.2../"0 1
cO= 4.~ CP~ J
O~Jtl7""~ .:: o. 3:3 P7: < 0, 4-0 ~-q .t::!.
. ~
( '1-$,5 4AV1 es 2..70 c ~.vJ
V ~ s- 0 ~.s
Pt:X. (;.{~Y' ()¡C .s.O-
-. -----
8
8
NOLTE and ASSOCIATES, Inc.
Engineers I Planners I Surveyors
JOB NO.
DATE
SPCJ33'2-
I( - ¿7-g~
O/Z-;>J.-
,
UBjECT O¡2.AI~Â ç;;cs: s-rvc; y J ..:;.A >cc,..ry l'C::ôcÅD
,.
DESIGNED BY
CHECKED BY
C (-1 ~ c..¡ c:.. I' A/ c...l!!!!-I' c.. ~ ~ A C I .,-y
/G I
B -( I'~r'-~
Œ
c:,:; + Z-.:J"
//<.J '- ~ <:) ~ ..; '-\J ~e
./
AT"
~ . ~ 10
( í. ,.../\,
4- 2..B 1- / )
0= 4-°
c..r-s
.::-
¡jIJ
&;) ~ "'r"~ ""7 (;,(.)'<"8 = O~ 2... '7 /
V.: 5" - ~ P-ï'$,
:: P4 ~ ~ (-,-..." ~
311-
Q ~ ð-? '- (A~Y)
A =- 0- '3.3
'-t=Q~,-7'
c... .:: I'.:s-'
--------------
C-A~A C,'r"1' :: 9::. (0- ?)(, $) ( 0- 3'3 + o.l-?) ')'1-
-~------------
- ~ -- -- -- -
C ~~A C I..,..Y =
4-,f,8
CF$ >
Q. 0
C- ,:::: .!.
<::) , Ie::-.
~
u ----------- ---
- ---- -- - u-
.- ----------.
.u--------_u_----
------.--
8
8
URBAN AREAS
TIME OF FLOW
OVERLAND
CURVES
----
800
Q
,
-
...
...
...
~
-
I
'"
~
Ž
3
~
~
~
100
600
400
...
u
Z
~
-
'"
ã
;.;..:¡~:::;
I; :::..:.;-;.~:
..----..
:-: :;-I:-~
1 - ." "-I_. .
3CIO
. .... . ...
," . . '--' -.
.. h -~.
. . -. . , .. ;-
200
. œ-= 1: ~-
t ~...,
.- .. _.. -
. . . --.. -"
¡;~::':':=;:.
.. . ,-'.... -
100
:; r:-:_-;;=~:
~ '-.. -:......
:~~:.. -
.._.~ ..
,::nl-: ; ; .
,...-.....
10
-
0
Surf8ce "- TI- c..-
~
- - -- --------- -
E.XAM PLE-:
(:,tVEN L..E.NGiTH OF FLo,^, ~
~ i-OPE..;:. ,. D Cf'e.
c.OEFftc'IE.NT OF- R.v~oF~
OV~ L..AN D FLOwr' mE.;:.
86
400
Fr-
e.
:: .70
K.~ A ï:>
t5
M,NVí~5
( I -£)
FLOOD CONTROL
4S'
30' :
338
45'
P,ep."d br
8
~
8
- -
u.s. DEPARTMEN~r OF COMMERCE
NATIONAL OCEANIC AND AT. OSPIIEHIC ADMINISTRATION
.paCIAL ITUDI&I BRANCH. OFFICE OF 81 DROLOOV. NATIONAL WEATtI£R SERvrca
30'
118'
4S'
30'
115'
117°
IS'
30'
151
116°
Revised 1/85
APPENDIX XI-E
"51
301
IS I
.338
"SI
SIn::
,-0-
u.s. DEPARTMENlr OF COMMERCE
Plep.t... br
8
8
NATIONAL OCI::A:"IC AND A"':~O~I'IIERIC ADMINISTHATION
SpaCIAL STUDIES 8HANCII. Ot'l"IC~ 01' IItO¡':OLOGY. NATIONAL WI::ATIIEK SERVICE
30'
-<
~
1
'J:
. ~
IWO
liS'
301
1.-. I
117°
,~ 1
116"
'1 ~i .
]01
Revised 1/85
APPENDIX XI-II
¡m I n í'~~:: ::: ,.. ";" ;,:,.í..;,:,~; ~ ~ 'D'~ :'645 u¥", n II 11m 1/
- . -]
. - . I . Intensity Un./Hr.) . n-
P6. 6 Hr. Precipitation (In.)
D .
.~
"
lit
..
~ . .. .."
~ - -
. .1
~ .
.. . .
.. . ~.. - . .I.""""""""'.
. _e.":: HHUUIUUIIIU"""
..: :r.'"
.. - . -..-- .......................-...
t- - ... . .. . mmwHJIHH Itt:H:HmI:
. I nmmtnmunll:1tttnmt
~ .
. 1001il
.. .! ',. .
-
1.5'
,.,
-,
-
t;.
J
1.0
-
".-"'1"': .
10
15 20
Minutes
30
40 50 1
Duration
2 3:
Hours
5
6
4
Directions for Application:
1) From precipitation r!laps detennine 6 hr. and
24 hr. amounts for the selected frequency.
These maps are printed in the County Hydrology
Manual (10.50 and 100 yr. maps included in thl
Design and Procedure Manual).
2) Adjust 6 hr. precipitation (if necessary) so
that it is within the range of 45% to 65% of
the 24 hr. precipitation. (Not applicable
to Desert)
3) Plot 6 hr. precipitation on the right side 4IÞ
of the chart.
4) Draw a line through the point parallel to the
plotted lines.
5) This line is the intensity-duration curve for
the location being analyzed.
Application Form:
0) Selected Frequency /00 yr.
*
1) P6 = 2.7 in.. P24= 4-."3. P6 =
P24
in.
Cø2.~S*
8
2) Adjusted *P 6c '2- .7
3) t = ~ .3 min.
c
4) I = 4-.S: in/hr.
*Not Applicable to Desert Region
Revised 1/85 APPENDIX XI-A
.'
,
'"
¡ ,
I
i-
....
-r
t-
~
III
!
~
lit
~
~
I.S""
REV.
8
8
CHART /-/04./2
t -Y.
t- LI'-f
~ ..~
~O" -f-t ,~
IlUIDrNTIAI. '"'En'
CIC IIDI 0..'
10
II
L-:.
I
I.
Noll ~"~-.- ;::::;:¡
II ~~,,' I ~~,+
-- r "'iiiT
81 " ..... J ; 'f...... I ; I I
II V / j FO;; .....l. . ¡ Ì"...... 'I
t !~...... I, ~1 '~I
.1 :7, -........1 I : ~ I.:
';~.f I '!".... I I~ /'"'.1'
.~. - 0 '1.: ~Io... ,,~¡ I "'":
.! vI :~~ / '~ 7 I /~V'
: I j,f¡ ¡ - i '/l~ ~ ~ #I ~! / : i)j
. V j ¡ ~ ~ ;¡, ~~.. ~ ~ / i
. ~ '-J/' I '.f --r--.t.~~.il . ~-¡. ~i l' /
-: I' I'
LI ; I !t'.~""""'- to) '^- ,
\I' I II , 110.. I~. J.~ 'C7 -./1.., ~ I
.. , ') - .J':"...... -.-.o¡ I' ~ I I
II: ,I ""'""-I. t 'f '"q . ff -N- ~: J.7 ~
10" V J ~ ...... ~ .. .~ ~. }. '" ~ 7 ,/ ~- ;
QI ........ : v ...... ::s..{¡' ~ ~ I ~l J,'-
QI I / -"... I J' ~ rç:.I ~it ~.
A1 1 I ;"'0 .... I j ~T"""'10.... I -.....:::. I-' "W/ ,--¡-
" / ~~~# f.' .'~ ~ I I -
cu- 7 I ~ ~ I ~ /: ~ T
04- ",V' ""- '- 7 ~ / I- N -
I I I I f"ll I I I I'
. I I. "'10 ID JO -010
OISCMA- (Crs)
ÞAM~ : ONE SlOE
Gi..flIO8tO '82,5.,.
CMtt ."'1 0.,... 8 Go4. Ylllcitr . 4.4 taL
'i
I ro
¡
.,
, I
. .
CITY OF SAN DIEGO - DESIGN GUICE
GUTTER ANC ROADWAY
DISCHARGE- VELOCITY CHART
SHT. NO-
70A