Loading...
1996-4601 G Street Address ~ fro 5 Category I .Lj ç¡q 7-0 Serial # If rp ð( 67 Name I Description Year Plan ck. # recdescv NORTH COUNTY COMPACTION ENGINEERING, INC. April 24, 1997 Project No. CE-5213 Page 2 Grading operations were performed in order to create a level building pad to accommodate post tension slab on grade construction. Should the finished pad be altered in any way, we should be contacted to provide additional recommendations. The site was graded in accordance with recommendations set forth in our previously submitted report. The site was grade to approximately conform to project plans. Actual pad size and elevation may differ. Finish grade operations are to be completed at a later date. LABORATORY TESTING Representative soils samples were collected and returned to the laboratory for testing. The following tests were performed and are tabulated on attached Plate No. Three. 1. Optimum MoisturelMaximum Density (ASTM D-1557) 2. Expansion Potential Test (UBC 18-2) 3. Direct Shear Test (ASTM D-3080) 4. Plastic Index Test (ASTM D-4318) 5 Sieve Analysis (ASTM D-421) SOIL CONDITIONS Native soils encountered were silty-clays, sandy-clays, and Gravelly-Clay. Fill soils were imported and generated from on-site excavation. The building site contained a transition from cut to fill. However, cut areas located within the building area were over excavated a minimum of 3 feet and brought to grade with compacted soil. Over excavation was carried a minimum of 10 feet beyond the exterior building perimeter. Hence, no consideration need be given this characteristic. Oversize materials having a diameter of greater than 12 inches were sorted out of fill fines and hauled off-site. Expansive soils were observed during grading and exist within 3 feet of finish grade. However, it is our opinion, the proposed post tension foundation system will perform well with regard to this condition if properly designed. NORTH .cOUNTY COMPACTION ENGINEERING, INC. April 24, 1997 Project No. CE-5213 Page 3 The key was approximately 25 feet wide, a minimum of 3 feet in depth, and inclined into the slope. During earthwork construction, native areas to receive fill were scarified, watered, and compacted to a minimum of ninety percent (90%) of maximum density Subsequent fill soils were placed, watered, and compacted in 6 inch lifts. Benches were constructed in natural ground at intermediate levels to properly support the fill. To determine the degree of compaction, field density tests were performed in accordance with ASTM D-1556 or D-2922 at the approximate horizontal locations designated on the attached Plate No. One entitled, "Test Location Sketch". A tabulation of test results and their vertical locations are presented on the attached Plate No. Two entitled "Tabulation of Test Results". During grading operations, all fill soils found to have a relative compaction of less the ninety percent (90%) were reworked until proper compaction was achieved. RECOMMENDATIONS AND CONCLUSIONS Continuous inspection was not requested to verify fill soils were placed in accordance with current standard practices regarding grading operations and earthwork construction. Therefore, as economically feasible as possible, part-time inspection was provided. Hence, the following recommendations .are based on the assumption that all areas tested are representative of the entire project. 1). Compacted fill and natural ground within the defined building areas have adequate strength to safely support the proposed loads. 2). Slopes may be considered stable with relation to deep seated failure provided they are properly maintained. Slopes should be planted with light groundcover (no gorilla ice plant) indigenous to the area. Drainage should be diverted away from the slopes to prevent water flowing on the face of slope. This will reduce the probability of failure as a result of erosion. 3). Continuous footings having a minimum width of 12 inches and founded a minimum of 24 inches below lowest adjacent grade for one and two stories, will have an estimated allowable bearing value of 1000 pounds per square foot. 4). Footings located on or adjacent to slopes should be founded at a depth such that the horizontal distance from the bottom outside face of footing to the face of the slope is a minimum of 8 feet. NORTH .COUNTY COMPACTION ENGINEERING, INC. April 24, 1997 Project No. CE-5213 Page 4 5). Plumbing trenches should be backfilled with non-expansive soils having a swell of less than two percent (2%) and a minimum sand equivalent of30. Backfill soils should be inspected and compacted to a minimum of ninety percent (90%). 6). Unless requested, recommendations for future improvements (additions, pools, recreational slabs, additional grading, etc.) were not included in this report. Prior to construction, we should be contacted to update conditions and provide additional recommendations. 7). Completion of grading operations were left at rough grade. Therefore, we . recommend a landscape architect be contacted to provide finish grade and drainage recommendations. Drainage recommendations should include two percent (2%) fall away from all foundation zones. POST -TENSION SLAB AND FOUNDATION The following post tension design criteria was calculated utilizing laboratory tests on representative soil sample obtained within the proposed founda~ion bearing zone and Section 1815, Standards 1994 Edition o(the Uniform Building Code. The design should be performed by a licensed engineer engaged in this type of design and who has a minimum of 5 years experience. 1). Continuous footings having a minimum width of 12 inches and founded a minimum of 24 inches below lowest adjacent grade will have an allowable bearing pressure of 1000 pounds per square foot. 2). On-Site soils were found to have an expansion index of 63. 3). Em Center Lift Em Edge Lift Y m Center Lift Ym Edge Lift = 5.5' (Edge moisture variation distance) = 2.6' (Edge moisture variation distance) = 1.76" (Max. differential soil movement) = 0.22" (Max. Differential soil movement) 4) Clayey soils should not be allowed to dry prior to placing concrete. They should be kept in a very moist condition or at a moisture content exceeding optimum moisture content by a minimum of three percent (3%). NORTH .cOUNTY COMPACTION ENGINEERING, INC. April 24, 1997 Project No. CE-5213 Page 5 Prior to pouring of concrete, North County COMPACTION ENGINEERING, INc. Should be contacted to inspect foundation recommendations for compliance to those set forth. During placement of concrete North County COMPACTION ENGINEERING, INC. And/or a qualified concrete inspector should be present to document construction of foundations. UNCERTAINTY AND LIMITATIONS In the event foundation excavation and steel placement inspection is required and/or requested, an additional cost of $170.00 will be invoiced to perform the field inspection and prepare a "Final Conformance Letter". If foundations are constructed in more than one phase, $120.00 for each additional inspection will be invoiced. It is the responsibility of the owner and/or his representative to carry our recommendations set forth in this report. San Diego County is located in a high risk area with regard to earthquake. Earthquake resistant projects are economically unfeasible. Therefore, damage as a result of earthquake is probable and we assume no liability. . We assume the on-site safety of our personnel only. We cannot assume liability of personnel other than our own, It is the responsibility of the owner and contractor to insure construction operations are conducted in a safe manner and in conformance with regulations governed by CAL-OSHA and/or local agencies. If you have any questions, please do not hesitate to contact us. This opportunity to be of service is sincerely appreciated. Respectfully submitted, North County COMPACTION ENGINEERING, INc. ~¿;a¿ Ronald K. Adams President eM Dale R. Regh Registered CiVl Geotechnical Engi RKA:kla cc: (3) submitted . , NORTH COUNTY COMPACTION ENGINEERING, INC. SOIL TESTING , PROPOSED SINGLE FAMILY DWELLING A S ~l pprox. ca \ LOT #22 OF WILDFLOWER ESTATES :". " , 1" = 40' ENCINITAS, CALIFORNIA Il'~~. '-~:~S_mj~_C~~~::--. " ,: -,', '" "',Z.R~_- .. , ' , " ~ ,00 4. 05'J~ J:!¡", -' - --=---;-- - -, ,-' '- I NOTE: Cut side of bldg '~/h 00-._, '...n.-'~"'" '-. -'-II: Pad was undercut fie.:, " -,."., ,Z4 ,....".~" -' t I 2:11Wl 3 feet & recompacte~,' " :: " \ " to grade. 'v " :- .'- '-J...' ',' ~... I .. .':_-- --' ,,- '~I 'I' .( .. " 24 ....." "'2.3 'TisT ..,., .. , "" ..' ' - ,-------~- .IS.. ..TEST, ",' ",--' .' ,..:~,~.~~,.. ..-.",'" ,-27 .' 30 ",'.. 17, ~j «.' ~ ~;~' 0," ~, <9... ð~ ...~. , b<9 '\ ' . .p' ," " ..' 2:1'- .,..... .....-...-- . . .-~~ ,. r1' ,..,.) , I ,~~ I ." fSJ! ~..Il \-r ,..4 to.., '11>' , ...' \0' :r::w<- .' ,.." _.. "....,-.-.."..'.. ." ,_.---~. TEST LocATION SKETCH ,PROJECT No. CE-5213 PLA TE No. ONE NORTH COUNTY COMPACTION ENGINEERING, INC. Test # Date Horizontal Vertical Field Moisture Dry Density Soil Percent of Location Location % Dry Wt. LB Cu. Ft. Type Compaction I 03/19/97 See 200.0 13.7 118.2 I 97.3 2 " Plate 198.0 13.4 111.8 II 92.0 3 03/20/97 One 201.0 12.6 112.3 II 92.4 4 " " 203.0 17.7 114.7 II 94.4 5 03/21/97 " 205.0 16.7 118.0 II 97.1 6 " " 207.0 16.4 116.2 II 95.6 7 " " 206.0 16.7 117.4 II 96.7 8 " " 208.0 17.2 113.6 II 93.5 9 03/2597 " 210.0 16.8 115.6 II 95.1 10 " " 211.0 15.2 110.3 II 90.7 11 ," " 210.0 16.9 109.6 II 90.2 12 03/26/97 " 212.0 22.4 112.3 II 92.4 13 " " 213.0 18.6 111.4 II 91.6 14 03/27/97 " 214.0 16.7 115.0 III 91.7 15 " " 215.0 15.6 113.7 III 90,6 16 " " 216.0 14.7 114.9 III 91.6 17 03/31/97 " 217.0 18.1 115.1 III 91.7 18 04/01/97 219.0 16.1 112.9 III 90.0 19 " " 219.0 17.7 117.9 III 94.6 20 220.0 12.5 123.0 III 98.0 21 04/02/97 " 221.0 17.3 113.3 III 90.3 22 222.0 15.1 114.9 III 91.6 23 " " 224.0 16.1 113.9 III 90.8 24 " 225.0 16.1 113.7 III 90.6 25 " " 224.0 14.3 114.2 III 91.0 26 " " 221.0 16.3 115.3 III 91.9 27 " " 222.0 15.4 112.9 III 90.0 28 " " 223.0 13.8 114.3 IV 93.5 29 " " 223.0 14.9 116.7 IV 95.4 30 04/03/97 " 225.0 15.6 114.1 IV 93.3 31 " " 225.0 17.5 113.6 IV 92.9 32 04/24/97 " 226.0 RFG 12.7 113.9 V 94.5 33 " " 226.0 RFG 13.5 115.1 V 95.5 REMARKS: RFG = Rough Finish Grade PROJECT NO, CE-5213 PLATE-NO. TWO NORTH CÇ>UNTY COMPACTION ENGINEERING, INC. TABULATION OF TEST RESULTS OPTIMUM MOISTURE/MAXIMUM DENSITY SOIL DESCRIPTION IYfE MAX. DRY DENSITY OPT. MOISTURE (LB. CU. FT) (%DRYWT) Orange Brown Silty-Clay I 121.5 14.5 Yellow Brown Gravelly-Clay II 121.5 14.2 Red Orange Silty-Sandy Gravelly-Clay III 125.4 11.8 Orange Brown Silty-Sandy Gravelly-Clay IV 122.2 13.6 Light Tan Silty-Sand (Import) V 120.5 12.2 EXPANSION POTENTIAL SAMPLE NO. CONDITION INITIAL MOISTURE (%) AIR DRY MOISTURE (%) FINAL MOISTURE (%) FINAL DRY DENSITY (PCF) LOAD (PSF) SWELL (%) EXPANSION INDEX I Remold 90% 15.0 ,9.7 22.1 109.3 150 13.4 134 IV Remold 90% 13.6 8.5 23.7 110.0 150 6.3 63 II Remold 90% 13.6 8.4 18.4 109.3 150 5.3 53 DIRECT SHEAR SAMPLE NO. CONDITION ANGLE INTERNAL FRICTION COHESION INTERCEPT (PCF) II Remold 90% 24 200 IV Remold 90% 20 200 PLASTIC INDEX/SIEVE ANALYSIS SAMPLE NO. LIQUID LIMIT PLASTIC LIMIT PLASTIC INDEX % PASSING #200 IV 42 22 20 50.4 PROJECT NO. CE-5213 PLATE NQ, THREE . '... . / K&S ENGINEERING Planning Engineering Surveying HYDROLOGICAL ANALYSIS FOR Wildflower Estates Lot 22 IN CITY OF Encinitas . ' ,..,') (' ." \ :,: \' \" ¡ r ô") \~ ~ Is \i \~i Ü' \ "\- ~ \ n \ ,...' 96 uú ;'Jutt 10 19, E'" .. c'C\"iG SER\lIC ;:, ENG\\\!E(:f~\;; NC\NITI\S CITY OF E. JN 9560 June 4, 1996 ~~Ýb D A 'lYE '.' , " TABLE OF CONTENTS l,SITE DESCRIPTION 2,HYDROLOGY DESIGN MODELS 3.HYDROLOGIC CALCULATIONS ... ",......,. ,....,...... APPENDIX A 4. HYDROLOGY MAPS. , . . . . . . . , . . , , . , , , . . . . , . . , . . . . . , . .. APPENDIX B 5. TABLES AND CHARTS......,..,....................., APPENDIX C . . ~ , l,SITE DESCRIPTION THE OFFSITE DRAINAGE AREA IS CONTAINED BY STREET CURB AND GUTTER. THE ONSITE DRAINAGE AREA IS SHEET FLOWING SOUTHERLY TO A LOW POINT ON THE TOP OF THE FILL SLOPE AND CONVEYED TO AN EXISTING DRAINAGE POND VIA 8" PVC PIPE, .' ~ ~ 2, HYDROLOGY DESIGN MODELS A, DESIGN METHODS THE RATIONAL METHOD IS USED IN THIS HYDROLOGY STUDY; THE RATIONAL FORMULA IS AS FOLLOWS: Q = CIA, WHERE: Q= PEAK DISCHARGE IN CUBIC FEET/SECOND * C = RUNOFF COEFFICIENT (DIMENSIONLESS) I = RAINFALL INTENSITY IN INCHES/HOUR A = TRIBUTARY DRAINAGE AREA IN ACRES *1 ACRE INCHES/HOUR = 1.008 CUBIC FEET/SEC THE OVERLAND FLOW METHOD IS ALSO USED IN THIS HYDROLOGY STUDY; THE OVERLAND FLOW FORMULA IS AS FOLLOWS: To=[1.8(1.1-C) (L).S]/(S%)1/3 C = RUNOFF COEFFICIENT L = OVERLAND TRAVEL DISTANCE IN FEET S = SLOPE IN PERCENT To= TIME IN MINUTES B, DESIGN CRITERIA - FREQUENCY, 100 YEAR STORM. - LAND USE PER SPECIFIC PLAN AND TENTATIVE MAP. - RAIN FALL INTENSITY PER COUNTY OF SAN DIEGO 1993 HYDROLOGY DESIGN MANUAL, C. REFERENCES - COUNTY OF SAN DIEGO 1993, HYDROLOGY MANUAL, - COUNTY OF SAN DIEGO 1992 REGIONAL STANDARD DRAWING. - HAND BOOK OF HYDRAULICS BY BRATER & KING, SIXTH EDITION, .' '- .. APPENDIX A (3. HYDROLOGIC CALCULATIONS) I - ... SAN DIEGO COUNTY RATIONAL-HYDROLOGY PROGRAM PACKAGE Rational Hydrology Study Date: 6- 4-1996 ---------------------------------------------------------------------------- .USER SPECIFIED HYDROLOGY INFORMATION* ---------------------------------------------------------------------------- Rational method hydrology program based on San Diego County Flood Control Division 1985 Hydrology Manual Storm Event(Year) = 100.00 Map data precipitation entered: 6 HOUR, Precipitation(Inches) = 2.700 24 Hour Precipitation (Inches) = 4,500 Adjusted 6 Hour Precipitation (Inches) = 2,700 P61P24 = 60.0 % San Diego Hydrology Manual "C" Values Used Runoff Coefficients by RATIONAL METHOD '1.- Ita +++++++++++++++++++++++++++++++++++++++++++++++++++++++++++++++++++++++++++ Process from Point/Station 1,000 to Point/Station 2,000 *** INITIAL AREA EVALUATION *** Decimal Fraction Soil Group A = .000 Decimal Fraction Soil Group B = ,000 Decimal Fraction Soil Group C = ,000 Decimal Fraction Soil Group D = 1.000 SINGLE F AMIL Y runoff coefficient = .5500 Initial Subarea Flow Dist. = 75,00 Highest Elevation = 252.70 Lowest Elevation = 226.00 Elevation Difference = 26,70 Time of concentration calculated by the Urban Areas overland flow method (APP X-C) = 2.606 Min. TC = [1.8*(Ll-C)*DISTANCE^.5)/(% SLOPE^(1/3)] TC = [1.8*(1.1- .5500)*( 75,OO^.5)/( 35.60^(1/3)])= 100,00 Year Rainfall Intensity (In ,/Hr.) = 10.829 Subarea(Acres) = .11 Subarea Runoff(CFS) = ,66 Total Area(Acres) = ,II Total Runoff(CFS) = .66 TC(MIN) = 2.61 2,606 ... +++++++++++++++++++++++++++++++++++++++++++++++++++++++++++++++++++++++++++ Process from Point/Station 2,000 to Point/Station 3,000 *** TRAPEZOIDAL/RECT. CHANNEL TRAVEL TIME *** Upstream point elevation = 226,00 Downstream point elevation = 225,00 Channel length thru subarea(Feet) = 240,00 Channel base (Feet) = ,00 Slope or "Z" of left channel bank = 10.000 Slope or "Z" of right channel bank = 10.000 Mannings "N" = ,044 Maximum depth of channel (Ft.) = .50 Flow(Q) thru subarea(CFS) = ,66 Upstream point elevation = 226,00 Downstream point elevation = 225,00 Flow length(Ft.) = 240.00 Travel time (Min,) = 6,24 TC(min.) = 8.85 Depth of flow = .32 (Ft.) Average Velocity = ,64 (FUSee.) Channel flow top width = 6.40 (Ft.) '-" I ,.. +++++++++++++++++++++++++++++++++++++++++++++++++++++++++++++++++++++++++++ Process from Point/Station 2,000 to Point/Station 3.000 ... SUBAREA FLOW ADDITION ... 100,00 Year Rainfall Intensity(In,/Hr.) = 4.922 Decimal Fraction Soil Group A = .000 Decimal Fraction Soil Group B = ,000 Decimal Fraction Soil Group C = ,000 Decimal Fraction Soil Group D = 1,000 SINGLE FAMILY runoff coefficient = ,5500 Subarea(Acres) = .39 Subarea Runoff(CFS) = Total Area(Acres) = ,50 Total Runoff(CFS) = TC(MIN) = 8,85 1.06 1.71 '. I ,.. +++++++++++++++++++++++++++++++++++++++++++++++++++++++++++++++++++++++++++ Process from Point/Station 2,000 to Point/Station 3,000 *** CONFLUENCE OF MINOR STREAMS *** --___------n_---__--------------------------------------------------------- 100,00 Year Rainfall Intensity(InJHr.) = 4.922 ALONG THE MAIN STREAM NUMBER: 1 The flow values used for the stream: 1 are: Time of concentration(min.) = 8.85 Rainfall intensity (in./hrl) = 4.92 Total flow area (Acres) = ,50 Total runoff (CFS) at confluence point = 1.71 4'- +++++++++++++++++++++++++++++++++++++++++++++++++++++++++++++++++++++++++++ Process from Point/Station 1.000 to Point/Station 4,000 *** INITIAL AREA EVALUATION *** Decimal Fraction Soil Group A = ,000 Decimal Fraction Soil Group B = ,000 Decimal Fraction Soil Group C = ,000 Decimal Fraction Soil Group D = 1,000 SINGLE FAMILY runoff coefficient = .5500 Initial Subarea Flow Dist. = 75,00 Highest Elevation = 252,70 Lowest Elevation = 226,00 Elevation Difference = 26,70 Time of concentration calculated by the Urban Areas overland flow method (APP X-C) = 2,606 Min. TC = [1.8*(1.1-C)*DISTANCE^.5)/(% SLOPE^(l/3)] TC = [1.8*(1.1- ,5500)*( 75.00^.5)/( 35.60^(l/3)])= 100,00 Year Rainfall Intensity(In,/Hr,) = 10.829 Subarea(Acres) = ,11 Subarea Runoff(CFS) = Total Area(Acres) = ,II Total Runoff(CFS) = TC(MIN) = 2,61 2,606 ,66 ,66 . - ++++++++++++111111+++++++++++++++++++++++++++++++++++++++++++++++++++++++++ Process from Point/Station 4,000 to Point/Station 3.000 *** TRAPEZOIDAL/RECT, CHANNEL TRAVEL TIME *** Upstream point elevation = 226,00 Downstream point elevation = 225.00 Channel length thru subarea (Feet) = 250,00 Channel base(Feet) = .00 Slope or "Z" of left channel bank = 10,000 Slope or "Z" of right channel bank = 10,000 Mannings "N" = ,044 Maximum depth of channel (pt) = .50 Flow(Q) thru subarea(CFS) = ,66 Upstream point elevation = 226,00 Downstream point elevation = 225,00 Flow length(Ft.) = 250.00 Travel time (Min,) = 6,60 TC(min,) = 9,21 Depth of flow = ,32 (Ft) Average Velocity = .63 (Ft/Sec,) Channel flow top width = 6,45 (Ft) ~ . .. +++++++++++++++++++++++++++++++++++++++++++++++++++++++++++++++++++++++++++ Process from Point/Station 4,000 to Point/Station 3,000 ... SUBAREA FLOW ADDITION ... 100,00 Year Rainfall Intensity(In./Hr.) = 4.797 Decimal Fraction Soil Group A = .000 Decimal Fraction Soil Group B = ,000 Decimal Fraction Soil Group C = .000 Decimal Fraction Soil Group D = 1.000 SINGLE FAMILY runoff coefficient = .5500 Subarea(Acres) = .43 Subarea Runoff(CFS) = Total Area(Acres) = ,54 Total Runoff(CFS) = TC(MIN) = 9.21 1.13 1.79 .... +++++++++++++++++++++++++++++++++++++++++++++++++++++++++++++++++++++++++++ Process from Point/Station 4.000 to Point/Station 3,000 *** CONFLUENCE OF MINOR STREAMS *** *** Compute Various Confluenced Flow Values *** ____n_-n-____-____-n_-n_--___--------------------------______nnnnn- 100,00 Year Rainfall Intensity(In./Hr.) = 4,797 ALONG THE MAIN STREAM NUMBER: 1 The flow values used for the stream: 2 are: Time of concentration(min,) = 9,21 Rainfall intensity (in,/hrl) = 4,80 Total flow area (Acres) = ,54 Total runoff (CFS) at confluence point = 1.79 Confluence information: Stream runoff Time Intensity Number (CFS) (min,) (inch/hour) ___nn--__________n____--_-------------------------------------_--____n_- I 1.71 2 1.79 QSMX(l) = + 1,000* 1,000* +1.000* ,961* 3.431 QSMX(2) = + ,975* 1.000* + 1,000* 1,000* 3.457 8.85 9,21 4,922 4,797 1.7) 1.8) 1.7) 1.8) Rainfall intensity and time of concentration used for 2 streams, Individual stream flow values are: 1.71 1.79 Possible confluenced flow values are: 3.43 3.46 Individual Stream Area values are: ,50 ,54 Computed confluence estimates are: Runoff(CFS) = 3.46 Time(min,) = 9.211 Total main stream study area (Acres) = 1.04 .... -- +++++++111111++++++++++++++++++++++++++++++++++++++++++++++++++++++++++++++ Process from Point/Station 3.000 to Point/Station 5,000 ... PIPEFLOW TIME (USER SPECIFIED SIZE) . *. Upstream point elevation = 218,00 Downstream point elevation = 201,00 Flow length(Ft.) = 62,00 Mannings N = .013 No, of pipes = 1 Required pipe flow (CFS) = Given pipe size (In,) = 8.00 Calculated Individual Pipe flow (CFS) = Nonnal flow depth in pipe = 4.22 (In,) Flow top width inside pipe = 7.99 (In,) Velocity = 18,531 (Ft/S) Travel time (Min,) = ,06 TC(min.) = 9.27 3.46 3.46 End of computations.. , TOT AL STUDY AREA (ACRES) = 1.04 . , ,- APPENDIX B ( 4 , HYDROLOGY MAP) .~ , ,- A=O.\\~G (XIST! rASa !.!)'! ~ 200 ~ÃEX ~ Ã?~ 24' ReI' I'ÐI ., l.. (5. APPENDIX C TABLES AND CHARTS) .. " ", ì >-- ' ~.. '{ \ Wa.h:r.sht:d D,;'VI d~ "\ --- --- - ~ ----J ¡ /~- ~ \, """ ~\L)e51 ~ -'-'~..,- ~ "'?-~..,- 1'°': I "--- ~.. /' "-- --- - ./ .....-- -- L Waler.s/;ed Divide H 'E I/~cll'f./e Slope Lliu:. ÛeSiC?l ,~/t?1 /' .; 'II' u'1/ale¡ .s/;~d Ov/í(!. ./\ ~ T" SlíÆO/77 ~ L I I , J?rea. );" :II ¡:?r(!!Q. 'ß. (' \. SAN DIEGO COUNTY DEPARTMENT OF SPECIAL DISTRICT SERVICES '- ',', - - ,--, , - ---~~'J --"--'~'-%i;.$i¡~" -:;: DES I <IN ,MANUA~ ' ,'"}1 ,:,/"!r-Äi?RÖVE~'~'/">:t"'17':~ ~I..¿r rl ,t:: COMPUTATION OF EFFECTIVE SLOPE FOR NATURAL WATERSHEDS ",-', , , APP.ENDI¥ x- F/" : IV-A" ' " .. ' r DATE ,- ' , \ £Glj"tlTION Tc. (II¡L J) .385 Æ. l/m~ 01 coac~/7lrallÌ;)/7 L I L~n911¡ 01 wa./~rsj¡~d It' r £;//I'~r~/7c4! in 4'14'va.Ji.on a./M9 e/l'~cI/y~ slo.o.:: 1//7~ (.set! I?~M¡X f.ß) h. L C M/I~.5 ,r.::~1 #ov-"s 1r1//7v!es 4 ¿4a ,. h' ..:. . ~- F.:: .::1 S"ooo ( tlot)o 3000 looo ' ... ItJtJO -" 900 BOO '100 GiJO "- " - St){) "- IO{) ~ ,,~ "-<:- ~ "- "- " "- "- "- " / 3ðO 200 / Ot) So (t) 30 NOTE ~ --............. .air"" ...... --- ----::l aFaR NATURAL WATERSHEDSj ZLJ I ADD TEN MINUTES T°:J~ UCOMPUTED TIME OF CON- CENTRATION. --------- -------- ILJ 5 'H SAN DI EGO COUNTY DEPARTMENT OF SPEC! AL DISTRICT SERVICES DESIGN MANUAL, '", -~, ,.:' APP'ROVED ,3./I./~~'~. , .) ~~¡$1~.~~~~~~£~~;~;;', ::,;ir~ " ' . " JtJ{){) ' 4~{) 20 " /8 - .3 cot) "- IS " I<t " ¿oat) " 12 18/)0 "- /GOo I{J It;f/)t) 9 12/)£) 8 lOOt) 7 9at) 80t) ¡; ?c/t) ¡j{)t) 5' - 5'O¿J 4- 4{)O .5 300 It) 5 05 2tJO t r r t r 3 18tJ 2 1;:0 / £0 j-tJ ~O ¡ ! I 7é NOMOGRAPH FOR DETERM I NATION .,OF TIME OF CONCENTRATION (Te) : :FŒt NAT~ WATERSHEDS ,DATE /2./II~ 1:' x;-l.f~¿ L ,.' ~ 1 . to_, .. Average Values of Roughness Coefficient (Manning's n) Type of Waterway Roughness Coefficient (n) 1. Closed Conduits (1) Steel (not lined) Cast Iron Aluminum Corrugated Metal Corrugated Metal Corrugated ~let al Corrugated ¡'¡etal Concrete RCP Clay (sewer) Asbestos Cement~ Pyc- Dr~in Tile (terra cotta) Cast-in-p1ace Pipe Reinforced Concrete Box 0,015 0,015 .021 0.024 . 0.021 0.018 0,012 0.012 0.013 O. OIl O.OlS 0,015 0.014 (not lined3 (2) (smooth asphalt quarterlining) (2) (smooth asphalt half lining) (smooth asphalt full lining) 2. Open Channels (1) a. Unlined Clay Loam Sand 0.023 0.020 b. Revetted Gravel Rock Pipe' and Wire Sacked Concrete 0.030 0.0":0 0.025 0.025 c. Lined Co~crete (poured) Air~ Blown Mortar (3) Asphaltic Concrete or Bituminous Plant Mix 0.014 0.016 0.018 d, Veg~tated (5) Grass lined, maintained Gra~s and Weeds Grass lined with concrete low flow channel .035 .045 .032 3. Pavement and Gu1ters (1) Concrete Bituminous (plant-mixed) 0.015 0.016 . ' I: i' ¡ I I r f ! I t J ¡: '. (' i' £, I .~~ -11,. if'" .-J,:i'., ' ... ';"" L'.~:-":" .;~' ,." 8'\: - TABLE 2 RUNOFF COEFFICIENTS (PAT! OW>.L METHOD) DEVELOPED AREAS (URBANl C oe f f j c ¡en t~.i Soi J Group (1) Land Use A B C D Residential: Single Family .40 .45 .50 .55 Multi-Units .45 .50 .60 .70 Mobi le homes ,45 .50 .55 .65 Rural (lot s greater than 1/2 acre) .30 .35 .40 .45 Corrrrerci al (2) .70 .75 .80 .85 80% Impervious Industrial (2) .80 .85 ,90 .95 90"10 1 mpe rv i ou s NOTES: (l)Soil Group m~DS are available at the offices of the Department of Public ~orks. (2)Where actual conditions deviate significantly from the tabulated impervious- ness values of 80"10 or 9œ~, the values given for coefficient C, may be revised by multiplying 80% or 90% by the ratio of actual imperviousness to the tabulated 'imperviousness. However, in no case shall the final coefficie!'\t be less than 0.50. For example: Consider commercial property on D soi I,group. Actual imperviousness ... 50% I J l ¡ I I , I r I I i ì t ¡ ¡ : f ! i ¡ ¡ f f ¡: Tabu1ated imperviousness - 8~1o Revised C = 50 x 0.85 - 0.53 80 ( IV-A-g t, APPENDIX IX-B ~ /1 . Rev. 5/81 :,' . ,/ : ,.-, f 'II .. HIGH\\'A Y DESIGN MANUAl 810-11 ,¿, . JI- January, 1987 (' Figure 816.6A Overland Time of Concentration Curves 1000 I'iiliil 1'!11111 ìl'Jj.",'i'/lljl~lì,1111:/1 I ,i I I' IT¡~I'tr::TTi~-i Till~i TrT -'I: T 1r+i~'7', ~'~~7T I ,. '. I. -h--.', I' J-+-:. I ¡-L,. '_+-+-,' ~....è Il¥J J-1.,~ -~t~. .' ..;',~_J,.. ,,-'--',.1.... ~ _.1_-.'. '. I ' ì. J ". . i, I, " "III'.LuLL-+-l.U" .r'I,I~~',......JI'f; /;.f!,-ì/l' 1'1': , I I ' -=r:::I:J iTT, ()' 1 r=.- ; -i-- L~ y . . t I : ¡ f: ! I 1 I ¡-1-:"'.'¡'¡ "0:;1 .T,~r-',J 'I: if:' '::11, '- ,II/ Ii li_/:/ji/lf,';;;'" 11,!i!,! '!,l.U:/'i/ 1!/,'-T7'i ii/'ll ;:i~ :I';:!.,::: 1:~II)'oi/!.:f;ÂI":..._L~,I_I-~.-&-.-¡1 ;::1 I I'I Ii -""""-~~~-"-~/.f:-t-~- " III II I.'..'." 1.l.ULLL.....l.t),;;~_.f '1__--'-.1.. I: it- i, -H+~. ~ ~;+H~~',¥~~--~: +~,_....!1t, . :.., .....9. ¿,. -,'i-4., I --ri-. I ~ I'I ,ili ,..J'I/'!I ,!,-+-f-~ "'~p=^' "iii, I , ',I, "".' I..I'LJ~-':Í~.'V".' C"-.-'~,,!. ' ili I "lliill'¡I(-CI-r~7C'Vlll .~,,'!I I, ,III,llll/I/-') i 'C',' II: I, ,I I , ,I' 'I I. 'fl I f i , . , II".! I'~I;/I:V 'f III /:'~ II --T-r-M I I I , ~ ,i,ll; 1I'~~',Ii;+-1+1--I+:/'/-./¡ :¡ ':/ lill,I" 'Il/'fi/'.!: '-'-h': i i/ ~,II' ,V~I/II'I'1 -I'~T-i ' /:1 :li,1 il/l,V,['II" 1,'1/,1, li",I!" I'll V-¡,I "1:';'/,1'/ I I I! i I ;I. / I', lll--,-',.L-lj. I .."""~- . ~--'..-.,' , ' ; Y'.D v ' il:!'I! , :¡'/:/ 1,1 IFiT:'/ -~,J:~~TYI II!!, Iii ;I,f ,/ :l /-'-.l~,L ~-- ,."""-""',/11 Ilill' fl' ill fl'l:,"ÎB='.,.. .I\) ,.;Z=iit-P='"., '-,-" I I I I r I : , / I. 1/ II I : j/ --:--, -=-=:..:- I -LJ. I 11,:fl /!!~I/I:'O () "¡,,t- I IIJI/' f¡/-,I"/"'l'-~"/II,'/ I 'll/.t I iÆ'.,1J~(¡r()";;'O/II:L'1 En' ! . ' : ' " I ,'" ' r r1~T' L-'-L-C;O".6*-,!' !--L~: :: :/~ l-fl-V-~/ ~/ I : ! ,~. ' ' ~--'~.,6~:ir¡-~ I I , , i I I ,/ :/ / / /: i' ! :,/ : " I¡-;-::-:" ¡I, _......J 'rJ'-j;;.(, I -:- I I: I I ' . / I ' 1'/ /'" '-;i I ~L ! ~o/",-t-,- i 'il!I/fT '//1/1/.,' /1-/ i/i~I:-O'II.:~ I 'II I '/'/',/1 ViY /,1/1 1'/-' 6°.2"""~ I ! , '1/, ~ I 1 I 1...-': ¿'~ '-!,I~~ ,~,,-Oy! i ' : I II, '/ h i/'/'JI// /' ~'/¡:'./""I"I I I! j/ I // I I, V, '" I :/' I I v' ~...L..4. . , '. 1 0 t:J;;; i:/'-1~,A/'IIIIV/ /1/1 I.Y":~'~;T-O~I 1/:/ (11"/ 111:/' -,/,;/ IV- .III-~'Il .,,/,Y 11'/ V./ I./( '.....-': ':iil~',1 100T "J-', 1 I 1 v' /'. r/'./ : ./". : ~ ~~-. I n).~ II :,/i./v,y,I~il.:..--íIII' i'llil:t~IIì ,1111 "",/,,/,I!.--'íJ,../,, I..,....,-, 'II~'I 'II ,I ' ~/ Y I ~ I ~....-.~ < I I I I '. Lh'go,. I , r~y,I""""'-;-I~:, 1;""-; '" ,Ii IIV';::":;';; I ~I I IJ....-r 'i I '....;-ríl I I, 11~095 II -:"'L,...J...-"'.I~!II~,~I!: .;--:-I'I~ I .~ I, ¡"'-,~'~IIII~11 ;, '~--:i III _I -- Ii' - I, ,:, 1 f- ' ,--- I .l.-I:-' I I I I I I l--LlJ...L, ' I I '" , , I I I I: I I I I I I I I ì í r~I:~ I ì I ! II II 11II III I I 1111'~î, 1 I 0 800 .... Cf) ill ill ill l- LL. ::;) Z Z ~ ill 600 80 Z 0 Z -l o:x: ill I-- > (/) <:( 0 cr: 400 60 ~- ...J LJ... W 0 > \ <C UJ \ D: 2 .... I- 0 0 Z 200 4-0 -'" « .t- ...J <1: a: ...J ill 0: > ill 0 > 0 0 20 To = 1.8(1.1-C) (L) 1/2 [~~~1 OO>J 1 /3 Where: C = Runoff Coefficient L = Overland Travel Distance in feet S = Slope in ft.lft, To ::: Time. in minutes . . . . . ¡ (, '-. ,", ",',',q", "',,' '"." ",,',00 ',' c~rY OF SAN DIEGO DEPARTMENT OF SANITATION & FLOOD CONTROL . I '¡ 451 ""\ 301 ,"" 151 .~, .338 " ,',. .!t!I.: ItSI ~~ . f r- --. ,-'- U,S. DEPARTMENlr OF Cm.1MERCE Pur-f'" br ~ tfATIOHAL OCt:A"IC AHO ^T:~OS"II¡': UC ^O}U..-I:lT"ATION 'P&C'AL STUDICS U~M CII. Ot'tïCI!: Or' lI'iol~oLnGY. N^TlU;>I^L Irl:ATIII::R SERVICE 30' ... .... . >- . w " """ .,,;, ." 11 ¡:" I, 'j . )0' I r¡ , 117" 116- '¡Ii' )n' I~ ' -----,--,--,-,-,--_._---,,_.----~--~.. ,'---~.~' --,,'~-~'-' ,-- --- -, ,./ , "'f' .-,' , , "', ~ ~TY OF SAN DIEGO D~ RTMENT OF SANITATION & FLOOD COUTROL ,45' 30' .. - 33. ) 45' .---,...-, ..,-. --- - -..... ( , I 15' I I CI t «I 1-.- " i 'e u.s. DEP^RnIE~lr OF Co:\tMERCE Pr~p"f'd br 30' J l ' ~ ) 18' 16' 30' 116- fCATIO:fAL OCEANIC AND ^T\ OSPIII::HrC AD~:1;-(15TRAT'ON ' "'ICIAL ITVO'i!:J UR^~C;U. OFfiCE OF lei IIROLOGY. NATIONAL ""EAnu::a SI'.R\'1Cl: 30' 151 15' " ", '"",= ". ',,00 ,- __00 'J .---- '---'- --., -.,. . ,-,,--,,--------,-~,--'-"""~-~--'~-"~'--'-"---~~"---~' -".- --'.""~~--~' "-'?,"" ,.._~"." - "-.-' . ' \ ,." JNTENSITY-DUN\TION OESIGtJ. CH^RT ~ . J ' , , 5 ,....-" ,--,., ~-~,oo- 00-- .., -,~-,--------"-,-,--,-,---,~-,~~,~~,~,,,-,~---,,--"-~'--",-"--~=-"-~-,=",~~-~-""""-",,,,,,,,~---,~ "-"'--r"'_,.,..-"-" - ",,' --',--c<-~-""" NORTH COUNTY COMPACTION ENGINEERING, INC. April 10, 1996 Project No. CE-5213 Al Mayo 1772 Kettering Street Irvine, CA 92714 Subject: \ ? J L~ l~ \~ u ~I l~~ I'D' ! Ilj ,.., " L:_) >-I' 'JUN 101996 ENGINEERING SEfW\CES CITY OF ENC!N!TAS Consolidation of Fill Soils Proposed Single Family Dwelling Lot #22 of Wildflower Estates Encinitas, California Dear Mr. Mayo: ,In response to the City's request, we are addressing herein settlement characteristics of the prevailing on-site soils to be utilized as fill material for partial construction of the proposed building pad. Please note the City Ordinance 23.24.460, I states: , 1. Fill Depths. Building structures upon fill materials in excess of 10 feet in depth shall only be allowed where all reasonable use of the property is otherwise precluded and then only upon attainment of the ul timate consolidation of the fill material achieved through a state of the art soils investigation, a settlement monitoring program and surcharging of the fill material with an appropriate overburden of soil.' During our soils investigation of December 20, 1995, Consolidation Tests were performed on the prevailing on-site soils in accordance with ASTM D-2435. Test results indicate that estimated settlement of on-site soils would be within tolerable limits with the proposed 23 foot fill depth. However, please note that the proposed on-site excavation is approximately 2700 cubic yards and to complete the building pad as planned, it will require approximately 13,000 yards of imported fill material. Due to the unknown settlement characteristics of imported materials at the time, estimated settlement of fill soils' cannot be accurately calculated. Therefore, upon' further consolidation testing of soils to be imported, our firm will determine at that time whether or not a settlement monitoring program will be required upon completion of grading. P.O. BOX 302002 . ESCONDIDO, CA 92030 (619) 480-1116 -' - NORTH COUNTY COMPACTION ENGINEERING, INC. April 10. 1996 Project No. CE-5213 Page 2 We should be contacted to inspect and test imported soils prior to hauling them on-site to assure they will be sui table for the proposed construction. If you have any questions, please do not hesitate to contact us. This opportunity to be of service is sincerely appreciated. Respectfully submitted, 4 North County COMPACTION ENGINEERING. INC. ~r-~ Ronald K. Adams President RKA:kla cc: (3 ) Submitted