Loading...
EnvirOmega Consultants Acoustical Study r. EnvirOmega Consultants (t 16732 Palmero Drive San Diego, California 92128 (619) 676-0046 April 271999 Don Hubbard Contracting P.O. Box 230577 Encinitas, California 92023-0577 • •j Attention: Mr. Don Hubbard Subject: Project Update A Don Hubbard Contracting Facility 46 Encinitas Boulevard Encinitas, California 92024 i Dear Mr. Hubbard: On December 3, 1998, a representative of EnvirOmega Consultants (EOC) observed the removal of two underground storage tanks (USTs) from your site located at 46 Encinitas Boulevard in Encinitas, California. Each 1,000 gallon UST (one unleaded gasoline and one diesel) was removed from a separate excavation with two soil samples collected from each excavation. While neither soil sample collected from the excavation created by the removal of the unleaded gasoline UST contained detectable concentrations of total petroleum hydrocarbons (TPH), soil staining and hydrocarbon odors were noted in the excavation. Of the two soil samples collected from the excavation created by the removal of the diesel UST, one sample contained 3,200 milligrams per kilogram of TPH-diesel and the other did not contain a detectable concentration of TPH. The regulator observing the removal of the USTs noted the presence of a "small amount of diesel floating on surface of groundwater' in the excavation created by the removal of the diesel UST. Following the removal of the USTs and the departure of the regulator from the site, in accordance with an approved "post tank removal work plan", EOC assisted with the excavation of approximately 150 cubic yards of clean and contaminated soil from the excavation created by the removal of the gasoline UST. During the excavation of the soil, it became apparent that the soil removal should be discontinued and that the excavations should be backfilled. This conclusion was based primarily on the fact that hydrocarbon odors continued to emanate from the excavation and some soil staining was still apparent on the excavation sidewalls. It should be noted that while soil removal was discontinued, the observed soil conditions did not necessarily suggest extensive contamination. Instead, EOC, with your concurrence, concluded that to avoid the possibility of removing excessive amounts of soil, soil removal should be stopped and replaced with an assessment effort, including soil borings. To address the subsurface conditions remaining in the areas of the removed USTs, EOC is preparing a work plan proposing the excavation of several borings and the possible installation of several groundwater monitoring wells. The County of San Diego Site Assessment and Mitigation (SAM) Program of the Department of Environmental Health requires the assessment Mr. Don Hubbard April 27, 1999 Page 2 of the extent of petroleum hydrocarbon impact to the soil and groundwater at sites where unauthorized releases have occurred and may require the mitigation of those impacts. Currently, we understand that both UST excavations have been filled to the ground surface with soil and that the soil removed from the gasoline UST excavation has been transported to Candelaria Environmental in Anza, California for disposal and treatment. We will submit a work plan proposing the advancement of soil borings and the collection of soil and groundwater samples to SAM within the next week and should receive approval of the work plan from SAM within four weeks of it's submission. Since you have been accepted into the State Cleanup Fund, costs to perform the assessment work should be approved by the Fund prior to the performance of the work. The preapproval should take no more than two weeks. Following preapproval, a well permit application will be submitted to SAM with the fieldwork being completed approximately three weeks later. Note that SAM requires a wait of two weeks from the submittal of a well permit application before that the fieldwork can be completed. The fieldwork should be completed within a few days with a report submitted to SAM with four weeks of the completion of the field activities. Depending on the results obtained from the` completion of the field activities, "site closure" could take as little as three months following the submittal of the report but may extend up to as much as several years. SAM typically requires one year of groundwater monitoring following the observation of contaminant impact to the groundwater, but in the event that additional soil and groundwater impact requiring mitigation is encountered, the time to site closure will likely be extended beyond one year. The time frame to site closure can be much more accurately estimated following the completion of the assessment effort. We have attempted to provide a reasonable estimate of the activities and time required to obtain closure for your site. If you have any questions or require additional explanation, please call me at 619-676-0046. Sincerely, David A. Eminhizer Environmental Scientist/Owner EnvirOmega Consultants cc: Mr. Bill Brown, Attorney for City of Encinitas